I am small farm on the perprosed route of the cable to Drax On the 5/4/22 we were approached by boom power to put a cable around the edge of 3 fields we signed a 1 year agreement so that a servey could be done A year later when boom power came back with a new agreement the cable route had moved much further into the fields and this would cut through about 30 land drains When we tried to negotiate with boom on how these drains would be rendstated boom power attitude seems to be take or leave it I now feel that that if they get planing permission they will come Back with a compulsory order So far we have not signed another agreement