A585 Windy Harbour to Skippool Improvement Scheme Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination closed on 9 October 2019

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

9 April 2019 - Preliminary Meeting

Closed

Preliminary Meeting

9 April 2019 - Open Floor Hearing

Closed

Open Floor Hearing (OFH1)

16 April 2019 - Issue by the ExA of

Closed

• Examination Timetable • The ExA’s Written Questions

26 April 2019 - Deadline 1

Closed

DEADLINE 1 (D1)

Deadline for receipt by the ExA of: • Comments on updated application documents • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Post Hearing submissions including written submissions of oral case made at OFH1 • Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Applicant’s draft itinerary for Accompanied Site Inspection (ASI) • Suggested locations for site inspections, and justification, for consideration by the ExA • Notification of wish to speak at any subsequent Open Floor Hearing (OFH) • Notification of wish to make oral representations at an Issue Specific Hearing (ISH) • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • Notification of wish to have future correspondence received electronically • Comments on any additional information/ submissions received • Responses to any further information requested by the ExA for this deadline

17 May 2019 - Deadline 2

Closed

DEADLINE 2 (D2)

Deadline for receipt by the ExA of: • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Local Impact Reports from any local authorities • Statements of Common Ground (SoCG) requested by the ExA • Responses to the ExA’s Written Questions • Applicant’s first revised draft DCO • Responses to comments on RRs • Comments on draft itinerary for ASI and suggested locations for site inspections • Notification of wish to attend an ASI • Comments on any additional information/ submissions received by D1 • Responses to any further information requested by the ExA for this deadline

31 May 2019 - Deadline 3

Closed

DEADLINE 3 (D3)

Deadline for receipt by the ExA of: • Comments on WRs • Comments on Local Impact Reports • Comments on SoCG • Comments on responses to the ExA’s Written Questions • Comments on Applicant’s first revised draft DCO • Comments on any additional information/ submissions received by D2 • Responses to any further information requested by the ExA for this deadline

4 June 2019 - Notification of Hearings and ASI

Closed

NOTIFICATION OF HEARINGS AND SITE INSPECTION

Time reserved for issue by the ExA of: • Notification of date, time and meeting place for ASI • Notification of Hearings

2 July 2019 - Accompanied Site Inspection

Closed

Accompanied Site Inspection (ASI)

3 July 2019 - Issue Specific Hearing 1 (ISH1)

Closed

Issue Specific Hearing on the draft DCO (ISH1)

3 July 2019 - Compulsory Acquisition Hearing

Closed

Compulsory Acquisition Hearing(CAH1)

3 July 2019 - Open Floor Hearing 2

Closed

Open Floor Hearing (OFH2)

12 July 2019 - Deadline 4

Closed

DEADLINE 4 (D4)

Deadline for receipt by the ExA of: • Post Hearing submissions including written submissions of oral case • Any revised/ updated SoCG (if any) • Comments on any additional information/ submissions received by D3 • Responses to any further information requested by the ExA for this deadline

23 July 2019 - Publication by ExA of -

Closed

• The ExA’s Further Written Questions (if required)

9 August 2019 - Deadline 5

Closed

DEADLINE 5 (D5)

Deadline for receipt by the ExA of: • Responses to the ExA’s further Written Questions (if required) • Applicant’s revised draft DCO • Comments on any revised/ updated SoCG • Comments on any additional information/ submissions received by D4 • Responses to any further information requested by the ExA for this deadline

13 August 2019 - Notification of Hearings

Closed

Time reserved for issue by the ExA of: • Any notification of Hearings – NOT REQUIRED

19 August 2019 - Publication of

Closed

• The ExA’s Further Written Questions

21 August 2019 - Deadline 6 (D6)

Closed

Deadline 6 (D6) Deadline for receipt by the ExA of: • Comments on responses to the ExA’s further Written Questions (issued on Tuesday 23 July 2019) • Comments on Applicant’s revised draft DCO • Comments on any additional information/ submissions received by D5 • Responses to any further information requested by the ExA for this deadline

27 August 2019 - Publication of

Closed

• Report on the Implications for European Sites (RIES)

2 September 2019 - Deadline 6a (D6a)

Closed

Deadline 6a (D6a) Deadline for receipt by the ExA of: • Responses to the ExA’s Additional Written Questions (issued on Monday 19 August 2019) • Responses to any further information requested by the ExA for this deadline

10 September 2019 - Hearings

Closed

NOT REQUIRED

10 September 2019 - Publication of

Closed

The ExA’s proposed schedule of changes to the draft DCO (if required)

20 September 2019 - Deadline 7 (D7)

Closed

Deadline 7 (D7) Deadline for receipt by the ExA of: • Comments on the ExA’s proposed schedule of changes to the draft DCO • Comments on the RIES • Comments on any responses to the ExA’s Additional Written Questions (issued on Monday 19 August 2019) • Comments on any additional information/ submissions received by D6 • Responses to any further information requested by the ExA for this deadline

1 October 2019 - Deadline 8 (D8)

Closed

Deadline 8 (D8) Deadline for receipt by the ExA of: • Response to comments on the RIES • Responses to comments on the ExA’s proposed schedule of changes to the draft DCO • Final DCO to be submitted by the Applicant in the SI template with the SI template validation report • Final updated Book of Reference • Final SoCG • Final Compulsory Acquisition Schedule • Final updated Guide to the Application • Comments on any additional information/ submissions received by D7 • Responses to any further information requested by the ExA for this deadline

7 October 2019 - Deadline 9 - midday

Closed

Deadline 9 (D9) - midday Deadline for receipt by the ExA of: • Comments on any additional information/ submissions received by D8 • Responses to any further information requested by the ExA for this deadline

9 October 2019 - Close of Examination

Closed

Responses to any further information requested by the ExA for this deadline.

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.