All project updates

9 April 2020

The Secretary of State has granted development consent for this application. For further information please refer to the following decision documentation:

Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as Made by the Secretary of State
Recommendation Report
Post-Examination Submissions
Regulation 31 Notice

9 April 2020

Decision made by the Secretary of State

9 January 2020

Recommendations given by the Planning Inspectorate

8 October 2019

The Submissions for Deadline 9 have now been published.

3 October 2019

The Submissions for Deadline 8 have now been published.

26 September 2019

Procedural decision in relation to the proposed Design Changes and Additional Land, Notification of change to the Examination Timetable and Request for Further Information has been published.

24 September 2019

The Submissions for Deadline 7 have now been published.

4 September 2019

The Submissions for Deadline 6a have now been published.

27 August 2019

22 August 2019

The Deadline 6 documents have now been published.  Additional information regarding the change request has been accepted at the discretion of the Examining Authority.

19 August 2019

The Examining Authority (ExA) has reviewed submissions received at Deadline 5 and decided to issue a Rule 8(3) letteramending the examination timetable to provide for the publication of the ExA Additional Written Questions and the subsequent responses.

13 August 2019

Having reviewed the submissions received at Deadline 4 and Deadline 5 the Examining Authority confirms that he does not intend to hold a further Issue Specific Hearing, Issue Specific Hearing on the draft DCO, Compulsory Acquisition Hearing or Open Floor Hearing between Tuesday 10 September and Thursday 12 September 2019.

12 August 2019

The documents for deadline 5 have been published

24 July 2019

The Examining Authority’s Further Written Questions have now been published

17 July 2019

The documents for deadline 4 have been published.

7 June 2019

A further Deadline 3 Submission has been published.

6 June 2019

The route of the Accompanied Site Inspection has now been published.

22 May 2019

The Submissions for Deadline 2 have now been published.

29 April 2019

Deadline 1 submissions have now been published.

16 April 2019

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

10 April 2019

The Audio Recordings for the Preliminary Meeting and Open Floor Hearing held on the 9 April 2019 have been Published and are available now.

9 April 2019

Preliminary Meeting takes place

12 March 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

11 March 2019

An Additional Submission that has been accepted at the discretion of the Examining Authority has been published.

15 February 2019

Three Additional Submissions have been published.

The applicant has sent us a letter explaining that some of the notifications they sent about the opportunity to make Relevant Representations were returned undelivered, and that some parties had not been served notice.

The applicant has sent or re-sent further notifications to those parties only, and has allowed more time for them to make their representations. If you have received a further notification and wish to make a representation, please contact us at A585WindyHarbourtoSkippool@pins.gsi.gov.uk or telephone 0303 444 5000

10 February 2019

Relevant representations published on the website

24 January 2019

Registration of interested parties closes

19 December 2018

Registration of interested parties begins

26 November 2018

The application has been accepted for examination

29 October 2018

Application received by the Planning Inspectorate