Cambridge Waste Water Treatment Plant Relocation Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 17 October 2023

The examination closed on 17 April 2024

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

10 October 2023 - Procedural Deadline A

Closed

Procedural Deadline A

Deadline for receipt by ExA of:

  • Notification of wish to speak at the Preliminary Meeting
  • Notification of wish to speak at the Open Floor Hearing
  • Notification of wish to speak at Hearings on 18th October 2023
  • Applicant's proposed itinerary for an Accompanied Site Inspection (ASI)1

17 October 2023 - Preliminary Meeting (PM)

Closed

Preliminary Meeting (PM)

17 October 2023 - Open Floor Hearing 1 (OFH1)

Closed

Open Floor Hearing 1 (OFH1)

18 October 2023 - Issue Specific Hearing 1 (ISH1)

Closed

Issue Specific Hearing 1 (ISH1)

  • draft Development Consent Order (dDCO)

18 October 2023 - Issue Specific Hearing 2 (ISH2)

Closed

Issue Specific Hearing 2 (ISH2)

  • The principle of the Proposed Development

20 November 2023 - Deadline 1 (D1)

Closed

Deadline 1 (D1)

Deadline for receipt by the ExA of:

  • Written Representations (WR) (including summaries of all WR exceeding 1500 words)
  • Responses to ExA’s ExQ1
  • Comments on Relevant Representations (RR)
  • Written summaries of oral submissions made at any hearings
  • Comments on the Applicant's change request
  • Comments on the Applicant’s proposed ASI itinerary received at PDA
  • Notification of wish to attend an ASI
  • Notification of wish to speak at an Open Floor Hearing
  • Notification of wish to speak at a Compulsory Acquisition Hearing
  • Notification by any Statutory Parties who have not submitted a RR of their wish to be considered as an Interested Party
  • Comments on any updated application documents
  • Responses to any further information requested by the ExA for this deadline

From Local Authorities

  • Local Impact Report (LIR)

From the Applicant

  • An updated dDCO
  • A Schedule of Changes to the dDCO
  • Updated Explanatory Memorandum (EM)
  • An application documents tracker
  • Updated Book of Reference (BoR)
  • Updated Schedule of Changes to the BoR
  • The Compulsory Acquisition (CA) Schedule
  • Initial Statements of Common Ground (SoCG) requested by ExA
  • Initial Principal Areas of Disagreement Statement (PADS)

6 December 2023 - Deadline 2 (D2)

Closed

Deadline 2 (D2)

Deadline for receipt by the ExA of:

  • Comments on WR
  • Responses to comments on RR
  • Comments on responses to ExA’s ExQ1
  • Comments on LIR
  • Comments on any submissions received at D1
  • Responses to any further information requested by the ExA for this deadline

From the Applicant

  • Updated proposed ASI itinerary
  • An updated dDCO
  • An updated Schedule of Changes to the dDCO
  • Updated EM
  • An updated application documents tracker
  • Updated BoR
  • Schedule of Changes to the BoR
  • An updated CA Schedule
  • Progressed SoCG
  • Updated PADS

18 December 2023 - Deadline 3 (D3)

Closed

Deadline 3 (D3)

Deadline for receipt by the ExA of:

  • Responses to comments on WR
  • Responses to comments on LIR
  • Comments on any submissions received at D2
  • Responses to any further information requested by the ExA for this deadline

From the Applicant

  • An updated dDCO
  • An updated Schedule of Changes to the dDCO
  • Updated EM
  • An updated application documents tracker
  • Updated BoR
  • Schedule of Changes to the BoR
  • An updated CA Schedule
  • Progressed SoCG
  • Updated PADS
  • Updated draft s106 agreements

8 January 2024 - Accompanied Site Inspection

Closed

Accompanied Site Inspection (ASI)

** Cancelled **

9 January 2024 - Compulsory Acquisition Hearing 1 (CAH1)

Closed

Compulsory Acquisition Hearing 1 (CAH1)

