View examination library (PDF, 818KB) containing document reference numbers
-
DR-001 - Submissions made directly to the Secretary of during Recommendation stage
(PDF, 11MB)
From UKWIN
-
PID-002 - Submissions made to the Planning Inspectorate during Decision stage and sent to Secretary of State
(PDF, 273KB)
From North Lincolnshire Green Energy Park Limited
-
PID-003 - Submissions made to the Planning Inspectorate during Decision stage and sent to Secretary of State
(PDF, 452KB)
From UKWIN
-
Written Ministerial Statement extending the statutory deadline for this application to 14 March 2025
(PDF, 136KB)
From Department for Energy Security and Net Zero
-
Response to Secretary of State Letter dated 20 September 2024
(PDF, 88KB)
From Department for Environment Food and Rural Affairs
-
NLGEP Follow Up Letter
(PDF, 471KB)
From North Lincolnshire Green Energy Park
-
Secretary of State Letter dated 20 September 2024
(PDF, 203KB)
From Department for Energy Security and Net Zero
-
Response UKWIN Query re Extension
(PDF, 115KB)
-
Response Applicant Query re Extension
(PDF, 116KB)
-
NLGEP letter following Ministerial Statement
(PDF, 187KB)
-
PID-005 - Submissions made to the Planning Inspectorate during Decision stage and sent to Secretary of State April 2024
(PDF, 105KB)
From United Kingdom Without Incineration Network (UKWIN)
-
PID-003 - Submissions made to the Planning Inspectorate during Decision stage and sent to Secretary of State April 2024
(PDF, 572KB)
From Keely Midgely
-
PID-004 - Submissions made to the Planning Inspectorate during Decision stage and sent to Secretary of State April 2024
(PDF, 311KB)
From Burton upon Stather Parish Council
-
PID-002 United Kingdom Without Incineration Network (UKWIN) - 27 February 2024
(PDF, 192KB)
From United Kingdom Without Incineration Network (UKWIN)
-
C3-003 update from the Applicant on the proposed Section 106 agreement 01 March 2024
(PDF, 157KB)
From North Lincolnshire Green Energy Park Limited
-
Secretary of State Consultation 2 Response
(PDF, 2MB)
From North Lincolnshire Green Energy Park Limited
-
Response to Secretary of State Consultation letter
(PDF, 190KB)
From DWD LLP on behalf of North Lincolnshire Green Energy Park Limited
-
Letter from the Secretary of State – dated 14 February 2024
(PDF, 171KB)
From Secretary of State Consultation
-
Late Submission - Accepted at the discretion of the Examining Authority - Comments on Applicants response to SoS Consultation 2 letter
(PDF, 426KB)
From UKWIN
-
Technical note produced by Beyond Waste
(PDF, 2MB)
From United Kingdom Without Incineration Network (UKWIN)
-
Response to SoS Consultation letter
(PDF, 386KB)
From United Kingdom Without Incineration Network (UKWIN)
-
9.46 Applicant's response to request for further information by the Secretary of State
(PDF, 6MB)
From DWD LLP on behalf of North Lincolnshire Green Energy Park Limited
-
Response to the Secretary of State Request for Information dated 8 December 2023
(PDF, 173KB)
From North Lincolnshire Council
-
Response to Secretary of State Consultation
(PDF, 151KB)
From Natural England
-
Secretary of State Consultation 2 Response
(PDF, 196KB)
From Environment Agency
-
Letter from the Secretary of State – dated 8 December 2023
(PDF, 236KB)
From Secretary of State Consultation
-
Late Secretary of State Consultation 1 Response
(PDF, 360KB)
From Health and Safety Executive
-
Response to Secretary of State Consultation 1
(PDF, 92KB)
From Natural England
-
9.44 Applicant's Response to Request for Further Information by the Secretary of State
(PDF, 10MB)
From North Lincolnshire Green Energy Park Limited
-
9.45 - Updated Grid Connection Letter [Rev 1]
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
6.2.19 - ES Chapter 19 Mitigation [Rev3] (clean)
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
1.2 Application Guide (Rev 12) Clean
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
6.2.9 - ES Chapter 9 Water Resources and Flood Risk [Rev 2] (tracked)
(PDF, 10MB)
From North Lincolnshire Green Energy Park Limited
-
6.3.7 - ES Annex 7 CoCP [Rev 8] (clean)
(PDF, 3MB)
From North Lincolnshire Green Energy Park Limited
-
1.2 Application Guide (Rev 12) Tracked
(PDF, 986KB)
From North Lincolnshire Green Energy Park Limited
-
6.3.8 - ES Annex 8 OEMP [Rev 3] (tracked)
(PDF, 684KB)
From North Lincolnshire Green Energy Park Limited
-
