Register of advice
This list is a record of general advice provided by the Planning Inspectorate. We publish this to comply with the 2008 Planning Act.
Project specific advice can be viewed on the relevant project page.
Search advice
Search by key words or the name of person the advice was given to.
Showing 1 to 100 of 697 entries, newest first.
Results per page View 25 results per page | View 50 results per page | 100
-
View advice to Pegasus Group
Request confirmation that a proposed solar farm should not be determined as a Nationally Significant Infrastructure Project
-
View advice to Flotation Energy and EnBW/bp
Lastly, since out meeting, the Project has been reviewing our approach to the Information to Support Appropriate Assessment (ISAA) and I would like to seek the Inspectorate’s view. The ISAA will form... Read more
-
View advice to Jonathan Dean
During the examination of an NSIP does an Interested Party have a statutory right to present during the examination, and if so, which regulation permits this?”
-
View advice to The Mineral Planning Group Ltd
Request confirmation that a proposed development should not be determined as a Nationally Significant Infrastructure Project.
-
View advice to David Rogers
Please see attached.
-
View meeting with National Highways
Project update and draft documents feedback review.
-
View advice to Russ Tucker
Please see attached.
-
View advice to Stop Botley West
Please see attached.
-
View advice to Aldham Parish council
Has another request for info been issued by the PI recently on the Norwich to Tilbury Pylons please. Another village has sent me a copy of a reponse they have sent to Briston but Aldham Parish Council... Read more
-
View advice to West Bergholt Parish Council
Please see attached
-
View advice to Various enquirers
Various representations about the merits of the Proposed Development.
-
View advice to David Rogers
Please see attached.
-
View advice to Nigel Pearce
Please see attached.
-
View advice to John Webley
Please see attached.
-
View advice to Alex Maidment
I strongly object to the plans for Gatwick expansion using a the conversion of the emergency runway approach. It will have a serious adverse effect on the environment and the well being of humans and... Read more
-
View advice to James Freeman
I would be grateful if you could advise on whether PINS are ok with handling a covering letter to a Joint Authority AoC response which includes the electronic signatures of ten senior officers from... Read more
-
View meeting with Gatroben Developments 2 Limited
The Planning Inspectorate (the Inspectorate) attended the initial Steering Group meeting for the Dogger Bank D Wind Farm, held via Teams on 12 July 2023. The meeting focused on the Applicant’s... Read more
-
View advice to West Sussex County Council
As you are aware, the ten Gatwick local authorities are working collectively on the Northern Runway Project. With regard to Adequacy of Consultation (AoC), the authorities propose to submit a joint... Read more
-
View advice to Merton Council
Merton Council queried whether it could be included in correspondence from the Planning Inspectorate regarding the adequacy of the Applicant’s Pre-application consultation.
-
View advice to Communities Against Gatwick Noise and Emissions
The enquirer expressed an intention to register as an Interested Party in respect of the scheme, and requested further details.
-
View advice to Anonymous
Section 3.3.60 of the Draft Overarching National Policy Statement for Energy (EN-1) reads: “subject to any legal requirements, the urgent need for CNP Infrastructure to achieving our energy... Read more
-
View advice to Anonymous
I am delighted to hear that there will now be a review of the offshore alternative to East Anglia Green proposals set out by National Grid, but having studied the terms of the National Grid ESO review... Read more
-
View advice to Panos Konidaris
Enquiry in relation to a high security control centre. Section 14 of the 2008 Planning Act sets out the projects which may be considered to be NSIP and the above development does not appear to be... Read more
-
View advice to Panos Konidaris
Enquiry in relation to a high security control centre. Section 14 of the 2008 Planning Act sets out the projects which may be considered to be NSIP and the above development does not appear to be... Read more
-
View advice to SASES
Please see attached.
-
View advice to Marc vlessing
Please see attached
-
View meeting with Elgin Energy and Pegasus Group
Project Inception Meeting.
-
View advice to Office for Health Improvement and Disparities at t
The Infrastructure Planning (Application: Prescribed Forms and Procedure) Regulations 2009 Schedule 1 sets out pre-application statutory consultees. A number of these organisations no longer exist.... Read more
-
View advice to Michael Mahony SASES
Please see attached
-
View advice to Department for Levelling, Housing and Communities
A letter, dated 22 March 2023, to London Resort Company Holdings (the applicant for the London Resort project) from Lee Rowley MP, Parliamentary Under Secretary of State for Local Government and... Read more
-
View meeting with Applicant & Anglian Water
Project update meeting
-
View advice to Thurrock Council
To update PINS, please note that the Council continues to discuss with NH the PPA that it is willing to offer with regards to its LTC DCO submission. In the meantime all engagement on the LTC DCO has... Read more
-
View advice to Essex, Suffolk, Norfolk Pylons
We are the umbrella community campaign group for residents along the 180km route of East Anglia GREEN. On 16 June we submitted an 80-page technical response to the non-statutory consultation. It... Read more
-
View meeting with Gatwick Officers Group
In relation to post-submission, we have a specific question at this stage about process. Our understanding was that the post-acceptance/pre-examination stage would take three months but GAL has... Read more
-
View meeting with National Grid Electricity Transmission (NGET)
Project update meeting.
