The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 24 May 2012

The examination closed on 24 November 2012

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

24 May 2012 - Preliminary Meeting

Closed

Preliminary Meeting to discuss how the application will be examined.

31 May 2012 - Deadline 1

Closed

Procedural decision including Principle Issues, confirmation of the examination timetable and first written questions from the ExA under Rule 8 of the Infrastructure Planning (Examination Procedure) Rules 2010. Initial draft of Statement to inform Habitats Regulations Assessment. Notification by ExA of the dates of Open Floor, Specific Issue and Compulsory Acquisition Hearings, and accompanied site inspections.

15 June 2012 - Deadline 2

Closed

Notification of Hearings under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010

28 June 2012 - Deadline 3

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Stone Creek Boat Club

29 June 2012 - Deadline 4

Closed

Comments on Relevant Representations (RRs) Any summaries of RRs exceeding 1500 words Written Representations (WRs) by all interested parties Any summaries of WRs exceeding 1500 words Local Impact Report (LIR) from any local authorities Responses to ExA’s first written questions Notification by an Interested Party of their wish to be heard at (a) an Open Floor hearing and (b) a Compulsory Acquisition hearing Notification of wish to make oral representations at the Issue Specific Hearing on the draft Development Consent Order including the draft Deemed Marine Licence

10 July 2012 - Deadline 5

Closed

Variation to timetable under Rule 8(3) of the Infrastructure Planning (Examination Procedure) Rules 2010.

12 July 2012 - Issue Specific Hearing 1

Closed

Draft Development Consent Order including the draft Deemed Marine Licence

23 July 2012 - Deadline 6

Closed

Any written summary of the oral case put at the Specific Issue Hearing on the draft Development Consent Order including the draft Deemed Marine Licence held on Thursday 12 July 2012

27 July 2012 - Deadline 7

Closed

Comments on LIRs Comments on responses to ExA’s first written questions Submissions on the case for cross-examination at any Issue Specific or Compulsory Acquisition hearing Any Statements of Common Ground (other than on Habitats Regulations Assessment (HRA) matters)

3 August 2012 - Deadline 8

Closed

Comments on WRs and responses to comments on RRs

7 August 2012 - Deadline 9

Closed

Variation to timetable under Rule 8(3) of the Infrastructure Planning (Examination Procedure) Rules 2010.

15 August 2012 - Deadline 10

Closed

Variation to timetable under Rule 8(3) of the Infrastructure Planning (Examination Procedure) Rules 2010 and notification of Hearings under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010

17 August 2012 - Deadline 11

Closed

Issue of second written questions from ExA

24 August 2012 - Deadline 12

Closed

Statements of Common Ground on HRA Notification of wish to speak at an Open Floor Hearing

31 August 2012 - Deadline 13

Closed

Notification of wish to make oral representations at the Specific Issue Hearing on compensation site matters, including HRA (11 September), HRA matters relating to the main development site (12 September), marine matters (13 September) and land access and transport (14 September)Notification of wish to make oral representations at the Specific Issue Hearing on compensation site matters, including HRA (11 September), HRA matters relating to the main development site (12 September), marine matters (13 September) and land access and transport (14 September)

5 September 2012 - Open Floor Hearing 1

Closed

Open Floor in East Riding of Yorkshire area

6 September 2012 - Open Floor Hearing 2

Closed

Open Floor in North Lincolnshire area

7 September 2012 - Deadline 14

Closed

Responses to ExA’s second written questions

11 September 2012 - Deadline 15

Closed

Variation to timetable under Rule 8(3) of the Infrastructure Planning (Examination Procedure) Rules 2010 and notification of Hearings under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010

11 September 2012 - Issue Specific Hearing 2

Closed

Specific Issue dealing with matters relating to the compensation site including HRA

12 September 2012 - Issue Specific Hearing 3

Closed

Specific Issue dealing with matters relating to the main development site

13 September 2012 - Issue Specific Hearing 4

Closed

Specific Issue dealing with marine matters

14 September 2012 - Issue Specific Hearing 5

Closed

Specific Issue dealing with land access and transport

17 September 2012 - Deadline 16

Closed

Any written summary of the oral case put at any Open Floor Hearing held in the East Riding of Yorkshire (5 September 2012) and North Lincolnshire (6 September 2012) areas

20 September 2012 - Deadline 17

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to ABP

21 September 2012 - Deadline 18

Closed

Variation to timetable under Rule 8(3) of the Infrastructure Planning (Examination Procedure) Rules 2010 and notification of Hearings under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010.

