West Burton Solar Project Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 8 November 2023

Caeodd yr archwiliad ar 8 May 2024

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

24 Awst 2023 - Procedural Deadline A

Caeedig

Procedural Deadline A

Deadline for receipt by the ExA of:

  • Written submissions on the Examination Procedure, including the draft Examination Timetable
  • Requests to be heard orally at the Preliminary Meeting
  • Requests to be heard at Open Floor Hearing 1

7 Medi 2023 - Preliminary Meeting

Caeedig

Preliminary Meeting

31 Hydref 2023 - Procedural Deadline B

Caeedig

Procedural Deadline B

Deadline for receipt by the ExA of:

  • Written submissions on revised draft Examination Timetable
  • Requests to be heard orally at the Preliminary Meeting
  • Requests to be heard at Open Floor Hearing 1 (Please respond even if you previously requested to be heard at the postponed OFH1)
  • Requests to be heard at Issue Specific Hearing 1

8 Tachwedd 2023 - resumed Preliminary Meeting

Caeedig

resumed Preliminary Meeting

8 Tachwedd 2023 - Open Floor Hearing

Caeedig

Open Floor Hearing 1

9 Tachwedd 2023 - Issue Specific Hearing 1

Caeedig

Issue Specific Hearing 1 on scope of Proposed development; Need, Site Selection and Alternatives; and Environmental Matters

24 Tachwedd 2023 - Deadline 1

Caeedig

Deadline 1

For receipt by the ExA of:

  • Statements of Common Ground requested by the ExA
  • Comments on Relevant Representations (RR)
  • Summaries of all RR exceeding 1500 words
  • Written summaries of oral submissions made at Open Floor Hearing 1 held on 8 November 2023
  • Notification by Statutory Parties of their wish to be considered as an Interested Party (IP) by the ExA
  • Applicant’s draft itinerary for a Site Inspection
  • Requests to be heard by interested parties at a further Open Floor Hearing
  • Requests by Affected Persons (defined in section 59(4) of the Planning Act 2008) to be heard at a Compulsory Acquisition Hearing
  • Suggested locations for site inspections (Accompanied or Unaccompanied), including the reason for nomination, issues to be observed and whether the location(s) require access to private land
  • Applicant’s updated documents – clean and tracked version showing changes since the last submitted versions of:
  • Draft Development Consent Order
  • Explanatory Memorandum
  • Book of Reference
  • Statement of Reasons
  • Report on the interrelationships with other National Infrastructure Projects
  • Schedule of progress regarding objections and agreements in relation to Compulsory Acquisition, Temporary Possession, other land rights and blight
  • Schedule of progress regarding Protective Provisions and Statutory Undertakers
  • Schedule of the latest versions of the Applicant’s submitted documents and documents to be certified
  • Schedule of Progress towards securing other consents
  • Any further information requested by ExA for this deadline

7 Rhagfyr 2023 - Deadline 1A

Caeedig

Deadline 1A

For receipt by the ExA of:

  • Local Impact Reports from Local Authorities
  • Written Representations (WR)
  • Summary of all WRs exceeding 1500 words
  • Comments on any Additional Submissions made after the close of the Relevant Representation period.

15 Rhagfyr 2023 - Publication by the Examining Authority (ExA)

Caeedig

Publication by the ExA of:

  • First Written Questions (if required)

3 Ionawr 2024 - Deadline 2

Caeedig

Deadline 2

For receipt by the ExA of:

  • Comments on any submissions received by Deadline 1
  • Updated Statements of Common Ground in clear and tracked changes versions
  • Comments on the Applicant’s draft itinerary for the Site Inspection
  • Applicant’s updated documents – clean and tracked version showing changes since the last submitted versions of:
  • Draft Development Consent Order
  • Explanatory Memorandum
  • Book of Reference
  • Statement of Reasons
  • Report on the interrelationships with other National Infrastructure Projects
  • Schedule of progress regarding objections and agreements in relation to Compulsory Acquisition, Temporary Possession, other land rights and blight
  • Schedule of progress regarding Protective Provisions and Statutory Undertakers
  • Schedule of the latest versions of the Applicant’s submitted documents and documents to be certified
  • Schedule of Progress towards securing other consents
  • Any further information requested by ExA for this deadline

9 Ionawr 2024 - Deadline 3

Caeedig

Deadline 3

For receipt by the ExA of:

  • Responses to the ExA’s First Written Questions

22 Ionawr 2024 - Weeks reserved for Hearings and Site Inspections

Caeedig

Hearings 23 and 24 January 2024:

  • Issue Specific Hearing 2 on the draft Development Consent Order (ISH2) - Tuesday 23 January 2024

  • Open Floor Hearing 2 (OFH2) - Wednesday 24 January 2024

5 Chwefror 2024 - Week reserved for hearings

Caeedig

Hearings 6 - 9 February 2024:

  • Compulsory Acquisition Hearing 1 (CAH1) - Tuesday 6 February 2024

  • Issue Specific Hearing 3 on Environmental Matters (ISH3) - Wednesday 7 February 2024

  • Issue Specific Hearing 4 on Environmental Matters (ISH4) - Thursday 8 February 2024