10 January 2024 - Issue Specific Hearing 3 (ISH3) Day 1

Closed

Issue Specific Hearing 3 (ISH3) Day 1 - environmental matters

Two day hearing taking place on Wednesday 10 January and Thursday 11 January 2024

11 January 2024 - Issue Specific Hearing 3 (ISH3) Day 2

Closed

Issue Specific Hearing 3 (ISH3) Day 2 - environmental matters

Two day hearing taking place on Wednesday 10 January and Thursday 11 January 2024

22 January 2024 - Deadline 4 (D4)

Closed

Deadline 4 (D4)

Deadline for receipt by the ExA of:

  • Written summaries of oral submissions made at any hearings
  • Comments on any submissions received at D3
  • Responses to any further information requested by the ExA for this deadline

From the Applicant

  • An updated dDCO
  • An updated Schedule of Changes to the dDCO
  • Updated EM
  • An updated application documents tracker
  • Updated BoR
  • Schedule of Changes to the BoR
  • An updated CA Schedule
  • Progressed SoCG
  • Updated PADS

31 January 2024 - Publication of ExQ 2

Closed

Publication by the ExA of:

  • ExA’s Second Written Questions (ExQ2) (if required)

19 February 2024 - Deadline 5 (D5)

Closed

Deadline 5 (D5)

Deadline for receipt by the ExA of:

  • Responses to ExQ2 (if required)
  • Comments on any submissions received at D4
  • Responses to any further information requested by the ExA for this deadline

From the Applicant

  • An updated dDCO
  • An updated Schedule of Changes to the dDCO
  • Updated EM
  • An updated application documents tracker
  • Updated BoR
  • Schedule of Changes to the BoR
  • An updated CA Schedule
  • Progressed SoCG
  • Updated PADS

5 March 2024 - Publication by the ExA 2

Closed

Publication by the ExA of:

  • The ExA’s schedule of changes to the dDCO (if required)
  • Report on Implications for European Sites (RIES) (if required)

12 March 2024 - Accompanied Site Inspection (Rescheduled visit)

Closed

Accompanied Site Inspection (Rescheduled visit)

13 March 2024 - Issue Specific Hearing 4 (ISH4) Day 1

Closed

Issue Specific Hearing 4 (ISH4) Day 1

14 March 2024 - Issue Specific Hearing 4 (ISH4) Day 2

Closed

Issue Specific Hearing 4 (ISH4) Day 2

21 March 2024 - Publication by the ExA 3

Closed

Publication by the ExA of:

  • ExA’s Third Written Questions (ExQ3) (if required)

2 April 2024 - Deadline 6 (D6)

Closed

Deadline 6 (D6)

Deadline for receipt by the ExA of:

  • Responses to ExQ3 (if required)
  • Comments on the ExA’s proposed schedule of changes to the dDCO (if required)
  • Updated EM
  • Comments on the RIES (if required)
  • Final draft s106 agreements
  • Written summaries of oral submissions made at any hearings
  • Comments on any submissions received at D5
  • Responses to any further information requested by the ExA for this deadline

9 April 2024 - Issue Specific Hearing 5 (ISH5)

Closed

Issue Specific Hearing 5 (ISH5) - Traffic and transport

12 April 2024 - Deadline 7 (D7)

Closed

Deadline 7 (D7)

Deadline for receipt by the ExA of:

  • Closing submissions
  • Comments on any submissions received at D6
  • Responses to any further information requested by the ExA for this deadline

From the Applicant

  • A finalised and validated version of the dDCO
  • A finalised Schedule of Changes to the dDCO
  • Finalised EM
  • A finalised application documents tracker
  • Finalised BoR
  • Final Schedule of Changes to the BoR
  • Finalised CA Schedule
  • Finalised SoCG
  • Finalised PADS
  • Finalised Statement of Reasons
  • Completed s106 agreements

17 April 2024 - Deadline 8 (D8)

Closed

Deadline 8 (D8)

Deadline for receipt by the ExA of:

  • Responses to any further information requested by the ExA for this deadline

The ExA must complete the Examination within six months