Advice to Ceredigion County Council
Back to listEnquiry
- From
- Ceredigion County Council
- Date advice given
- 10 December 2010
- Enquiry type
Do you publish the Local Impact Report documents on your website along with the other Project Documents? I’ve been trying to find an example of an LIR that has been submitted to yourselves.
Advice given
Rule 8 of The Infrastructure Planning (Examination Procedure) Rules 2010 (the 2010 Rules) requires the Examining Authority (ExA) at, or soon after the end of, the Preliminary Meeting to set a timetable for its examination of the application. This includes a provision for setting a date under Rule8(1)(j) of the 2010 Rules by which the local impact report must be received by the Commission and the period within which an interested party will have the opportunity to make comments on that report.
To date, only one Development Consent Order (DCO) application has been accepted by the Commission and this is currently at the pre-examination stage. The Preliminary Meeting for this DCO application has not yet been held and the Commission has not therefore received any LIRs pertaining to any DCO applications.
Under Rule 21 of the 2010 Rules, the Commission is required to make all representations and documents available to interested parties and any LIRs will therefore be made available at the appropriate time.
I attach IPC Advice Note 1 for your reference.