Representation by Anglian Water (Anglian Water)

Date submitted
15 November 2022
Submitted by
Other statutory consultees

Anglian Water is the statutory undertaker for water services in the application area. Consultation with the Applicant has taken place regarding several matters, critically on Protective Provisions and the Discharge of Requirements for a Drainage Strategy. We note that Anglian Water's requirement to be a consultee to the discharge of the requirement regarding the drainage strategy is set out in Schedule 2, Requirement 8 and confirm that we are content with the wording in the Draft DCO. The Protective Provisions for Anglian Water are set out in Schedule 11, Part 7 and these were agreed with Anglian Water prior to the submission of the application for DCO. Anglian Water is working with the Applicant in respect of a Statement of Common Ground and look forward to being able to submit this to the Examining Authority shortly.