-
View meeting with Tonbridge and Malling Borough Council and Kent Cou
Project Meeting Note
-
View meeting with Some Local Authorities impacted by the scheme
Tripartite Meeting Part One.
-
View meeting with National Highways and some Local Authorities
Tripartite Meeting Part Two.
-
View meeting with National Grid Ventures
Project Inception Meeting.
-
View advice to Newark and Sherwood District Council
The Council has received two separate planning applications on directly adjacent sites for two 49.9MW solar farms. They have been submitted by the same agent, on behalf of different companies logged... Read more
-
View meeting with Alfanar Energy Limited
Project Inception Meeting.
-
View meeting with Highways England
Project update meeting.
-
View advice to 7000 Acres
Good evening, We as members of the local community being affected by large scale solar have found it necessary to form the "Seven Thousand Acres" action group in direct response to the proposals from... Read more
-
View advice to Drax Power Limited
We note that Reg 5(3) of the APFP Regulations requests that: (3) Any plans, drawings or sections required to be provided by paragraph (2) shall be no larger than A0 size, shall be drawn to an... Read more
-
View advice to Anonymous
Phone call with Thurrock Council
-
View advice to Offshore Wind
Dear Sir/Madam, I work for a UK based offshore wind energy consultancy called BVG Associates and am currently trying to understand the permitting requirements across the UK. Can you please help answer... Read more
-
View advice to Thurrock Council – anon
Phone call with Thurrock Council
-
View meeting with GL Hearn
Inception Meeting
-
View advice to Sandra Betts
in relation to Nationally Significant Infrastructure Projects (NSIPS) in the Norfolk County Council area
-
View advice to Gatwick Area Conservation Campaign
In relation to the baselines Gatwick has proposed for the project in its consultation (which we note have changed from the baselines proposed in its Scoping Report), you say: "they are not matters... Read more
-
View meeting with Highways England
Project Meeting Update.
-
View meeting with Highways England
Project Update Meeting.
-
View meeting with Highways England
Project Update Meeting.
-
View advice to Debbie Bryce
Enquiry about the status of an emerging National Policy Statement for the purposes of making a decision on an application for a Development Consent Order.
-
View meeting with National Grid Carbon
Project inception meeting.
-
View advice to Corylus Planning and Environmental Ltd
Good Afternoon, I have a relatively straightforward question that I have ben unable to find the answer for on your website. I have been asked to look at a potential large scale solar park. I... Read more
-
View advice to Graham Fraley
Dear Sirs I am trying to clarify procedure. If a local council gives planning permission for groundwork investigation related to a NIP and groundworks are clearly for a larger project should the local... Read more
-
View advice to Horus Capital
Subject: Solar PV NSIP planning Dear James, We have been in touch before in relation to the requirements for NSIP on solar PV projects. Horus is starting the development of 3 single and independent... Read more
-
View advice to Amy Moseley
Good Afternoon, I am doing some research around Strategic Rail Freight Interchange. I found a recent article covering the refused Rail Freight Interchange in North Yorkshire outside Sherburn.... Read more
-
View advice to David Lyon
Dear Sir or Madam, I wonder if you can help, I manage, together with several of my colleagues a number of large offshore high voltage electrical windfarm connections with cables onshore and offshore... Read more
-
View advice to Clare Coombes
Dear Sirs I’m hoping you can assist me. I currently live in Easthorpe, Essex which could or could not be affected by the A12 widening scheme. I have spoken to the Highway’s Agency who have told me the... Read more
-
View advice to Natural England
Natural England wished to discuss the Planning Inspectorate’s process from the point of application with respect to the information supplied by an applicant to support an assessment under the... Read more
-
View advice to Anonymous
Hi there We’re acting on behalf of a number of NSIP projects looking to undertake statutory consultation over the next few month. Are you providing any guidance on pre-application consultation... Read more
-
View advice to West Devon Borough Council
Dear Sir/Madam, We have had an EIA Screening Request relating to the addition of a 50MW black start facility to an existing 900MW gas fired power station. Given the scale of the project, could you... Read more
-
View meeting with SSE
Inception meeting.
