Register of advice
This list is a record of general advice provided by the Planning Inspectorate. We publish this to comply with the 2008 Planning Act.
Project specific advice can be viewed on the relevant project page.
Search advice
Search by key words or the name of person the advice was given to.
Showing 101 to 200 of 727 entries, newest first.
Results per page View 25 results per page | View 50 results per page | 100
-
View advice to Medway Council
Dear Inspectorate. I am a planning officer working for the Medway Council. I am writing to seek your advice with regard to the above proposal. Medway Council is about to receive two separate planning ... Read more
-
View meeting with A66 Northern Trans-Pennine Project
Please see attached.
-
View advice to Storelectric Ltd
Dear Mr Johannson as promised my notes to the C&W planning office, just to clarify the base application uses a compressor of under 50MW and generation is under 50MW, in this case we see no problem and... Read more
-
View meeting with Civil Aviation Authority
Meeting to discuss Airspace matters specifically in respect of NSIP aviation projects
-
View meeting with Environment Agency
Please see attached.
-
View meeting with Highways England
A12 Chelmsford to A120 project update meeting
-
View meeting with Intertek
Please see attached
-
View meeting with Equinor UK
Meeting Note
-
View meeting with Invicta
Inception meeting
-
View meeting with Island Green Power
Inception Meeting Note
-
View meeting with Civil Aviation Authority
Meeting to discuss Airspace matters specifically in respect of NSIP aviation projects
-
View advice to Cierco and the Welsh Government
Inception meeting between Cierco ,The Planning Inspectorate and The Welsh Government
-
View advice to Adem Mehmet
Dear Adem, Thank you for your enquiry regarding statutory requirements for applicants. Statutory requirements are in regards to funding. Please see Regulation 5 (h) — ‘Applications for orders g... Read more
-
View meeting with Equinor UK
Project Update Meeting
-
View advice to Jacobs Environment, Maritime & Resilience
Can you please advise if it possible to extend the time period for implementation of a previously consented DCO scheme?
-
View advice to Chris Purslow
Hello, Could you please confirm if Parish Councils would be considered a statutory stakeholder for a DCO application under the 2008 Planning Act if located in a host local authority ward or if in t... Read more
-
View advice to A Henderson
Please could you confirm whether it is possible to submit a DCO application in outline, following by subsequent reserved matters? If so, please can you provide some further details on the process?
-
View advice to Stephen Blyth
Is it possible for a husband and wife to register separately as interested parties if they have the same email address?
-
View advice to Welsh Government
have a query relating to section 92 of the 2008 Act which I wondered if you could help with. 92(2) states: “The Examining authority must fix, and cause each affected person to be informed of, the... Read more
-
View advice to Kettering Borough Council
Query regarding the Planning Act 2008 (PA2008) process, definitions of highway Nationally Significant Infrastructure Projects (NSIPs) and consultation requirements.
-
View advice to James Wilson
We are part of a team assessing the feasibility of a pipeline project in Dorset. The location and route of the pipeline is Portland Port to the NTS at Mappower, Dorset. In 2007 a project was gra... Read more
-
View advice to Waitrose
I am enquiring about registering as an interested party for a nationally significant infrastructure project. An individual appears to need to state how the proposed infrastructure project is going to ... Read more
-
View advice to National Grid
Discussion regarding the s52 authorisation request process
-
View advice to Jonathan Dean
Do the NPSs, in particular EN-1, 5 & 6 have a "fixed life" or are they in place until superseded?
-
View advice to Grey Friars Investments
I would be grateful if you would confirm the number of DCO applications in the 5 years to April 2018 that have been withdrawn during the 28 acceptance period (i.e. after the submission but prior to a ... Read more
-
View advice to General - anon
Compilation of advice about the Environmental Impact Assessment scoping process, undertaken by the Planning Inspectorate on behalf of the Secretary of State.
-
View advice to Ivan Stone
Does PINS have responsibility for enforcing (monitoring, revoking) a DCO once it has been granted. If development is not in line with the DCO what is PINS role? Who is responsible for monitoring and e... Read more
-
View advice to Lee
Is it correct that an applicant for a DCO must provide copies of relevant documents to members of the public during public consultation?
-
View meeting with Hartlepool Borough Council
Project Inception Meeting - Hartlepool Western Growth Corridor
-
View advice to Mick George Ltd
• What point should a waste application be considered to be submitted as a NSIP? (is there a threshold ie size, annual import, waste type ie hazardous, etc) • Is there any point when an NSIP is m... Read more
-
View advice to Mark Redding
As you are probably aware South Northants is facing the prospect of two developments alongside each other and a relatively small group of people are dividing their time between putting a case against ... Read more
-
View meeting with Statera Energy Ltd
Project meeting
-
View advice to Suffolk County Council
Query regarding timing of consultation
-
View advice to Graham Farley
Could the department please clarify procedure for a Nuclear New Build projected for Bradwell in Essex. The Government has given the project the go-ahead subject to planning. Now the developer ha... Read more
-
View advice to Clare Garrard
I recently attended a consultation event for the A303 Sparkford to Ilchester scheme and would like to register my interest in the application.
