We use some essential cookies to make this service work.
We'd also like to use analytics cookies so we can understand how you use the service and make improvements.
You’ve accepted analytics cookies. You can change your cookie settings at any time.
You’ve rejected analytics cookies. You can change your cookie settings at any time.
Beta This is a beta service - your feedback will help us to improve it
The list below includes a record of advice we have provided for this project.
There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.
Search by key words or the name of person the advice was given to.
Showing 1 to 30 of 30 documents, newest first.
Results per page View 25 results per page | View 50 results per page | 100
Request for information regarding the Examination stage of the Planning Act 2008 process
Request for advice on how the process works.
Query regarding the proposed access routes for the gas connection.
Request to attend hearings on 14 and 15 May 2014 as a non-interested party.
Email from Selby District Council regarding their status as an Interested Party 'IP'.
Late representation received regarding Knottingley Power Project. The Examining Authority exercised its discretion and has chosen not to accept the representation at this stage.
Late representation received on 12 March 2014 regarding Knottingley Power Project. The Examining Authority exercised its discretion and has chosen not to accept the representation at this stage.
Advice to Parish Council regarding its status as an interested party.
Comments received from Chapel Haddlesey Parish Council regarding Knottingley Power Project application.
The applicant noted minor errors in its original application documents submitted to the Inspectorate and requested to submitt revised documents along with a schedule highlighting and explaining the ch... Read more
Advice regarding submissions before Preliminary Meeting.
Advice to local planning authority on getting involved in the examination of the application
Request for information relating to attendance at the Preliminary Meeting.
Request to submit written representation and query relating to attendance at the Preliminary Meeting.
Email from Local Planning Authority requesting extension for deadlines set in draft timetable for examination.
Advice to local planning authority regarding Local Impact Report.
Query regarding liability of operator of development in making compensation payments if applicant cease to be operator when payment is due.
The enquiry received from the applicant regarding deadline for submission of Certificates of Compliance with s56 of the Planning Act (as amended) The applicant enquired whether certificates must be... Read more
Phone call regarding letters submitted to the applicant at the relevant representation stage
Advice given on the relevant representation process
The use of an illegible 'captcha with this form is crass. The entire planning system is biased against residents and now you are making it harder for us to register
Phonecall from Canal Trust regarding making a relevant representation.
Email regarding applicant's adequacy consultation.
Email rgarding adequacy of consultation.
Pre-submission update from the applicant and discussion on the draft documents submitted to the Planning Inspectorate.
Enquiry regarding Statements of Common Ground
Project update meeting - Please see attached note
Inception meeting between the Planning Inspectorate and ESBI
Introductory Meeting and discussion of pre-application process.