Advice to Public Health Wales
Back to listEnquiry
- From
- Public Health Wales
- Date advice given
- 21 June 2010
- Enquiry type
- Phone
Mr Brunt had received a consultation request from Covanta and wanted clarification as to where in the process the application is.
Advice given
The Brig Y Cwn project is currently in the pre-application stage. As such, the promoter has a duty to consult Health Boards (amongst others) under s42 of the Planning Act 2008. Once an application is made, the Commission will determine whether or not it can accept the application for examination. If the application is accepted, the Health Board will be treated as an interested party for the purposes of the examination, and is thereby entitled to make relevant and detailed representations.