24 September 2012 - Deadline 19

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to ABP Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able Any written summary of the oral case put at the Specific Issue Hearing held on the compensation site, including HRA matters (11 September 2012), HRA matters relating to the main development site (12 September 2012), marine matters (13 September 2012) and land access and transport (14 September 2012)

25 September 2012 - Deadline 20

Closed

Site inspection in the company of Interested Parties under Rule 16 of the Infrastructure Planning (Examination Procedure) Rules 2010

26 September 2012 - Deadline 21

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able

28 September 2012 - Deadline 22

Closed

Notification of wish to make oral representations at the Compulsory Acquisition Hearing (16 and 17 October) Specific Issue Hearing dealing with HRA (compensation site) (9 October), Compulsory Acquisition (compensation site) (9 October), Compulsory Acquisition (main development site) (10 October), further Specific Issue Hearings dealing with HRA (main development site) (11 October) and the draft Development Consent Order

4 October 2012 - Deadline 23

Closed

Letter form the ExA in response to RSPB letter regarding changes to the examination timetable and new hearings

9 October 2012 - Deadline 24

Closed

Supplementary information for Affected Persons, as defined in s.92 (5) of the Planning Act 2008 (The Planning Act) regarding Compulsory Acquisition Hearings to be held 16, 17 and 18 October 2012.

12 October 2012 - Deadline 25

Closed

Comments on responses to ExA’s second written questions. Notification of wish to make oral representations at the Specific Issue Hearings dealing with Local Impact Reports (22 October AM) and road transport (22 October PM)

16 October 2012 - Issue Specific Hearing 6

Closed

Compulsory Acquisition Hearing

17 October 2012 - Deadline 26

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to NE, MMO, RSPB and LWT Publication of the REIS Report

17 October 2012 - Issue Specific Hearing 7

Closed

Compulsory Acquisition Hearing

22 October 2012 - Deadline 27

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to ERYC

22 October 2012 - Issue Specific Hearing 8

Closed

Specific Issue Hearing on Local Impact Reports

22 October 2012 - Issue Specific Hearing 9

Closed

Specific Issue Hearing on matters regarding Road Transport

23 October 2012 - Deadline 28

Closed

ExA’s site inspection of the compensation site, the application site and the surrounding area in the company of Interested Parties Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to all Interested Parties

25 October 2012 - Deadline 29

Closed

Site inspection in the company of Interested Parties under Rule 16 of the Infrastructure Planning (Examination Procedure) Rules 2010

26 October 2012 - Deadline 30

Closed

Any written summary of the oral case put at the Compulsory Acquisition Hearings (16 and 17 October and Specific Issue Hearings dealing with road transport and Local Impact Reports (22 October) Any revised proposed requirements for inclusion within the draft Development Consent Order (including the deemed Marine Licence)

1 November 2012 - Deadline 31

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to ERYC Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to MMO

2 November 2012 - Deadline 32

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to ABP

12 November 2012 - Issue Specific Hearing 10

Closed

ISH on Compensation proposals

13 November 2012 - Deadline 33

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able

13 November 2012 - Issue Specific Hearing 11

Closed

ISH on Compensation proposals

15 November 2012 - Deadline 34

Closed

Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Able, NE, RSPB, MMO and EA

16 November 2012 - Deadline 35

Closed

Any written summary of the oral case put at the Specific Issue Hearings (12 and 13 November) Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Crown Estate

21 November 2012 - Issue Specific Hearing 12

Closed

ISH on draft Development Consent Order (DCO)/draft Deemed Marine Licence (DML)

22 November 2012 - Issue Specific Hearing 13

Closed

ISH on draft Development Consent Order (DCO)/draft Deemed Marine Licence (DML)

23 November 2012 - Deadline 36

Closed

Any written summary of the oral case put at the further Specific Issue Hearings dealing with the draft DCO/DML

27 November 2012 - Deadline 37

Closed

Decision from Secretary of State in response to ABP application made under s.98 (4) of The Planning Act 2008 Completion of the examination under s.99 of The Planning Act 2008

14 August 2024 - Invitation to comment

Closed

Invitation to comment

Invitation from the Department for Transport to make comment on:

  • Representations on the Applicant’s response to the representations published on 1 July 2024 on the request seeking a time extension to the Able Marine Energy Park Development Consent Order.