-
View meeting with Highways England
A meeting was held to discuss EIA scoping for the A1 Morpeth to Felton scheme
-
View advice to Global Ecofuel Solutions S.L.
GEFS and UK partners are looking to build a biorefinery under two Department for Transport programmes to provide alternative fuels for transport and aviation. The project will take waste wood category... Read more
-
View advice to Wood Group
I am writing regarding a query on the Planning Act 2008 requirements of an NSIP. I would like to find out whether it would be possible to gain any clarification whether the requirements that qualify a... Read more
-
View advice to Innogy Renewables UK Limited
Varying a DCO Requirement Could you briefly explain how a developer would formally vary a Requirement imposed on a DCO? In the absence of any specific legislation covering this point, I am assuming... Read more
-
View meeting with Highways England
Initial meeting to discuss the A1 Alnwick to Ellingham scheme
-
View meeting with Statera Energy
Thurrock Hybrid Power Plant - Project Update Meeting
-
View advice to Des Brennan
Local Authorities have had a well-established role in the Secretary of State’s determination of Nationally Significant Infrastructure Projects and in implementing/enforcing Development Consent Orders.... Read more
-
View advice to Pinsent Masons
I wish to inspect the Book of Reference for the Rookery South Energy from Waste Generating Station, which is no longer available for inspection on the National Infrastructure Planning website. Ple... Read more
-
View meeting with Highways England
Meeting to discuss progress of potential NSIP applications
-
View meeting with Highways England
A meeting between Highways England and the Planning Inspectorate to discuss the A1 Morpeth to Felton proposals
-
View meeting with Radioactive Waste Management
A meeting to discuss the Planning Act 2008 process for Nationally Significant Infrastructure Projects (NSIPs)
-
View meeting with AES Electric Ltd
Project meeting
-
View meeting with AES Electric Ltd
Introduction to the battery storage project at Culham Science Centre, Abingdon
-
View advice to General
Compilation of advice to local communities about the Pre-application procedure and community consultation.
-
View meeting with Civil Aviation Authority
Meeting to discuss the role of the CAA in the Planning Act 2008 process
-
View advice to Peter Miller
Mr Miller wrote to ask about the proposed Upper Orwell Crossings scheme. He asked that we clarify its current status and what happens next.
-
View advice to NFU
Can section 53 (s53) of the Planning Act 2008 (PA2008) authorise the pumping of water?
-
View advice to JLL
JLL have been instructed by AES Electric Ltd to provide planning strategy advice regarding developing and operating a grid scale battery storage project located at the Culham Science Centre, Abingdon.... Read more
-
View meeting with Heathrow Southern Railway Ltd
Inception Meeting with Heathrow Southern Railway Ltd - 19/07/2017
-
View advice to Andrew Gough
Recent decisions by the Secretary of State (e.g. Radlett) have contained an opinion as to whether the proposed development will work as an SRFI. I am therefore writing to ask what tests would be appli... Read more
-
View advice to General
Compilation of advice relating to section 53 of the Planning Act 2008.
-
View advice to Katie Excell
I am writing a legal dissertation focusing on nationally significant infrastructure projects including related housing developments, under s160 of the Housing and Planning Act 2016. I was just won... Read more
-
View advice to The Wildlife Trusts
See attached letter dated 6 April 2017
-
View meeting with Mace
Discussion of generic planning issues
-
View meeting with Heathrow Airport Ltd
Project update meeting.
-
View advice to Brian Sumpton
I do understand that every situation is unique and the appointed Planning Inspector has to use his own judgement in making his recommendations to the Secretary of State. Section 5.184 of the NPSNN sta... Read more
-
View meeting with Highways England
Pins Meeting with Highways England relating to A12 Chelmsford to A120
-
View advice to Dave Chillistone
As I understand the process, in order for a NSIP to proceed, a DCO application must be made to the Planning Inspectorate. What if a relatively small infrastructure project (a railway re-opening) fa... Read more
-
View advice to Brian Sumpton
Could you please help clarify the legal position regarding proposed diversions to public rights of way. The Highways Act 1980 section 119 suggests that the SoS can not confirm a diversion order if ... Read more
-
View advice to David Hoare
I would like to know whether any DCO has been subject to longer examination/determination timescales than those outlined in the Planning Act 2008 (i.e. 6 months for examination, 3 months for the panel... Read more
-
View advice to Mark Redding
I would like to speak to someone regarding the recent changes (March 2017) to the Planning Act 2008 to allow 500 houses to be included within a DCO application. I am keen to understand who or what pro... Read more
-
View meeting with Highways England
To discuss the process for applying for an application under section 53 of the Planning Act to access land for the purposes of environmental surveys and to provide a brief project update for the A303 ... Read more
-
View meeting with Highways England
Introduction to six Highways England schemes in the north of England.
