Cyngor i Highways Agency
Yn ôl i'r rhestrYmholiad
- Oddiwrth
- Highways Agency
- Y dyddiad y rhoddwyd y cyngor
- 17 Awst 2011
- Math o ymholiad
- Phone
IPC noticed that the scoping report submitted by the Highways Agency (HA) on 10th August included a description of works that did not appear to be encapsulated by the red line plan submitted with the request. IPC contacted HA to confirm these issues and query with them the intention for the DCO process.
Cyngor a roddwyd
Ms Pickering from the Highways Agency (HA) was contacted to discuss the information provided to support a request by the HA for a scoping opinion from the IPC. The IPC asked if the elements of the project particularly in relation to de-trunking activities would be included within the scope of works for the Development Consent Order (DCO). The HA confirmed that the DCO would include the works required for de-trunking and that the red line plan provided with the scoping request did not cover all of the land to which the DCO would relate. The IPC informed the HA that on the basis of the discussion it would be neccessary for the IPC to request further information under EIA Regulation 8 (5). The IPC also confirmed that this would be made via a formal notification letter.