Cyngor i Pegasus Group

Yn ôl i'r rhestr

Ymholiad

Oddiwrth
Pegasus Group
Y dyddiad y rhoddwyd y cyngor
5 Gorffennaf 2016
Math o ymholiad
Email

I am looking for a timeline chart that shows the NSIP process stages, and the length of anticipated time to complete each one.

I recall a thirty-odd page document setting out the details of the process for applicants. Where would I find this please?

Cyngor a roddwyd

Thank you for your email.

Advice Note 8.1 has a timeline chart that shows the NSIP process stages: https://infrastructure.planninginspectorate.gov.uk/wp-content/uploads/2013/04/Advice-note-8-1v4.pdf

The Planning Inspectorate offers a free pre-application service for developers, the pre-application prospectus is now available on our website. This document sets out the Planning Inspectorate’s service for applicants at the pre-application stage of the nationally significant infrastructure planning process: https://infrastructure.planninginspectorate.gov.uk/wp-content/uploads/2014/05/NSIP-prospectus_May2014.pdf

Planning Act 2008: guidance on the pre-application process sets out the requirements and procedures for the pre-application process and consultation for major infrastructure projects: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/418009/150326_Pre-Application_Guidance.pdf

Further guidance documents produced by DCLG which may be helpful can be found under the following link: https://infrastructure.planninginspectorate.gov.uk/legislation-and-advice/guidance/

The Planning Inspectorate has produced a suite of Advice notes which cover a range of process matters. These can be found under the following link: https://infrastructure.planninginspectorate.gov.uk/legislation-and-advice/advice-notes/

If the information provided is not what you were looking for, please do not hesitate to contact us.