-
View advice to Royal Haskoning DHV
What are your organisations concerns if you were to receive a digital, web based, versus a paper based Environmental Statement? Do you think your organisation would accept a digital ES (assuming it co... Read more
-
View meeting with Heathrow Airport Ltd
Note of presentation to the Civil Aviation Authority and airlines, airport tour and project update meeting
-
View advice to Martyn Thompson
I hope you can assist me with the following question regarding a potential project my company is considering. The project is the design & construction of a combined heat & power (CHP) project that wi... Read more
-
View advice to Stor Power Ltd
1. Would a battery storage project with a capacity of more than 50 MW be classified as an NSIP? 2. If a site already has consent for a 40MW Gas fired electricity peaking plant and either the same o... Read more
-
View advice to Churchgate Accountants Limited
Dear Sirs, On your advice notes page: https://infrastructure.planninginspectorate.gov.uk/legislation-and-advice/advice-notes/ Advice note 5 on rights of entry refer to S53 of the Planning Act 2008, se... Read more
-
View meeting with Statera Energy
Meeting regarding a potential NSIP project
-
View meeting with Stop Rail Central
Meeting to discuss procedural aspects of the Planning Act 2008 process
-
View advice to Jamie Macnamara
What are the rules governing applicants in DCO processes in the following specific circumstances; · Application is at pre-application stage (Scoping Report submitted) and is currently progres... Read more
-
View meeting with Highways England
Project Update Meeting
-
View meeting with Norfolk County Council
To provide an overview of the Planning Act 2008 process to the A47 Alliance Steering Group Meeting
-
View meeting with Highways England
Project Update Meeting
-
View meeting with Heathrow Airport Ltd
Project update meeting.
-
View advice to ATKINS
I understand that an application for a DCO makes provision for developers to detail other consents etc that are required under legislation other than the 2008 Act. Certain prescribed consents can be c... Read more
-
View advice to Strutt & Parker LLP
I had a quick enquiry in respect of nationally significant infrastructure projects which I was hoping you may be able to assist with. I assume that in preparation of a planning application, a screenin... Read more
-
View advice to Bean Residents Association
Can you tell us if the above Highways England project has been accepted as a NSIP? Ii is currently subject to ‘informal’ Public Consultation (18th Jan to 1st March 2017). HE Scheme Milestones show... Read more
-
View advice to Pegasus Planning
Can solar farm applications in England and Scotland fall under the remit of the Planning Act 2008.
-
View meeting with Heathrow Strategic Planning Group
The Planning Inspectorate were invited to give a presentation to the HSPG about the Planning Act 2008 process.
-
View advice to Gowling WLG
The enquirer requested to view the Book of Reference associated with The Daventry International Rail Freight Interchange Alteration Order 2014.
-
View advice to Andrew Troupe
Planning permission has been granted for a new battery storage facility in South Oxfordshire with a capacity of more than 50MW - does this mean that battery storage is not regarded as a form of energy... Read more
-
View meeting with Heathrow Airport Ltd
Project update meeting.
-
View meeting with Highways England
A303 Amesbury to Berwick Down (Stonehenge) Project Update Meeting
-
View meeting with Highways England
A428 Black Cat to Caxton Gibbet - Introduction Meeting
-
View meeting with Storelectric
Meeting regarding a possible NSIP project
-
View meeting with Suffolk County Council
Lake Lothing Third Crossing Introduction Meeting
-
View advice to Canal and River Trust
Since S160 of the Housing & Planning Act allowed for residential development to be included in NSIPs to an extent, have there been changes to your website content and any guidance around this at all? ... Read more
-
View meeting with Highways England
A2 Bean to Ebbsfleet project update meeting
-
View meeting with Statera Energy Ltd
Meeting regarding possible battery storage projects
-
View meeting with Suffolk County Council
Project introduction – Upper Orwell Crossings
-
View advice to Natural Power
Dear Sir/Madam, I am enquiring who would determine an onshore wind project located in Wales with a capacity of 50 MW. Would this be an NSIP project and determined by Planning Inspectorate, as all ... Read more
-
View advice to DJ Lee
Can I begin the process of applying for a Development Consent Order for the development of a Geological Disposal Facility for Higher Activity Radioactive Wastes from The UK's Civil Nuclear industry an... Read more
-
View meeting with Highways England
A47 Project Update Meeting
-
View advice to Pegasus Group
I am looking for a timeline chart that shows the NSIP process stages, and the length of anticipated time to complete each one. I recall a thirty-odd page document setting out the details of the pr... Read more