1. Section 51 advice
  2. Advice in detail

Advice to Rebekah Smith

Back to list

Enquiry

From
Rebekah Smith
Date advice given
19 February 2018
Enquiry type
Email

Please can you explain/reassure me that I have not wasted 20 hours+ on this and that my email will be submitted as a negative response to the recent public consultation process carried out by RSP.

Advice given

Last Friday’s deadline was imposed by the Applicant, RiverOak Strategic Partners (RSP). RSP was carrying out statutory consultation seeking feedback on the substance of its proposed application ie the Proposed Development and its impacts.

Whilst RSP will not have been actively seeking feedback on the consultation ‘process’ in this period, it is correct that you have sent your comments in this respect to RSP for consideration in the first instance.

You also copied your comments about the consultation process to Thanet District Council, which importantly will be able to consider them in making a representation about the adequacy of RSP’s consultation to the Secretary of State if/ when an application is submitted to the Planning Inspectorate. Amongst other things, the Planning Inspectorate must have regard to any Adequacy of Consultation Representations received from local authorities in taking its decision about whether or not an application can be accepted for examination.

On that basis your commentary about the consultation process is not wasted, and you have taken all of the appropriate steps advised in our Community Consultation FAQ: https://infrastructure.planninginspectorate.gov.uk/application-process/frequently-asked-questions/