1. Section 51 advice
  2. