We use some essential cookies to make this service work.
We'd also like to use analytics cookies so we can understand how you use the service and make improvements.
You’ve accepted analytics cookies. You can change your cookie settings at any time.
You’ve rejected analytics cookies. You can change your cookie settings at any time.
Beta This is a beta service - your feedback will help us to improve it
The list below includes a record of advice we have provided for this project.
There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.
Search by key words or the name of person the advice was given to.
Showing 1 to 25 of 29 documents, newest first.
Results per page 25 | View 50 results per page | View 100 results per page
Resourcing update.
Relevant Representation process.
Advice following issue of decision to accept the application for examination.
I strongly object to the plans for Gatwick expansion using a the conversion of the emergency runway approach. It will have a serious adverse effect on the environment and the well being of humans and ... Read more
I would be grateful if you could advise on whether PINS are ok with handling a covering letter to a Joint Authority AoC response which includes the electronic signatures of ten senior officers from ea... Read more
“As you are aware, the ten Gatwick local authorities are working collectively on the Northern Runway Project. With regard to Adequacy of Consultation (AoC), the authorities propose to submit a joint r... Read more
Merton Council queried whether it could be included in correspondence from the Planning Inspectorate regarding the adequacy of the Applicant’s Pre-application consultation.
The enquirer expressed an intention to register as an Interested Party in respect of the scheme, and requested further details.
See attached
Project Update Meeting.
Project update meeting.
Local authority out-reach meeting.
In relation to post-submission, we have a specific question at this stage about process. Our understanding was that the post-acceptance/pre-examination stage would take three months but GAL has sugges... Read more
Project Update Meeting
During the meeting between the Applicant and the Planning Inspectorate on 16 September 2022, the Applicant queried how socio-economic effects from diminution in property value had been addressed throu... Read more
GATCOM Meeting
I note you have mentioned raising concerns at the AoC stage. As GATCOM is not a Local Authority, does this apply?
I wonder if you could shed some light on a matter related to Gatwick’s preparation of its DCO application please? Gatwick Airport Limited (GAL) published as part of its pre-application consultation a ... Read more
I have another matter on which I wish to seek advice about the DCO process. Having read the Inspectorate’s guidance it is not clear what remedies are available to interested parties to raise issues wh... Read more
1. In relation to local authorities, and I’m thinking here specifically of Crawley Borough Council, please can you confirm where the roles are specified? 2. Under section 42 – the duty to consult abou... Read more
In relation to the baselines Gatwick has proposed for the project in its consultation (which we note have changed from the baselines proposed in its Scoping Report), you say: "they are not matters tha... Read more
what work has PINS done, or plans to do, to confirm that the baseline level of 61 million passengers set out in Gatwick's Scoping Report is appropriate.
Pagination navigation
Showing 1 to 25 of 29 results