There are no deadlines and events
Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 9 November 2011
The examination closed on 22 March 2012
9 November 2011 - Deadline 1
ClosedPreliminary Meeting
9 November 2011 - Preliminary Meeting
ClosedPreliminary Meeting
15 November 2011 - Deadline 2
ClosedNotice by Examining Authority (ExA) of procedural decision including confirmation of the examination timetable and written questions from the ExA under Rule 8 of the Infrastructure Planning (Examination Procedure) Rules 2010
21 November 2011 - Deadline 3
ClosedNotice by ExA of site inspection in the company of Interested Parties under Rule 16 of the Infrastructure Planning (Examination Procedure) Rules 2010
6 December 2011 - Deadline 4
ClosedExA’s site inspection in the company of Interested Parties
8 December 2011 - Deadline 5
ClosedDeadline for receipt by the ExA of:
•Written representations •Responses to written questions
9 January 2012 - Deadline 6
ClosedDeadline for receipt by ExA of:
•Statements of Common Ground •Local Impact Report(s) •Written comments on responses to ExA’s written questions •Written comments on Relevant Representations •Written comments on Written representations •Notification of wish to make oral representations at any Open-floor, Compulsory acquisition or Issue specific hearings
13 January 2012 - Deadline 7
ClosedNotice by ExA of:
•Requests for further information and written comments under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 •Hearings under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010 •Extension to deadline for written comments on Written representation submitted by the Environment Agency.
6 February 2012 - Deadline 8
ClosedDeadline for receipt by ExA of:
•Written comments on Statements of Common Ground •Written comments on any Local Impact Report(s) •Written responses to ExA’s requests for further information and written comments •Written comments on the Written Representation submitted by the Environment Agency.
14 February 2012 - Deadline 9
ClosedOpen-floor hearing (am)
14 February 2012 - Deadline 10
ClosedIssue specific hearing on draft Development Consent Order (DCO); Order plans; drawings and documents (Session 1) (pm)
14 February 2012 - Open Floor Hearing
ClosedOpen Floor Hearing
14 February 2012 - Issue Specific Hearing
ClosedHearing on the specific issue on the draft DCO, order plans, drawings and documents
15 February 2012 - Deadline 11
ClosedIssue specific hearing on draft DCO; Order plans; drawings and documents (Session 2)
21 February 2012 - Deadline 12
ClosedCompulsory acquisition hearing (Session 1)
21 February 2012 - Compulsory Acquisition Hearing
ClosedCompulsory Acquisition Hearing
22 February 2012 - Deadline 13
ClosedCompulsory acquisition hearing (Session 2)
29 February 2012 - Deadline 14
ClosedDeadline for receipt by ExA of:
•Written comments on responses to ExA’s requests for further information and written comments •Any written summary of any case put forward at any hearing
2 March 2012 - Deadline 15
ClosedNotice of ExA’s requests for further information and written comments under Rules 17 and 8(1)(k) of the Infrastructure Planning (Examination Procedure) Rules 2010 inviting final comments on the draft DCO
13 March 2012 - Deadline 16
ClosedDeadline for receipt by ExA of final comments on the draft DCO
22 March 2012 - Deadline 17
ClosedNotification by ExA of completion of the examination