All project updates
28 Hydref 2024
The Secretary of State has made a decision to extend the completion period of the Able Marine Energy Park DCO by one year to 28 October 2025. Further construction will only be allowed in the circumstances set out in the decision letter. For further information, please refer to the decision letter (PDF, 140KB).
3 Hydref 2024
Responses to Department for Transport's request for comments on the further information submitted by the Applicant has been published.
17 Medi 2024
The Applicant’s response to the Department for Transport’s requests of 5 and 8 August 2024 has been published. The Department for Transport invites comments from all Interested Parties on this submission. The Department for Transport would be grateful for a response from Natural England by 1 October 2024
19 Awst 2024
Responses to the Department for Transport’s request of 25 July 2024 for comments on the further information supplied by the Applicant on 1 July 2024 in respect of the request seeking a time extension to the Able Marine Energy Park Development Consent Order were published on 19 August 2024
31 Gorffennaf 2024
The deadline for receipt of representations on the Applicant’s response to the representations published on 1 July 2024 on the request seeking a time extension to the Able Marine Energy Park Development Consent Order has been extended to 14 August 2024.
25 Gorffennaf 2024
The Applicant has provided a response (PDF 585KB) to the representations published on 1 July 2024 on the request seeking a time extension to the Able Marine Energy Park Development Consent Order. The Department for Transport invites any comments on the response to be submitted by 9 August 2024.
8 Gorffennaf 2024
Representations on the request seeking a time extension to the Able Marine Energy Park Development Consent Order were published on 1 July 2024. The Department for Transport invites any comments on these responses to be submitted by 22 July 2024.
14 Mehefin 2024
The deadline for receipt of representations regarding the application for the power to grant an extension to the Able Marine Energy Park Development Consent Order made by Able UK Ltd has been extended to 21 June 2024.
View the documents.
10 Mai 2024
An application for the power to grant an extension to the Able Marine Energy Park Development Consent Order has been made by Able UK Ltd. The deadline for receipt of representations is 6 June 2024.
16 Gorffennaf 2021
To view the application documents for the Material Change and to make a Relevant Representation please follow this link.
13 Mai 2021
Secretary of State Decision Letter (PDF, 205 KB)
Amendment Order (PDF, 77 KB)
Test for Likely Significant Effects Report (PDF, 1 MB)
17 Mawrth 2021
2 Mawrth 2021
Please email your comments to ablemarineenergypark@planninginspectorate.gov.uk. by 23:59 on 16 March 2021.
23 Rhagfyr 2020
10 Rhagfyr 2020
20 Tachwedd 2020
The Secretary of State now invites interested parties to comment on the Applicant’s submissions by 8 December 2020.
The Applicant has responded to the Secretary of State’s letter of 28 October 2020 with the following documents:
Covering Letter
Response to Secretary of State
Draft Amendment Order
Application Statement Rev D
Revised Shadow HRA
Indicative Masterplan
Halton Marshes Layout Core Area Buffers
16 Tachwedd 2020
Covering Letter
Response to Secretary of State
Draft Amendment Order
Application Statement Rev D
Revised Shadow HRA
Indicative Masterplan
Halton Marshes Layout Core Area Buffers
28 Hydref 2020
The Applicant is invited to respond to the Secretary of State by Thursday 12 November 2020 to provide any relevant information on the matters referred to in the letter.
23 Medi 2020
19 Medi 2018
If you wish to make a representation, this should be emailed to ablemarineenergypark@pins.gsi.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol, BS1 6PN
The deadline for receipt of representations is 29 October 2018.
4 Gorffennaf 2017
31 Hydref 2014
The Development Consent Order came into force on 29th October 2014.
10 Chwefror 2014
For further information see the [ipc_link path="https://www.parliament.uk/business/bills-and-legislation/secondary-legislation/special-procedure-orders/"]Parliament website[/ipc_link].
18 Rhagfyr 2013
For further information, please refer to the following decision documentation:
Secretary of State Decision Letter
Text of the Development Consent Order the Secretary of State intends to make
Planning Inspectorate notification of decision
See also:
Examining Authority's Findings and Recommendations with Appendices - published on 28 August 2013 (ZIP 4 MB)
18 Rhagfyr 2013
20 Tachwedd 2013
See also [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-000766-131018_TR030001_Planning%20Inspectorate%20notification%20letter.doc"]notification letter[/ipc_link] sent to interested parties on 18 October.
18 Hydref 2013
25 Medi 2013
On 24 September 2013, the Department for Transport allowed a further 3 weeks (until 16 October 2013) for the Applicant to respond to the Department’s letter of 28 August 2013. [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-002119-Applicant%20request%20to%20extend%20deadline%20for%20further%20information.pdf"]The applicant’s request for further time[/ipc_link], which explains the reasons for the request, has been published. As indicated in the Department’s letter of 28 August 2013, interested parties will have 28 days to comment on the Applicant’s response to that letter. The Department has not altered the 18 December 2013 deadline for the decision.
