Yn ôl i'r rhestrYmholiad
- Oddiwrth
- Pegasus Group
- Y dyddiad y rhoddwyd y cyngor
- 5 Gorffennaf 2016
- Math o ymholiad
I am looking for a timeline chart that shows the NSIP process stages, and the length of anticipated time to complete each one.
I recall a thirty-odd page document setting out the details of the process for applicants. Where would I find this please?
Cyngor a roddwyd
Thank you for your email.
Advice Note 8.1 has a timeline chart that shows the NSIP process stages: https://infrastructure.planninginspectorate.gov.uk/wp-content/uploads/2013/04/Advice-note-8-1v4.pdf
The Planning Inspectorate offers a free pre-application service for developers, the pre-application prospectus is now available on our website. This document sets out the Planning Inspectorate’s service for applicants at the pre-application stage of the nationally significant infrastructure planning process: https://infrastructure.planninginspectorate.gov.uk/wp-content/uploads/2014/05/NSIP-prospectus_May2014.pdf
Planning Act 2008: guidance on the pre-application process sets out the requirements and procedures for the pre-application process and consultation for major infrastructure projects: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/418009/150326_Pre-Application_Guidance.pdf
Further guidance documents produced by DCLG which may be helpful can be found under the following link: https://infrastructure.planninginspectorate.gov.uk/legislation-and-advice/guidance/
The Planning Inspectorate has produced a suite of Advice notes which cover a range of process matters. These can be found under the following link: https://infrastructure.planninginspectorate.gov.uk/legislation-and-advice/advice-notes/
If the information provided is not what you were looking for, please do not hesitate to contact us.