Morgan Offshore Wind Project Generation Assets Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 10 September 2024

Mae disgwyl i'r archwiliad gau 10 March 2025

Dweud eich dweud

Terfynau amser a digwyddiadau i ddod

16 Ionawr 2025 - Deadline 5

Agor

Deadline 5

For receipt by the Examining Authority of:

  • Responses to ExQ2 (if required)
  • Comments on any other submissions received at Deadline 4
  • Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

6 Chwefror 2025 - REIS and dDCO commentary or schedule of changes publication

Publication by the Examining Authority of:

  • Report on the Implications for European Sites (RIES) and any associated questions (if required)
  • Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if required)

10 Chwefror 2025 - Hearings during week commencing 10 February 2024

Reserve dates for:

  • Further Hearings (if required)

27 Chwefror 2025 - Deadline 6

Deadline 6

For receipt by the Examining Authority of:

  • Post-hearing submissions including written submissions of oral cases (if applicable)
  • Comments on responses to ExQ2 (if provided)
  • Comments on the RIES (if provided)
  • Comments on the Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if provided)
  • Finalised Statements of Common Ground
  • Final Statement of Commonality and Close of Examination Progress Tracker
  • Applicant’s Closing Statement with summary of areas of disagreement
  • Closing Statements from Interested Parties regarding matters that they have previously raised during the Examination and have not been resolved to their satisfaction (if desired)
  • Final Report on interrelationship with other infrastructure projects
  • Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report
  • Final Guide to the Application
  • Comments on any further information/ submissions received by Deadline 5
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

10 Mawrth 2025 - Deadline 7

Deadline 7

For receipt by the Examining Authority of:

  • Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 (if required)

10 Mawrth 2025 - Close of Examination

The Examining Authority is under a duty to complete the Examination of the application by the end of the period of six months.

Please note that the Examining Authority may close the Examination before the end of the six-month period if it is satisfied that all relevant matters have been addressed and discussed.

Terfynau amser a digwyddiadau blaenorol

27 Awst 2024 - Pre-Exam Procedural Deadline

Caeedig

Deadline for receipt by the ExA of:

  • Written submissions on the Examination Procedure, including any submissions about the draft Examination Timetable
  • Comments on Relevant Representations (RRs)
  • Summaries of all RRs exceeding 1500 words
  • Submission of Pre-examination Progress Tracker (Appendix G)
  • Requests to be heard orally at the Preliminary Meeting including which agenda items you wish to speak on (Appendix A)
  • Requests to participate in the Issue Specific Hearing on Tuesday 10 September 2024
  • Suggested locations for site inspections for consideration by the ExA, including justification, and whether such locations can be seen from public land or require private access

10 Medi 2024 - Preliminary Meeting

Caeedig

The Preliminary Meeting for the Morgan Offshore Wind Project: Generation Assets Development Consent Order Application is to be held at the Princess Royal Suite, Princess Royal Strand, Aintree Racecourse, Ormskirk Road, Aintree, Liverpool, United Kingdom, L9 5AS and by virtual means using Microsoft Teams. This meeting will commence at 10:00 on Tuesday 10 September 2024.

A livestream is available for this event. Please click on this link to view the livestream for this event.

The recording and the transcript of the Preliminary Meeting are available. View recording and transcript.

10 Medi 2024 - Issue Specific Hearing 1 (ISH1)

Caeedig

ISH1 on the Scope of Development and Interrelationship with other Infrastructure Projects is to be held at the Princess Royal Suite, Princess Royal Strand, Aintree Racecourse, Ormskirk Road, Aintree, Liverpool, United Kingdom, L9 5AS and by virtual means using Microsoft Teams. This hearing will commence at 14:00 on Tuesday 10 September 2024.

A livestream is available for this event. Please click on this link to view the livestream for this event.

Recordings and transcripts of the Issue Specific Hearing 1 are available. View recordings and transcripts.