Secretary of State Consultation 1 Response
(PDF, 268KB)
From Jotun Paints (Europe) Ltd
-
6.3.7 - ES Annex 7 CoCP [Rev 8] (tracked)
(PDF, 3MB)
From North Lincolnshire Green Energy Park Limited
-
NLGEP Covering Letter
(PDF, 201KB)
From North Lincolnshire Green Energy Park Limited
-
6.2.19 - ES Chapter 19 Mitigation [Rev 3] (tracked)
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Secretary of State Consultation 1 Response
(PDF, 55KB)
From HSE
-
6.2.9 - ES Chapter 9 Water Resources and Flood Risk [Rev 2] (clean)
(PDF, 10MB)
From North Lincolnshire Green Energy Park Limited
-
6.3.8 - ES Annex 8 OEMP[Rev 3] (clean)
(PDF, 684KB)
From North Lincolnshire Green Energy Park Limited
-
Response to Secretary of State Consultation 1
(PDF, 237KB)
From North Lincolnshire Council
-
Letter from the Secretary of State – dated 22 September 2023
(PDF, 224KB)
From Secretary of State Consultation
-
Deadline 9 Submission - 9.40 Applicants Response to Examining Authority's Rule 17 request for information
(PDF, 943KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 9.12 Draft Development Consent order (dDCO) Schedule of Changes (Revision 6) (Tracked)
(PDF, 462KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - Cover Letter
(PDF, 586KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.2.18 - Final Statement of Common Ground (SoCG) with Economic Benefits Group
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 1.2 Application Guide (Clean)
(PDF, 871KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.1 Statement of Commonality (Revision 8) (Clean)
(PDF, 956KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.2.3 - Final Statement of Common Ground (SoCG) with Network Rail Infrastructure Limited
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.2.12 - Final Statement of Common Ground (SoCG) with Natural England
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 9.12 Draft Development Consent order (dDCO) Schedule of Changes (Revision 6) (Clean)
(PDF, 400KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.2.6 - Final Statement of Common Ground (SoCG) with AB Agri Limited
(PDF, 968KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 1.2 Application Guide (Tracked)
(PDF, 899KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 2.1 Draft Development Consent Order revision 8 - (Clean)
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.1 Statement of Commonality (Revision 8) (Tracked)
(PDF, 982KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 9.43 - Comments on Cadent Gas Limited's submission recieved at Deadline 9
(PDF, 866KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 2.1 Draft Development Consent Order revision 8 – Tracked
(PDF, 797KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 Submission - 8.2.17 - Final Statement of Common Ground (SoCG) with Bagmoor Wind Limited
(PDF, 873KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 10 submission - Withdrawal of objection
(PDF, 215KB)
From Addleshaw Goddard LLP on behalf of Network Rail Infrastructure Limited
-
Notification of completion of the Examining Authority’s Examination
(PDF, 133KB)
-
Additional Submission - Accepted at the discretion of the Examining Authority - 9.7 Schedule of Changes to Book of Reference (BoR) and Land Plans [Revision 3]
(PDF, 144KB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 6.2.10 - Environmental Statement (ES) Chapter 10 - Ecology and Nature Conservation [Revision 1] (clean)
(PDF, 53MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 4.2 Land Plans [Revision 3]
(PDF, 25MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 9.41 - Updated Grid Connection Letter
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 1.2 Application Guide (Clean) [Revision 11]
(PDF, 904KB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 1.2 Application Guide (Tracked) [Revision 11]
(PDF, 937KB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 9.37 - Closing Submissions [Revision 0]
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 6.3.7 Environmental Statement (ES) - Annex 7 - Code of Construction Practice (CoCP [Revision 7] (tracked)
(PDF, 2MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 3.1 Book of Reference (BoR) [Revision 4] (tracked)
(PDF, 101KB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 5.9 Report to Inform Habitats Regulations Assessment (HRA) [Revision 3] (clean).
