All project updates
5 April 2024
A Decision Letter (PDF, 199KB) and Amendment Order (PDF, 78KB) have been issued by the Department of Energy Security and Net Zero to make a change that is not material to the Immingham Open Cycle Gas Turbine Order 2020.
21 March 2024
The Applicant has provided their Consultation and Publicity Statement (PDF, 165KB). The Secretary of State previously issued a letter (PDF, 158KB) to confirm those parties that the Applicant should consult.
12 February 2024
Representations received in response to the application for a non-material change to the Made VPI Immingham OCGT Development Consent Order VPI Immingham OCGT - Project Information have been published.
22 December 2023
The non-material change 2 documents have been published.
The deadline for receipt of representations is 1st February 2024.
If you wish to make a representation, this should be emailed to ImminghamOCGT@planninginspectorate.gov.uk or posted to:
Immingham OCGT Case Team - National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN
8 February 2023
22 December 2022
30 November 2022
14 October 2022
If you wish to make a representation, this should be emailed to ImminghamOCGT@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol
BS1 6PN
The deadline for receipt of representations is 11:59pm on Thursday 17 November 2022
17 May 2021
Correction Notice (PDF, 160 KB); and Correction Order (PDF, 57 KB)
7 August 2020
Planning Inspectorate Notification of Consent Letter
Secretary of State Decision Letter
Examining Authority Recommendation Report
Development Consent Order as made by the Secretary of State
Habitats Regulation Assessment
Regulation 31 Notice
Post-Examination Submissions
7 August 2020
21 July 2020
6 July 2020
The deadline for the consultation responses is 23:59 on 20 July 2020.
30 June 2020
10 June 2020
The deadline for the consultation responses is 23:59 on 26 June 2020.
11 May 2020
The Examining Authority issued a Recommendation Report to the Secretary of State on 7 May 2020. The Secretary of State has three months in which to issue a decision. The decision letter and the Recommendation Report will be published on this project page once a decision has been made.
7 May 2020
10 February 2020
8 February 2020
7 February 2020
24 January 2020
10 January 2020
3 January 2020
13 December 2019
2 December 2019
26 November 2019
19 November 2019
5 November 2019
24 October 2019
11 October 2019
7 October 2019
25 September 2019
The Accompanied Site Inspection Itinerary has also been published.
16 September 2019
13 September 2019
30 August 2019
15 August 2019
Procedural decision following Preliminary Meeting.
8 August 2019
8 August 2019
10 July 2019
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
8 July 2019
25 June 2019
16 May 2019
9 May 2019
18 April 2019
If the application is accepted for examination anyone interested in the application will be able to register and express their views during the relevant representation stage and the subsequent examination.
15 April 2019
The applicant has agreed that all application documents can be published as soon as practicable to help everyone become familiar with the detail of what is being proposed in this application. The Planning Inspectorate will therefore make the application documents available as soon as practicable.
This provision is solely for the purpose of allowing more time to all those who wish to become familiar with the detail of what is being proposed ahead of the relevant representation period without lengthening the overall time required for the application process. There will be no opportunity at this stage to make comments on the application. However, if the application is accepted anyone interested in the application will be able to register and express their views during the relevant representation stage and the subsequent examination