Back to list Viking CCS Pipeline

Representation by The Spilman Family (The Spilman Family)

Date submitted
15 January 2024
Submitted by
Members of the public/businesses

• Failure to agree a method statement for the pipeline construction and failure to provide clarity regarding construction depth of the pipeline and assurances that the land can be farmed going forward • No consultation has taken place regarding potential future development of the pipeline corridor and compensation provision via a development clause • No consultation regarding the implementation of a haul road during the construction period • No consultation has taken place on drainage • Lack of integrity/being disingenuous regarding the option area • No consultation on certain matters regarding the block valve for example: location, how will the landowner be compensated for this? What are the rights? How will it work alongside Anglian Waters infrastructure?