Ymholiad

Oddiwrth
Environmental Agency
Y dyddiad y rhoddwyd y cyngor
21 Chwefror 2011
Math o ymholiad
Email

When does the developer have to submit the statement of common ground?

Cyngor a roddwyd

For clarification, a Statement of Common Ground is not required to be submitted as part of the initial application submission to the IPC, it will be required (where appropriate) to be submitted during the examination stage. We do however encourage all parties to undertake preparatory work on such statements as early as possible in the process.

Shortly after the preliminary meeting is held, the Examining authority will set a deadline for receipt of the statement of common ground.