Representation by Masons Rural (Masons Rural) on behalf of J H Pridgeon (J H Pridgeon)
- Date submitted
- 11 January 2024
- Submitted by
- Members of the public/businesses
Fully Withdrawn via REP1-116 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents. Have not ever met with the client either. • Failure to agree a method statement for the pipeline construction and failure to provide clarity regarding construction depth of the pipeline and assurances that the land can be farmed going forward • No consultation has taken place regarding potential future development of the pipeline corridor and compensation provision via a development clause • No consultation regarding the implementation of a haul road during the construction period