Hinkley Point C New Nuclear Power Station

Section 51 advice

The list below includes a record of advice we have provided for this project.

There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.

Search advice

Search by key words or the name of person the advice was given to.

Showing 76 to 100 of 120 documents, newest first.

Results per page 25 | View 50 results per page | View 100 results per page

  • View meeting with EDF

    The IPC chaired a tripartate meeting between various stakeholders to discuss the forthcoming appilcation for a generating station at Hinkley Point in Somerset.

  • View advice to Nick Lloyd-Davies

    1. Would the IPC require an application for a direction deeming Hazardous Substances Consent (HSC) to have been granted to be made at the same time as submission of the application for development... Read more

  • View meeting with EDF Energy

    The IPC case team met a team from EDF Energy to discuss the forthcoming application at Hinkley Point in Somerset, and particularly the consultation being undertaken regarding the junction 24 site and... Read more

  • View advice to Avon and Somerset Police

    Mr Steve Crago, of Avon and Somerset Police, made an enquiry by telephone with regard to drafting s106 obligations under the Planning Act 2008 regime; relating to the Hinkley C generating station... Read more

  • View meeting with Various Stakeholders

    The IPC observed a meeting held by EDF Energy to present a summary of progress with the Habitats Regulations Assessment for the proposed Hinkley C Nuclear Power Station, for discussion with Natural... Read more

  • View meeting with Otterhampton Parish Council

    To discuss the role of the Infrastructure Planning Commission and opportunities for engagement with the application process under the 2008 Act, with particular reference to the forthcoming application... Read more

  • View meeting with EDF

    Meeting between EDF, IPC, Sedgemoor DC, West Somerset DC, Somerset CC, Environment Agency and Highways Agency to discuss emerging issues arising out of the proposed application for Hinkley C.

  • View meeting with Ian Bryant

    Meeting with EDF Energy, West Somerset District Council, Sedgemoor District Council, Somerset County Council, Environment Agency and Highways Agency to discuss the proposed Hinkley Point 'C' project.

  • View meeting with Richard Mayson

    Meeting to discuss the proposed Hinkley Point 'C' scheme

  • View meeting with EDF Energy

    Pre-Application meeting between EDF Energy, and their legal advisers, and the IPC case team to discuss progress on the Hinkley C generating station project, preliminary works applications and... Read more

  • View advice to Jamie Robertson

    In relation to http://infrastructure.independent.gov.uk/projects/south-west/hinkley-point-c-new-nuclear-power-station/ I have recently written to the developer questionning the adequacy of its... Read more

  • View advice to Chris Eaglen

    Dr Chris Eaglen submitted three representations on the proposed Hinkley C Generating Station in West... Read more

  • View advice to Jamie Robertson

    Re: http://infrastructure.independent.gov.uk/projects/south-west/hinkley-point-c-new-nuclear-power-station/ According to your website: "The application is expected to be submitted to the IPC... Read more

  • View meeting with EDF Energy NNB

    Whether the proposed temporary accommodation campuses can lawfully be included within the Hinkley Point C application as associated development under s115(2) of the Planning Act 2008 (the Act) .

  • View meeting with Pinsent Masons

    Meeting with Pinsent Masons to discuss associated development.

  • View advice to David Templeman

    The enquirer requested that we inform EDF Energy and central government that a new road is vital (at Dunball), before any permission is granted for the proposed new build at Hinkley Point.

  • View meeting with Stop Hinkley

    The IPC case team met with delegates from Stop Hinkley Group on 1 December 2010 to discuss the IPC application process and how to participate, with referance to the forthcoming application at Hinkley... Read more

  • View advice to Crispin Aubrey

    Crispin Aubery, on behalf of Stop Hinkley Group, wrote to the IPC with questions in relation to the Hinkley Point C proposal. Firstly, he wanted to know the IPC's relationship to the current... Read more

  • View meeting with Richard Mayson

    The IPC case team chaired a tripartate meeting of stakeholders for the proposed Hinkley C power station on 11 November 2010, including the Highways Agency, the Enviroment Agency, West Somerset DC,... Read more

  • View advice to Kevin Baker

    Following any application for the proposed Hinkley Point C development consent order and following the examination, which minister makes the final decision whether or not the DCO is issued? If not the... Read more

  • View advice to Lesley Flash

    Dear Sir or Madam I wish to draw your most urgent attention to the following facts: The hamlets of Shurton, Burton and Wick are extremely close to the boundary of the proposed development. ... Read more

  • View advice to Mr & Mrs D Harvey

    As you are probably aware by now, it's not the building of a new power station that the people of Somerset are trying to stop. EDF are planning to use existing roads for lorries, cars and coaches.... Read more

  • View advice to John Randall

    See Attached letter

  • View advice to Michael Laver

    As requested at a recent meeting with the Stogursey Parish Council I forward to you a copy of my comments to EdF on their Stage 2 Consultation document for your information.

  • View advice to L A Laird

    Mrs Laird wrote to us regarding the merits of the proposed development, and the impacts she feels it will have upon the village of Combwich.