Willington C Gas Pipeline

Cyngor Adran 51

Mae'r rhestr isod yn cynnwys cofnod o gyngor a roddwyd gennym ar gyfer y prosiect hwn.

Mae dyletswydd statudol, o dan adran 51 Deddf Cynllunio 2008, ynglŷn â chais neu ddarpar gais. Mae hyn yn cynnwys cofnodi enw'r unigolyn a ofynnodd am y cyngor a'r cyngor a roddwyd. Mae'n rhaid i'r wybodaeth hon gael ei chyhoeddi.

Chwilio cyngor

Chwiliwch yn ôl geiriau allweddol neu enw'r unigolyn y rhoddwyd y cyngor iddo.

Yn dangos 1 i 25 o 49 o ddogfennau, gyda'r rhai mwyaf newydd yn gyntaf.

Canlyniadau fesul tudalen 25 | View 50 results per page | View 100 results per page

  • Gweld cyngor i Derby Aero Club

    Query regarding original submissions to the applicant.

  • Gweld cyngor i K Howell

    Query about the accompanied site visit

  • Gweld cyngor i Sheffield Metropolitan Council

    After receiving the Rule 8 letter dated 20 January 2014, Sheffield Metropolitan Council queried whether it was correct that they were contacted in regards to the Willington C Gas Pipeline.

  • Gweld cyfarfod gyda RWE npower

    Teleconference between RWE npower and The Planning Inspectorate

  • Gweld cyngor i RWE npower - Hugh Morris

    Please see attached meeting note.

  • Gweld cyfarfod gyda RWE npower

    Pre-submission update meeting between the Planning Inspectorate and the applicant.

  • Gweld cyngor i RWE npower

    Mr Morris submited a query regarding the required level of pre-application consulation in relation to potential changes in the pipeline?s limit of deviation at the A515 Yoxall road crossing.

  • Gweld cyngor i RWE npower

    Comments on draft DCO and s127 applications

  • Gweld cyfarfod gyda Hugh Morris RWE

    Please see attachment.

  • Gweld cyngor i RWE npower

    You asked us to try to make the Consultation Report as 'user friendly' as possible and we are looking at making the signposts as clear as possible so that appended documents can be located. Also, wher... Darllen mwy

  • Gweld cyfarfod gyda RWE Npower

    Pre-Submission Update and Review

  • Gweld cyfarfod gyda Willington C Project team

    Tele-conference to update the Planning Inspectorate on the Willington C team?s progress and discuss technical queries in relation to application documents.

  • Gweld cyngor i Reynolds Porter Chamberlain LLP

    We have been discussing the Article relating to Statutory undertakers' equipment and the insertion of protective provisions into the order i.e as a back up in case we fail to agree something with the ... Darllen mwy

  • Gweld cyngor i RWE Npower

    we are planning our Stage 2 consultations to start in mid July and wish to confirm the requirements of S46. We served our initial S46 notification on the 7th of July 2010, in advance of our Stage ... Darllen mwy

  • Gweld cyngor i Adriana Gasparini

    The planning inspectorate letter of advice to us dated 03/05/2012 refers to the use of a font size and numbering consistent with SI drafting and points us to the Rookery South DCO. Although NID g... Darllen mwy

  • Gweld cyngor i RWE npower

    Could the Inspectorate provide RWE with the list of the s43 local authorities taking account of the amendments introduced by the Localism Act

  • Gweld cyngor i RWE nPower

    Is it acceptable for the Inspectorate to receive the information in support of s 127 as part of the Statement of Reasons?

  • Gweld cyngor i RWE npower

    N/a

  • Gweld cyngor i RWE Npower, RPC, Bruton Knowles

    Please see attached meeting note, letter confirming the advice provided in the meeting and follow up clarification email.

  • Gweld cyngor i RWE npower

    As a result of changes to the WCGP application program, the actual consultation process will be different to that described in the SOCC. The main difference is that in the SOCC, we proposed holding th... Darllen mwy

  • Gweld cyngor i RPC LLP

    Please advise me about the MP16 survey rights which we spoke about with regard to the drafting of our article 16 and whether NID are likely to be concerned about the extent of land covered by that pr... Darllen mwy

  • Gweld cyngor i RWE npower

    I would like to request your advice regarding the appropriate terminology to describe the submission to Natural England of a GCN license application, during the pre application stage, in order to esta... Darllen mwy

  • Gweld cyfarfod gyda RWE Npower

    To discuss RWE?s application schedule.

  • Gweld cyngor i RWE npower

    On the 3rd of October, I raised a question regarding the actual process for the transfer of benefit. You advised me to contact DECC regarding this issue and DECC have now responded that they expect th... Darllen mwy

  • Gweld cyfarfod gyda East Staffordshire BC

    At a meeting with the relevant local authorities and RWEnpower for this project on 23 June 2011, RWEnpower asked to which degree an application could be changed following submission