12 Medi 2024 - Issue of Rule 8 Documentation

Caeedig

Issue by the Examining Authority of:

  • Examination Timetable
  • Any Written Questions deemed necessary arising from ISH1 (if required)

3 Hydref 2024 - Deadline 1

Caeedig

Deadline 1

For receipt by the Examining Authority of:

  • Post-hearing submissions for ISH1, including written submissions of oral cases and comments on any oral submissions put at the hearing
  • Written Representations including summaries if exceeding 1500 words
  • Summaries of all RRs exceeding 1500 words (if not provided at the pre-Examination Procedural Deadline)
  • Responses to RRs (if not provided at the pre-Examination Procedural Deadline)
  • Local Impact Reports from any local authorities and the Isle of Man Government
  • Initial Statements of Common Ground and Statement of Commonality (or as combined with the Progress Tracker)
  • Submission of Report on interrelationship with other infrastructure projects
  • Requests by Interested Parties to be heard at an Open Floor Hearing (OFH)
  • Notification by Statutory Parties of their wish to be considered as an IP by the Examining Authority
  • Notification of wish to have future correspondence received electronically
  • Comments on any further information or additional submissions accepted by the Examining Authority
  • Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

22 Hydref 2024 - Deadline 2

Caeedig

Deadline 2

For receipt by the Examining Authority of:

  • Comments on Written Representations
  • Comments on Local Impact Reports
  • Responses to any written questions arising from ISH1 (if supplied)
  • Applicant’s Progress Tracker and Statement of Commonality
  • Applicant’s first update to the draft Development Consent Order
  • Applicant’s first update to the Guide to the Application
  • Applicant’s draft itinerary for Accompanied Site Inspection (if required)
  • Any other updated documents and statements from the Applicant deemed necessary following responses at Deadline 1
  • Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

29 Hydref 2024 - Publication of the Written Questions (ExQ1)

Caeedig

Publication of the Written Questions (ExQ1)

Publication by the Examining Authority of:

  • Examining Authority's First Written Questions (ExQ1)

Please click on this link to view the Examining Authority's First Written Questions (ExQ1).

12 Tachwedd 2024 - Deadline 3

Caeedig

Deadline 3

For receipt by the Examining Authority of:

  • Responses to ExQ1
  • Comments on the Applicant’s first update to the draft Development Consent Order
  • Comments on the progress tracker or Statement of Commonality
  • Comments on the Applicant’s draft itinerary for the Accompanied Site Inspection (if required)
  • Notification of wish to attend the Accompanied Site Inspection (if required)
  • Comments on any other submissions received at Deadline 2
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

19 Tachwedd 2024 - Final ASI itinerary publication

Caeedig

Publication by the Examining Authority of:

  • Final itinerary for the Accompanied Site Inspection (if required)- Not required

An Accompanied Site Inspection will not held for this case during the week commencing Monday 25 November 2024 and therefore no final itinerary will be published on Tuesday 19 November 2024.

26 Tachwedd 2024 - Issue Specific Hearing 2 on Environmental Matters and Other Sea Users (Day 1)

Caeedig

Issue Specific Hearing 2 on Environmental Matters and Other Sea Users (Day 1)

Blended event held at Merchant Suite, Delta Hotels Liverpool City Centre, One Queen Square, Liverpool, L1 1RH and by virtual means using Microsoft Teams

Registration and seating available from: 09:30am and the event will commence at 10:00am. Full instructions on how to join online or by telephone will be provided in advance to those who have pre-registered.

A livestream will be available for this event. Please click on this link to view the livestream for this event.

27 Tachwedd 2024 - Issue Specific Hearing 2 on Environmental Matters and Other Sea Users (Day 2) (if required)

Caeedig

Issue Specific Hearing 2 on Environmental Matters and Other Sea Users (Day 2) (if required)

Blended event held at Merchant Suite, Delta Hotels Liverpool City Centre, One Queen Square, Liverpool, L1 1RH and by virtual means using Microsoft Teams

Registration and seating available from: 09:00am and the event will commence at 09:30am. Full instructions on how to join online or by telephone will be provided in advance to those who have pre-registered.

A livestream will be available for this event. Please click on this link to view the livestream for this event.

10 Rhagfyr 2024 - Deadline 4

Caeedig

Deadline 4

For receipt by the Examining Authority of:

  • Post-hearing submissions including written submissions of oral cases (if required)
  • Applicant’s mid-Examination Progress Tracker and update to the Statement of Commonality
  • Mid-Examination Report on interrelationship with other infrastructure projects
  • Applicant’s second update to the draft Development Consent Order
  • Applicant’s second update to the Guide to the Application
  • Comments on responses to ExQ1
  • Comments on any other submissions received at Deadline 3
  • Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

19 Rhagfyr 2024 - Examining Authority's Second Written Questions

Caeedig

Publication by the Examining Authority of:

  • Further Written Questions (ExQ2) (if required)