(PDF, 17MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 6.3.7 Environmental Statement (ES) - Annex 7 - Code of Construction Practice (CoCP [Revision 7] (clean)
(PDF, 2MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 5.9 Report to Inform Habitats Regulations Assessment (HRA) [Revision 3] (tracked)
(PDF, 17MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 3.1 Book of Reference (BoR) [Revision 4] (clean)
(PDF, 101KB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 9.42 Comments on Anglian Water's Response to Rule 17 letter
(PDF, 919KB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 6.2.10 - Environmental Statement (ES) Chapter 10 - Ecology and Nature Conservation [Revision 1] (tracked)
(PDF, 53MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - 5.13 Deed of Development Consent Obligation [Revision 1]
(PDF, 27MB)
From North Lincolnshire Green Energy Park Limited
-
Additional Submission - Accepted at the discretion of the Examining Authority - Additional submission covering letter
(PDF, 208KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 9.3 Compulsory Acquisition (CA) Schedule (Revision 8) (tracked)
(PDF, 685KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - The Engineer - Jet2 announces Sustainable Aviation Fuel investment
(PDF, 679KB)
From United Kingdom Without Incineration Network (UKWIN)
-
Deadline 9 Submission - 6.3.7 - Code of Construction Practice (CoCP) [Revision 6] (CLEAN)
(PDF, 2MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 9.12 draft Development Consent Order (dDCO) Schedule of Changes (D9) - Tracked
(PDF, 428KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - Comments on any additional information/submissions received at Deadline 8
(PDF, 282KB)
From United Kingdom Without Incineration Network (UKWIN)
-
Deadline 9 Submission - 6.2.14 - Environmental Statement (ES) - Chapter 14 - Economic Community and Land Use Impacts (Revision 2) (clean)
(PDF, 15MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 6.2.18 - Environmental Statement (ES) - Chapter 18 - Cumulative and Indirect Effects {Revision 1) (clean)
(PDF, 14MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 2.1 Draft Development Consent Order (revision 7) (tracked).
(PDF, 732KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 6.2.16 - Environmental Statement (ES) - Chapter 16 Major Accidents and Disasters (Revision 1) (clean).
(PDF, 870KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 2.1 - Validation Report - Deadline 9
(PDF, 744KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - Comments on responses to the Examining Authority's Third Written Questions (ExQ3)
(PDF, 138KB)
From Environment Agency
-
Deadline 9 Submission - 9.3 Compulsory Acquisition (CA) Schedule (Revision 8) (clean)
(PDF, 943KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 8.2.8 - FINAL Statement of Common Ground (SoCG) with Environment Agency
(PDF, 822KB)
From North Lincolnshire Green Energy Park Limited
-
Late Deadline 9 Submission - Accepted at the discretion of the Examining Authority - Withdrawal of objection
(PDF, 81KB)
From National Highways
-
Deadline 9 Submission - 8.2.6 - DRAFT Statement of Common Ground (SoCG) with AB Agri Limited
(PDF, 986KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 8.1 Statement of Commonality (Clean)
(PDF, 1MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 8.2.17 - Draft Statement of Common Ground (SoCG) with Bagmoor Wind Limited
(PDF, 791KB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 5.4 - Combined Heat and Power Assessment (Tracked)
(PDF, 2MB)
From North Lincolnshire Green Energy Park Limited
-
Deadline 9 Submission - 9.2 National Policy Statement (NPS) Tracker (Revision 2) (tracked)
(PDF, 2MB)
From North Lincolnshire Green Energy Park Limited
-
Late Deadline 9 Submission - accepted at the discretion of the Examining Authority
(PDF, 138KB)
From CMS Cameron McKenna Nabarro Olswang LLP on behalf of Cadent Gas Limited