Skip to main content
Dod o hyd i Brosiect Seilwaith Cenedlaethol

Gwasanaeth beta yw hwn - bydd eich adborth yn ein helpu i'w wella.

East Yorkshire Solar Farm Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 21 May 2024

Caeodd yr archwiliad ar 21 November 2024

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

7 Mai 2024 - Procedural Deadline A

Caeedig

Procedural Deadline A

Deadline for receipt by the Examining Authority (ExA) of:

  • Written submissions on the Examination Procedure, including any submissions about the use of virtual methods
  • Requests to be heard orally at the Preliminary Meeting

21 Mai 2024 - Preliminary Meeting

Caeedig

Preliminary Meeting

Blended Preliminary Meeting at The Parsonage Hotel and Spa, Escrick, York, YO19 6LF and virtually via Microsoft Teams.

21 Mai 2024 - Issue Specific Hearing 1 (ISH1) on the Draft Development Consent Order

Caeedig

Issue Specific Hearing 1 (ISH1) on the Draft Development Consent Order

Blended Issue Specific Hearing 1 (ISH1) on the Draft Development Consent Order at The Parsonage Hotel and Spa, Escrick, York, YO19 6LF and virtually via Microsoft Teams.

Please note that there is a reserve day for this hearing (if required) on Wednesday 22 May 2024 at the same venue commencing at 10:00am.

28 Mai 2024 - Issue by the Examining Authority of Examination Timetable and publication of Examining Authority's First Written Questions

Caeedig

Issue by the Examining Authority of Examination Timetable and publication of Examining Authority's First Written Questions

18 Mehefin 2024 - Deadline 1

Caeedig

Deadline 1

For receipt by the ExA of:

  • Written summaries of oral submissions from Issue Specific Hearing held on 21 May
  • Post hearing submissions requested by ExA
  • Comments on Relevant Representations (RR)
  • Summaries of all RR exceeding 1500 words
  • Written Representations (WR)
  • Local Impact Report (LIR) from North Yorkshire Council
  • Statements of Common Ground (SoCGs) requested by the ExA
  • Statement of Commonality for SoCG
  • Responses to ExQ1
  • Submission of suggested sites to be included in any Accompanied Site Inspection (ASI) including reasons why the site needs to be visited on an accompanied basis and any access requirements 
  • Revised Application Guide from the Applicant
  • A Compulsory Acquisition Schedule from the Applicant
  • Status of Negotiations Schedule (SNS) from the Applicant
  • Updated Book of Reference (BoR) and Schedule of Changes to the BoR and tracked versions (if required)
  • Comments on any updated application documents
  • Notification of wish to have any future correspondence received electronically  
  • Notification of Statutory Parties of their wish to be considered as an Interested party (IP)
  • Notification of any Affected Person (AP) of a wish to speak at a Compulsory Acquisition Hearing (CAH) 
  • Notification of an interested party of a wish to speak at an Open Floor Hearing (OFH)
  • Notification of wish to attend an ASI
  • Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules
  • Comments on any further information/submissions accepted by the ExA
  • Other

27 Mehefin 2024 - Deadline 2

Caeedig

Deadline 2

For receipt by the ExA of:

  • Comments on submissions received at Deadline 1
  • LIR from East Riding of Yorkshire Council
  • Applicant’s draft itinerary for the ASI
  • Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules
  • Other

2 Gorffennaf 2024 - Publication by the ExA of ExA’s final itinerary for the Accompanied Site Inspection

Caeedig

Publication by the ExA of ExA’s final itinerary for the Accompanied Site Inspection

9 Gorffennaf 2024 - Compulsory Acquisition Hearing 1

Caeedig

Compulsory Acquisition Hearing 1

9 Gorffennaf 2024 - Open Floor Hearing

Caeedig

Open Floor Hearing

10 Gorffennaf 2024 - Issue Specific Hearing 2 on Environmental Matters

Caeedig

Issue Specific Hearing 2 on Environmental Matters

11 Gorffennaf 2024 - Accompanied Site Inspection

Caeedig

Accompanied Site Inspection

Accompanied Site Inspection on Thursday 11 July 2024 starting at the Loftsome Bridge Hotel, Station Road, Wressle, Yorkshire, Y08 6EN from 09:15am (for a safety briefing) and departing at 09:30am.

