M1 Junction 10a Grade Separation - Luton Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 15 November 2012

Caeodd yr archwiliad ar 13 May 2013

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

15 Tachwedd 2012 - Preliminary Meeting

Caeedig

The audio recording of the Preliminary Meeting that took place on 15 November 2012 has now been published.

30 Tachwedd 2012 - Deadline 1

Caeedig

Issue of: Procedural timetable, Note of Preliminary Meeting held on 15 November 2012 and First Written Questions

21 Rhagfyr 2012 - Deadline 2

Caeedig

Date by which Statutory Parties (SP) must notify the Examining authority of their wish to be considered as an Interested Party

9 Ionawr 2013 - Deadline 3

Caeedig

Deadline for receipt by the Examining authority of: Any summaries of Relevant Representations exceeding 1500 words, Written Representations by all Interested Parties, Any summaries of Written Representations exceeding 1500 words, Local Impact Report from any local authorities, Responses to Examining authority’s first Written Questions, Notification by an Interested Party of their wish to be heard at (a) an Open Floor Hearing or a (b) a Compulsory Acquisition Hearing and Comments on Relevant Representations

6 Chwefror 2013 - Deadline 4

Caeedig

Deadline for receipt by the Examining authority of: Comments on Written Representations, Comments on Local Impact Reports, Comments on responses to Examining authority’s first Written Questions, Any Statements of Common Ground, Responses to Comments on Relevant Representations and Notification of wish to cross-examine at Issue Specific and Compulsory Acquisition hearings

13 Chwefror 2013 - Issue Specific Hearing 1

Caeedig

Registration for the Hearing into the Developement Consent Order opens at 09:00

Following the hearing an accompanied site visit will take place at 14:00 and start at the Luton Borough Council Town Hall.

20 Chwefror 2013 - Deadline 5

Caeedig

Issue of: Second Written Questions

13 Mawrth 2013 - Deadline 6

Caeedig

Deadline for receipt by the Examining authority of: Responses to Examining authority’s second Written Questions

10 Ebrill 2013 - Deadline 7

Caeedig

Deadline for receipt by the Examining authority of: Comments on responses to Examining authority’s second Written Questions

10 Ebrill 2013 - Deadline 8

Caeedig

Deadline for receipt by the Examining authority of: Any initial revised proposed schedules or requirements for inclusion within the draft Development Consent Order

17 Ebrill 2013 - Issue Specific Hearing 2

Caeedig

Environmental Impacts & Mitigation Proposals

17 Ebrill 2013 - Issue Specific Hearing 3

Caeedig

Need, Costs & Benefits

18 Ebrill 2013 - Issue Specific Hearing 4

Caeedig

Draft Development Consent Order

19 Ebrill 2013 - Issue Specific Hearing 5

Caeedig

Compulsory Acquisition

26 Ebrill 2013 - Deadline 9

Caeedig

Deadline for receipt by the Examining authority of: Any revised proposed schedules or requirements for inclusion within the draft Development Consent Order

30 Ebrill 2013 - Issue Specific Hearing 6

Caeedig

Resumed Hearings

3 Mai 2013 - Deadline 10

Caeedig

Deadline for receipt of Final Draft DCO and any related material

9 Mai 2013 - Deadline 11

Caeedig

Deadline for receipt of comments on Final Draft DCO and any related material

13 Mai 2013 - Deadline 12

Caeedig

Deadline for the receipt of the applicant’s response to comments on Final Draft DCO and any related material