Back to list North Lincolnshire Green Energy Park

Representation by British Steel Ltd (British Steel Ltd)

Date submitted
7 September 2022
Submitted by
Members of the public/businesses

British Steel have concerns that the development may have an impact on some of the pipes, water mains and cables in the area which service our site. For example there is a coke oven effluent line and o2 supply to our Biological Effluent Treatment Plant at Normanby Park from the main site. There is also a tidal outfall pipe from the balancing tank at Normandy Park to Neap House and a water rising main from Gunness to our main site that passes under the motor way near Glanford Park. British Steel would like some reassurance that any service media in the area will not be effected by the development and our access rights remain unchanged..