23 Gorffennaf 2024 - Deadline 3

Caeedig

Deadline 3

For receipt by the ExA of:

  • Comments on any submissions received by Deadline 2
  • Written summaries of oral contributions at hearings (if required)
  • Post-hearing submissions requested by the ExA (if required)
  • Applicant’s updated dDCO, EM, BoR, SoR, SNS and CA Schedule
  • Updated SoCGs
  • Updated Statement of Commonality of SoCGs
  • Any further information requested by the ExA under Rule 17
  • Other

1 Awst 2024 - Examining Authority's Second Written Questions

Caeedig

Examining Authority's Second Written Questions

Publication of Examining Authority's Second Written Questions (ExQ2) (if required)

15 Awst 2024 - Deadline 4

Caeedig

Deadline 4

For receipt by the ExA of:

  • Comments on submissions at Deadline 3
  • Responses to the ExAs Second Written Questions
  • Applicant’s updated dDCO, EM, BoR, SoR, SNS and CA Schedule
  • Updated SoCGs
  • Updated Statement of Commonality
  • Updated Section 106 Agreement/unilateral undertaking (if required)
  • Any further information requested by the ExA under Rule 17
  • Other

3 Medi 2024 - Deadline 5

Caeedig

Deadline 5

For receipt by the ExA of:

  • Comments on submissions at Deadline 4
  • Any further information requested by the ExA under Rule 17
  • Other

18 Medi 2024 - Time reserved for hearings during week commencing 16 September 2024

Caeedig

Time reserved for hearings during week commencing 16 September 2024

Time reserved for hearings: Issue Specific Hearing(s) (if required) Compulsory Acquisition Hearing (if required)

1 Hydref 2024 - Deadline 6

Caeedig

Deadline 6

For receipt by the ExA of:

  • Comments on any submissions at Deadline 5
  • Applicant’s updated dDCO and EM
  • Applicant’s updated BoR, SoR, SNS and CA Schedule
  • Updated SoCGs
  • Updated SoCG and Statement of Commonality of SoCG
  • Final signed and dated Section 106 Agreement/Unilateral Undertaking (if required)
  • Updated Navigation Document/Guide to the application
  • Written summaries of oral contributions at hearings (if required)
  • Post-hearing submissions requested by the ExA (if required)
  • Any further information requested by the ExA under Rule 17
  • Other

15 Hydref 2024 - Publication by the ExA of The ExA’s schedule of changes to the draft DCO, Report on Implications for European Sites (RIES) and ExQ3

Caeedig

Publication by the ExA of The ExA’s schedule of changes to the draft DCO, Report on Implications for European Sites (RIES) and ExQ3

Publication by the ExA of:

  • The ExA’s schedule of changes to the draft DCO (if required)
  • Report on Implications for European Sites (RIES) (if required)
  • ExA’s Written Questions (ExQ3) (if required)

5 Tachwedd 2024 - Deadline 7

Caeedig

Deadline 7

For receipt by the ExA of:

  • Comments on submissions at Deadline 6
  • Comments on the ExA’s schedule of changes to the dDCO (if required)
  • Comments on RIES (if required)
  • Responses to ExQ3 (if required)
  • Any further information requested by the ExA under Rule 17
  • Other

14 Tachwedd 2024 - Deadline 8

Caeedig

Deadline 8

For receipt by the ExA of:

  • Comments on submissions at Deadline 7
  • Applicant’s final dDCO - Final and/or updated DCO in editable and PDF formats to be submitted by the Applicant in the SI template with the SI template validation report
  • Applicant’s final EM
  • Applicant’s final BoR, SoR, SNS and CA Schedule
  • Summary Statements from Interested Parties
  • Final SoCG
  • Final Statement of Commonality of SoCG
  • List of matters not agreed where SoCG could not be finalised
  • Final Navigation Document/Guide to the application
  • Final Status of Negotiations with Statutory Undertakers
  • Final NPS tracker
  • Final signed and dated section 106
  • Responses to comments on RIES (if required)
  • Any further information requested by the ExA under Rule 17
  • Other

21 Tachwedd 2024 - Deadline for completion of Examination

Caeedig

Deadline for completion of Examination

The ExA is under a duty to complete the Examination of the application by the end of the period of six months