All project updates
17 December 2024
All the submissions for Deadline 1 have been published.
The Examining Authority has also exercised its discretion to accept an additional submission from The Coal Authority (PDF, 1MB)
The examination library (PDF, 435KB) has been updated.
11 December 2024
The following documents have now been published:
· The Examination Timetable (Rule 8 letter) (PDF, 309KB)
· Preliminary Meeting note (PDF, 151KB)
The examination library (PDF, 444KB) has been updated.
11 December 2024
The following have now been published:
Rule 8 letter - Exam Timetable and procedure
· Unaccompanied Site Inspection (USI1) Note (PDF, 899KB)
· Recordings and transcripts for the Preliminary Meeting (PM)
· Recordings and transcripts for Open Floor Hearing 1 (OFH1)
· Recordings and transcripts for Issue Specific Hearing 1 (ISH1)
· Recordings and transcripts for Compulsory Acquisition Hearing 1 (CAH1)
· Action points arising from ISH1 (PDF, 108KB)
· Action points arising from CAH1 (PDF, 46KB)
The examination library (PDF, 444KB) has been updated.
2 December 2024
We have sent instructions for registered participants to join the virtual or at the venue Preliminary Meeting, Open Floor Hearing 1 (OFH1), Issue Specific Hearing 1 (ISH1) and Compulsory Acquisition Hearing 1 (CAH1).
You can also observe the hearings online. If the livestream does not work, try refreshing your webpage.
26 November 2024
All the submissions for Procedural Deadline A have been published.
The examination library (PDF, 411KB) will be updated shortly.
18 November 2024
The agendas for the proposed hearings in the week commencing 2nd December 2024 have been published here.
The Examination Library (PDF, 383KB) will be updated shortly.
Updated on 18 November 2024
13 November 2024
The Examining Authority has exercised its discretion to accept additional submissions.
The submissions come from Camblesforth Parish Council (PDF, 124KB) and 14 submissions from Enso Green Holdings D Limited
The examination library (PDF, 377KB) will be updated shortly.
1 November 2024
The notification of preliminary meeting (‘Rule 6 letter’) has been sent. The letter also includes the draft examination timetable and initial assessment of principal issues.
View the Rule 6 letter (PDF, 429KB)
1 October 2024
The deadline for registering to have your say about the Helios Renewable Energy Project has now passed.
22 August 2024
You can now register to have your say . The deadline to register is 30 September 2024.
31 July 2024
We received the application on 2 July 2024.
The application was accepted for examination on 30 July 2024.
View the acceptance letter (PDF, 147KB)