A66 Northern Trans-Pennine Project Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 29 November 2022

The examination closed on 29 May 2023

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

16 November 2022 - Procedural Deadline

Closed

Procedural Deadline

Deadline for receipt by the ExA of:

  • Responses to the Rule 6 letter
  • Submission of additional or updated drawings as requested in Annex D
  • Requests to be heard orally at the Preliminary Meeting and under which part of the agenda set out in Annex A
  • Requests by Interested Parties to be heard orally at the Open Floor Hearing 1
  • Requests by Affected Persons to be heard orally at the Compulsory Acquisition Hearing 1
  • Notification of intention to attend the Issue Specific Hearing(s)

29 November 2022 - Preliminary Meeting

Closed

Preliminary Meeting (PM)

Tuesday 29 November 2022 at 10.00am

29 November 2022 - Open Floor Hearing (OFH1)

Closed

Open Floor Hearing (OFH1)

Tuesday 29 November 2022 at 2.30pm

30 November 2022 - Issue Specific Hearing (ISH1)

Closed

Issue Specific Hearing (ISH1)

ISH1 on Alternative Route Options

Wednesday 30 November 2022 at 10:00am

(n.b this meeting will need to conclude no later than 3.30pm)

1 December 2022 - Issue Specific Hearing (ISH2)

Closed

Issue Specific Hearing (ISH2)

ISH2 on:

  • The Environmental Management Plan;
  • other environmental matters; and
  • the draft Development Consent Order (draft DCO)

Thursday 1 December 2022 at 10.00am

2 December 2022 - Compulsory Acquisition Hearing (CAH1)

Closed

Compulsory Acquisition Hearing (CAH1)

Friday 2 December 2022 at 10.00am

18 December 2022 - Deadline 1

Closed

Deadline 1

For receipt by the ExA of:

  • Comments on any updates to application documents submitted by the Applicant before or at the PM
  • Comments on Relevant Representations (RRs)
  • Summaries of all RRs exceeding 1500 words
  • Written Representations (WRs)
  • Summaries of all WRs exceeding 1500 words
  • Local Impact Reports
  • Notification by Statutory Parties of their wish to be considered as an IP by the ExA
  • Notification of wish to be heard at any subsequent Issue Specific Hearings (ISH)
  • Requests to be heard at any subsequent Compulsory Acquisition Hearing (CAH). Requests by Affected Persons (defined in section 59(4) of the Planning Act 2008) to be heard at a CAH
  • Request to be heard at any subsequent Open Floor Hearing (OFH)
  • Provision of suggested locations and justifications for Accompanied Site Inspections (ASI) for consideration by the ExA (if held)
  • Post-hearing submissions including written submissions of oral cases
  • Notification of wish to have future correspondence received electronically
  • Submission of additional or updated drawings as requested in Annex D of the Rule 6 letter (if not submitted at the Pre-Examination Procedural Deadline)
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions accepted by the ExA

15 January 2023 - Deadline 2

Closed

Deadline 2

For receipt by the ExA of:

  • Comments on WR
  • Comments on the LIRs
  • The Applicant’s revised draft DCO
  • Compulsory Acquisition Status of Negotiations Schedule
  • Statutory Undertakers Status of Negotiations Schedule
  • Applicant’s draft itinerary for the ASI (if required)
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions received by Deadline 1

24 January 2023 - Deadline 3

Closed

Deadline 3

For receipt by the ExA of:

  • Updated Statements of Common Ground requested by ExA – see Annex D of the Rule 6 letter
  • Updated Statements of Commonality of Statements of Common Ground
  • Updated Principal Areas of Disagreement Summary Statements
  • Comments on the Applicant’s draft ASI Itinerary
  • Comments on the Applicant’s revised draft DCO
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions received by Deadline 2

31 January 2023 - Publication by the ExA

Closed

Publication by the ExA of:

  • Written Questions
  • Notification of Hearings (if required)
  • Notification of ASI (if required)
  • The ExA’s final itinerary for the ASI (if required)

14 February 2023 - Deadline 4

Closed

Deadline 4

For receipt by the ExA of:

  • Responses to Written Questions
  • Notification of wish to attend an Accompanied Site Inspection (ASI) (if required)

28 February 2023 - Accompanied Site Inspection (ASI)

Closed

Accompanied Site Inspection (ASI) (if required)

28 February 2023 - Open Floor Hearing (OFH2)

Closed

Open Floor Hearing (OFH2) (if required)(evening)

1 March 2023 - Compulsory Acquisition Hearing (CAH2)

Closed

Compulsory Acquisition Hearing (CAH2) (if required)

2 March 2023 - Issue Specific Hearing (ISH3)

Closed

Issue Specific Hearing (ISH3)(if required)

On Environmental Matters and/or the draft DCO. This Hearing will be scheduled over two days if needed.

3 March 2023 - Issue Specific Hearing (ISH3 Resumed)

Closed

Issue Specific Hearing (ISH3 Resumed) (if required)

14 March 2023 - Deadline 5

Closed

Deadline 5

For receipt by the ExA of:

  • Post-hearing submissions including written submissions of oral cases
  • The Applicant’s revised draft DCO
  • Compulsory Acquisition Status of Negotiations Schedule
  • Statutory Undertakers Status of Negotiations Schedule
  • Updated Statements of Common Ground
  • Updated Statement of Commonality of Statements of Common Ground
  • Updated Principal Areas of Disagreement Summary Statements
  • Guide to the Application
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions received by Deadline 4

24 March 2023 - Publication by the ExA.

Closed

Publication by the ExA of:

  • Further Written Questions (if required)

30 March 2023 - Reserve Accompanied Site Inspection

Closed

Accompanied Site Inspection (if required)

4 April 2023 - Deadline 6

Closed

Deadline 6

For receipt by the ExA of:

  • Responses to ExA’s Further Written Questions (if required)
  • Comments on the Applicant’s revised dDCO
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions received by Deadline 5

18 April 2023 - .Publication by the ExA

Closed

Publication by the ExA of:

  • Report on the Implications for European Sites (RIES) (if required)
  • ExA’s commentary on, or schedule of changes to, the draft DCO (if required)

9 May 2023 - Deadline 7

Closed

Deadline 7

For receipt by the ExA of:

  • Comments on the RIES (if required)
  • Comments on ExA’s commentary on, or schedule of changes to, the draft DCO (if required)
  • Final Principal Areas of Disagreement Summary Statements
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions received by Deadline 6

16 May 2023 - Deadline 8

Closed

Deadline 8

For receipt by the ExA of:

  • Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report
  • Final Book of Reference (BoR) and schedule of changes to BoR
  • Final Explanatory Memorandum
  • Final Statement of Reasons
  • Final Compulsory Acquisition Status of Negotiations Schedule
  • Final Statutory Undertakers Status of Negotiations Schedule
  • Final Statements of Common Ground
  • Final Statement of Commonality of Statements of Common Ground
  • Final Guide to the Application
  • Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
  • Comments on any further information/ submissions received by Deadline 7

26 May 2023 - Deadline 9

Closed

Deadline 9

For receipt by the ExA of:

  • Any further information requested by ExA Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010