16 Ionawr 2025 - Deadline 5
AgorDeadline 5
For receipt by the Examining Authority of:
- Responses to ExQ2 (if required)
- Comments on any other submissions received at Deadline 4
- Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
6 Chwefror 2025 - REIS and dDCO commentary or schedule of changes publication
Publication by the Examining Authority of:
- Report on the Implications for European Sites (RIES) and any associated questions (if required)
- Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if required)
10 Chwefror 2025 - Hearings during week commencing 10 February 2024
Reserve dates for:
- Further Hearings (if required)
27 Chwefror 2025 - Deadline 6
Deadline 6
For receipt by the Examining Authority of:
- Post-hearing submissions including written submissions of oral cases (if applicable)
- Comments on responses to ExQ2 (if provided)
- Comments on the RIES (if provided)
- Comments on the Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if provided)
- Finalised Statements of Common Ground
- Final Statement of Commonality and Close of Examination Progress Tracker
- Applicant’s Closing Statement with summary of areas of disagreement
- Closing Statements from Interested Parties regarding matters that they have previously raised during the Examination and have not been resolved to their satisfaction (if desired)
- Final Report on interrelationship with other infrastructure projects
- Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report
- Final Guide to the Application
- Comments on any further information/ submissions received by Deadline 5
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
10 Mawrth 2025 - Deadline 7
Deadline 7
For receipt by the Examining Authority of:
- Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 (if required)
10 Mawrth 2025 - Close of Examination
The Examining Authority is under a duty to complete the Examination of the application by the end of the period of six months.
Please note that the Examining Authority may close the Examination before the end of the six-month period if it is satisfied that all relevant matters have been addressed and discussed.