Daventry International Rail Freight Terminal Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 8 July 2013

Caeodd yr archwiliad ar 8 January 2014

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

8 Gorffennaf 2013 - Preliminary Meeting

Caeedig

Preliminary Meeting for DIRFT 3

15 Gorffennaf 2013 - Deadline 1

Caeedig

Issue of:

  • Procedural timetable
  • Examining Authority’s (ExA) first written questions

19 Gorffennaf 2013 - Site Visit (Accompanied)

Caeedig

Accompanied site visit

14 Awst 2013 - Deadline 2

Caeedig

Deadline for receipt by the ExA of:

  • Comments on relevant representations (RRs) already received
  • Summaries of all RRs exceeding 1500 words
  • Written representations (WRs) by all interested parties
  • Summaries of all WRs exceeding 1500 words
  • Local Impact Report(s) (LIR) from local authorities
  • Responses to the ExA’s first written questions
  • Statements of Common Ground from the applicant
  • Revised version of the draft Development Consent Order from the applicant

30 Awst 2013 - Issue Specific Hearing 1

Caeedig

First hearing on draft development consent order

13 Medi 2013 - Deadline 3

Caeedig

Deadline for receipt by the ExA of:

  • Comments on WRs and responses to comments on RRs
  • Comments on LIRs
  • Comments on responses to the ExA's first written questions

20 Medi 2013 - Deadline 4

Caeedig

Issue of the ExA’s further written questions

11 Hydref 2013 - Deadline 5

Caeedig

Deadline for receipt by the ExA of:

  • Requests for any issue specific hearings, compulsory acquisition and open floor hearings
  • Responses to Examining Authority's further written questions

22 Hydref 2013 - Issue Specific Hearing 2

Caeedig

Second hearing on draft DCO

25 Hydref 2013 - Deadline 6

Caeedig

Notification by the ExA of date, time and place of:

  • Open floor hearing (if requested)
  • Compulsory acquisition hearing (if requested)
  • Any issue specific hearings (in the event the ExA decides during the progress of the examination that they are needed)

1 Tachwedd 2013 - Deadline 7

Caeedig

Deadline for receipt by the ExA of:

  • Comments on responses to ExA's further written questions

18 Tachwedd 2013 - Deadline 8

Caeedig

Deadline for submission to the ExA of the final draft DCO and completed s106 undertaking(s) and Period reserved (18 November to 29 November) for final draft DCO hearing, any other issue specific hearings, compulsory acquisition and open floor hearings

27 Tachwedd 2013 - Issue Specific Hearing 3

Caeedig

Third hearing on draft DCO

27 Tachwedd 2013 - Open Floor Hearing

Caeedig

Open Floor Hearing

20 Rhagfyr 2013 - Deadline 9

Caeedig

Deadline for receipt by the ExA of:

  • Written comments on the Draft National Policy Statement (NPS) for the National Road and Rail Networks