-
View meeting with Civil Aviation Authority
Meeting to discuss Airspace matters specifically in respect of NSIP aviation projects
-
View meeting with Independent Commission on Civil Aviation Noise
Introduction and general process meeting specifically in respect of NSIP aviation projects
-
View meeting with Innogy Renewables UK
Note of the inception meeting for Galloper Offshore Windfarm Extension project
-
View advice to Derby City Council
Please see attached document
-
View advice to Cheshire West and Chester Borough Council
Dear Sir/Madam, I have been liaising with a developer in respect of a potential project for electricity generation utilising compressed air which would be stored underground using pre-existing caverns... Read more
-
View advice to Medway Council
Dear Inspectorate. I am a planning officer working for the Medway Council. I am writing to seek your advice with regard to the above proposal. Medway Council is about to receive two separate planning... Read more
-
View meeting with Anonymous
Please see attached.
-
View advice to Storelectric Ltd
Dear Mr Johannson as promised my notes to the C&W planning office, just to clarify the base application uses a compressor of under 50MW and generation is under 50MW, in this case we see no problem and... Read more
-
View meeting with Civil Aviation Authority
Meeting to discuss Airspace matters specifically in respect of NSIP aviation projects
-
View meeting with Anonymous
Please see attached.
-
View meeting with Highways England
A12 Chelmsford to A120 project update meeting
-
View meeting with Intertek
Please see attached
-
View meeting with Anonymous
Meeting Note
-
View meeting with Invicta
Inception meeting
-
View meeting with Anonymous
Inception Meeting Note
-
View meeting with Civil Aviation Authority
Meeting to discuss Airspace matters specifically in respect of NSIP aviation projects
-
View advice to Cierco and the Welsh Government
Inception meeting between Cierco ,The Planning Inspectorate and The Welsh Government
-
View advice to Adem Mehmet
Dear Adem, Thank you for your enquiry regarding statutory requirements for applicants. Statutory requirements are in regards to funding. Please see Regulation 5 (h) — ‘Applications for orders... Read more
-
View meeting with Equinor UK
Project Update Meeting
-
View advice to Jacobs Environment, Maritime & Resilience
Can you please advise if it possible to extend the time period for implementation of a previously consented DCO scheme?
-
View advice to Chris Purslow
Hello, Could you please confirm if Parish Councils would be considered a statutory stakeholder for a DCO application under the 2008 Planning Act if located in a host local authority ward or if in... Read more
-
View advice to A Henderson
Please could you confirm whether it is possible to submit a DCO application in outline, following by subsequent reserved matters? If so, please can you provide some further details on the process?
-
View advice to Stephen Blyth
Is it possible for a husband and wife to register separately as interested parties if they have the same email address?
-
View advice to Welsh Government
have a query relating to section 92 of the 2008 Act which I wondered if you could help with. 92(2) states: “The Examining authority must fix, and cause each affected person to be informed of, the... Read more
-
View advice to Kettering Borough Council
Query regarding the Planning Act 2008 (PA2008) process, definitions of highway Nationally Significant Infrastructure Projects (NSIPs) and consultation requirements.
-
View advice to James Wilson
We are part of a team assessing the feasibility of a pipeline project in Dorset. The location and route of the pipeline is Portland Port to the NTS at Mappower, Dorset. In 2007 a project was... Read more
-
View advice to Waitrose
I am enquiring about registering as an interested party for a nationally significant infrastructure project. An individual appears to need to state how the proposed infrastructure project is going to... Read more
-
View advice to National Grid
Discussion regarding the s52 authorisation request process
-
View advice to Jonathan Dean
Do the NPSs, in particular EN-1, 5 & 6 have a "fixed life" or are they in place until superseded?
-
View advice to Grey Friars Investments
I would be grateful if you would confirm the number of DCO applications in the 5 years to April 2018 that have been withdrawn during the 28 acceptance period (i.e. after the submission but prior to a... Read more
-
View advice to General - anon
Compilation of advice about the Environmental Impact Assessment scoping process, undertaken by the Planning Inspectorate on behalf of the Secretary of State.
-
View advice to Ivan Stone
Does PINS have responsibility for enforcing (monitoring, revoking) a DCO once it has been granted. If development is not in line with the DCO what is PINS role? Who is responsible for monitoring and... Read more
-
View advice to Anonymous
Is it correct that an applicant for a DCO must provide copies of relevant documents to members of the public during public consultation?
-
View meeting with Hartlepool Borough Council
Project Inception Meeting - Hartlepool Western Growth Corridor
-
View advice to Mick George Ltd
• What point should a waste application be considered to be submitted as a NSIP? (is there a threshold ie size, annual import, waste type ie hazardous, etc) • Is there any point when an NSIP is... Read more