  • Morning of Friday 9 February reserved in case ISH4 Thursday 8 February over-runs

6 Chwefror 2024 - Compulsory Acquisition Hearing

Caeedig

Compulsory Acquisition Hearing (CAH1)

7 Chwefror 2024 - Issue Specific Hearing 3

Caeedig

Issue Specific Hearing 3 (ISH3) on Environmental Matters

8 Chwefror 2024 - Issue Specific Hearing 4

Caeedig

Issue Specific Hearing 4 (ISH4) on Environmental Matters

28 Chwefror 2024 - Deadline 4

Caeedig

Deadline 4

For receipt by the ExA of:

  • Comments on any submissions received by Deadlines 2 and 3
  • Updated Statements of Common Ground in clean and tracked change versions
  • Written summaries of oral submissions made at hearings held w/c 22 January and w/c 5 February 2024 (if required)
  • Updated Applicant’s documents – clean version and version showing tracked changes since the last submitted versions of:
  • Draft Development Consent Order
  • Explanatory Memorandum
  • Book of Reference
  • Statement of Reasons
  • Report on the interrelationships with other National Infrastructure Projects
  • Schedule of progress regarding objections and agreements in relation to Compulsory Acquisition, Temporary Possession, other land rights and blight
  • Schedule of progress regarding Protective Provisions and Statutory Undertakers
  • Schedule of the latest versions of the Applicant’s submitted documents and documents to be certified
  • Schedule of Progress towards securing other consents
  • Any further information requested by ExA for this deadline

13 Mawrth 2024 - Issue Specific Hearing 5

Caeedig

Issue Specific Hearing 5 (ISH5) Wednesday 13 March 2024 on postponed matters from ISH3 Wednesday 7 February 2024 and ISH4 Thursday 8 February 2024.

The morning of Thursday 14 March 2024 is also reserved in the event that ISH5 on Wednesday 13 March 2024 over-runs

15 Mawrth 2024 - Deadline 4A

Caeedig

Closing date for CA Regulations RRs

Deadline 4A

Deadline for receipt by the ExA of:

  • CA Regulations Written Representations (CA Regulations WRs) relating to the effect of the change requests.
  • Summaries of any CA Regulations WRs that exceed 1500 words.
  • Any further information requested by the ExA under Rule 17 of the EPR.

18 Mawrth 2024 - Deadline 4B

Caeedig

Deadline 4B

For receipt by the Examining Authority of

  • Requests from any additional Interested Parties and any additional Affected Persons to speak at a further Open Floor Hearing

  • Requests from any additional Interested Parties and any additional Affected Persons to speak at a further Issue Specific Hearing

  • Requests from any additional Interested Parties and any additional Affected Persons to speak at a Compulsory Acquisition Hearing

19 Mawrth 2024 - Publication by the Examining Authority

Caeedig

Publication by the ExA of:

  • Second Written Questions (if required)
  • Report on the Implications for European Sites (if required)

11 Ebrill 2024 - Deadline 5

Caeedig

Deadline 5

For receipt by the ExA of:

  • Comments on any submissions received by Deadline 4
  • Any further information requested by ExA
  • Responses to the ExAs Second Written Questions
  • Comments on submissions for Deadline 4A

19 Ebrill 2024 - Publication by the ExA

Caeedig

Publication of:

  • The ExA’s commentary on, or schedule of changes to, the draft Development Consent Order (if required)

23 Ebrill 2024 - Additional Hearings

Caeedig

Additional hearings Tuesday 23 April 2024:

Issue Specific Hearing 6 Compulsory Acquisition Hearing 2 Open Floor Hearing 3

30 Ebrill 2024 - Deadline 6

Caeedig

Deadline 6

For receipt by the ExA of:

  • Comments on any submissions received by Deadline 5

  • Comments on ExA’s commentary on, or schedule of changes to, the dDCO (if required)

  • Final Statements of Common Ground in clear and tracked changes versions

  • Updated Applicant’s final documents – clean version and version showing tracked changes since the last submitted versions of:

  • Report on the interrelationships with other National Infrastructure Projects

  • Schedule of progress regarding objections and agreements in relation to Compulsory Acquisition, Temporary Possession, other land rights and blight

  • Schedule of progress regarding Protective Provisions and Statutory Undertakers

  • Schedule of the latest versions of the Applicant’s submitted documents and documents to be certified

  • Schedule of Progress towards securing other consents

  • Draft Development Consent Order

  • Explanatory Memorandum

  • Book of Reference

  • Statement of Reasons

  • Written summary of oral submissions at hearings held on 22 and 23 April 2024 (if required)

  • Any further information requested by ExA

8 Mai 2024 - Deadline 7

Caeedig

Deadline 7

For receipt by the ExA of:

  • Summary statements from parties regarding matters that they have previously raised during the Examination that have not been resolved to their satisfaction
  • Comments on any submissions received by Deadline 6
  • Any other information requested by the ExA for this deadline

8 Mai 2024 - End of Examination

Caeedig

The ExA is under a duty to complete the Examination of the application by the end of the period of six months