1. Section 51 advice
  2. Advice in detail

Advice to Ashfield Land Management Limited and Gazeley GLP N

Back to list

Enquiry

From
Ashfield Land Management Limited and Gazeley GLP N
Date advice given
16 October 2018
Enquiry type
Phone

A series of telephone calls took place on 16 to 19 October 2018 in order for the Planning Inspectorate to set out some concerns identified with the application, and in order to give the applicant the opportunity to direct the Inspectorate within the application to documents which may address the concerns.

Advice given

The Planning Inspectorate highlighted some inconsistencies between certain documents and plans, conflicting internal references between and within documents and some inconsistencies between the hard and electronic copy of the submitted application in regard to the following documents: - Works plans - Draft DCO - Environmental Statement - Parameters plan Please see the letter confirming that the application was not accepted: https://infrastructure.planninginspectorate.gov.uk/wp-content/ipc/uploads/projects/TR050004/TR050004-002909-181019_Notification%20of%20Decision%20Not%20to%20Accept%20Application.pdf