The Department for Transport has asked the Planning Inspectorate to make available correspondence received by the Department after the close of the examination and referred to in its "minded to approve" letter, including a [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-002150-DEFRA%20S127%20letter%20certificate%20and%20notice%20(Anglian%20Water).pdf"]certificate issued by the Secretary of State for Environment Food and Rural Affairs in relation to the Section 127 application made by the applicant[/ipc_link], two "minded to issue" letters from the Secretary of State for Energy and Climate Change in relation to the Section 127 applications made by the applicant ([ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-002149-130828_DECC%20Centrica%20s127%20letter.pdf"]Centrica letter[/ipc_link] | [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-002156-130828_DECC%20EON%20s127%20letter.pdf"]EON letter[/ipc_link]) and a [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-002259-Letter%20from%20The%20Crown%20Estate%20of%2022%20August%202013%20reporting%20on%20its%20negotiations%20with%20Able.pdf"]letter from the Crown Estate [/ipc_link]. The Department is not inviting representations on these matters.
26 Gorffennaf 2013
21 Mai 2013
25 Chwefror 2013
24 Chwefror 2013
27 Tachwedd 2012
Now that the examination is closed the Panel will no longer be able to receive written representations and submissions about this application.
The Panel must prepare a report on the application to the relevant Secretary of State, including a recommendation, within 3 months of the end of the six month examination period. The Secretary of State then has a further 3 months to make the decision on whether to grant or refuse development consent.
22 Tachwedd 2012
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001685-121120_%20TR030001_Associated%20British%20Ports.pdf"]
View Associated British Ports Letter[/ipc_link]
Able Humber Ports Ltd responded to Associated British Ports letter to The Secretary of State for Transport on the 22 November 12.
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001691-121122%20TR030001%20Able%20Humber%20Ports%20Ltd.pdf"]View Able Humber Ports Ltd letter[/ipc_link]
The Secretary of State for Transport has responded to Associated British Ports letter.
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001488-121127_TR030001_Secretary%20of%20State%20response%20to%20application%20by%20ABP%20under%20s98%20(4)%20of%20PA2008.pdf"]View The Secretary of State for Transport Letter[/ipc_link]
19 Tachwedd 2012
- [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001850-The%20Examining%20Authority.15%20November%202012.pdf"]Able Humber Ports Ltd[/ipc_link] on 15 November
- [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001851-The%20Examining%20Authority%2015-11-2012.pdf"]Able Humber Ports Ltd, Natural England, Environment Agency, Marine Management Organisation and Royal Society for the Protection of Birds[/ipc_link] on 15 November
- [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001853-The%20Examining%20Authority"]The Crown Estate[/ipc_link] on 16 November
15 Tachwedd 2012
12 Tachwedd 2012
12 Tachwedd 2012
9 Tachwedd 2012
8 Tachwedd 2012
7 Tachwedd 2012
26 Hydref 2012
17 Hydref 2012
16 Hydref 2012
10 Hydref 2012
5 Hydref 2012
4 Hydref 2012
2 Hydref 2012
17 Medi 2012
12 Medi 2012
11 Medi 2012
17 Awst 2012
15 Awst 2012
In addition we have produced [ipc_link path="/wp-content/ipc/uploads/projects/TR030001/2.%20Post-Submission/Procedural%20Decisions/120815%20TR030001%20AMEP%20Examination%20Timetable.pdf"]the timetable in calendar format[/ipc_link] in order to assist understanding of the various deadlines and events.
26 Gorffennaf 2012
19 Gorffennaf 2012
13 Gorffennaf 2012
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001865-Able%20Marine%20Energy%20Park%20draft%20DCO%20Specific%20Issue%20Hearing%20Part%201.mp3"]Part 1[/ipc_link] (MP3 109 MB)
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001866-Able%20Marine%20Energy%20Park%20draft%20DCO%20Specific%20Issue%20Hearing%20Part%202.mp3"]Part 2[/ipc_link] (MP3 77 MB)
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001867-Able%20Marine%20Energy%20Park%20draft%20DCO%20Specific%20Issue%20Hearing%20Part%203.mp3"]Part 3[/ipc_link] (MP3 42 MB)
11 Gorffennaf 2012
10 Gorffennaf 2012
[ipc_link path="/wp-content/ipc/uploads/projects/TR030001/TR030001-001883-DRAFT%20DCO%20Hearing%20agenda%20letter.doc"]Letter[/ipc_link] issued on 4 July by examining authority dealing with the Specific Issue Hearing considering the draft Development Consent Order to be held on 12 July 2012.
19 Mehefin 2012
31 Mai 2012
Procedural decision following Preliminary Meeting.
24 Mai 2012
1 Mai 2012
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.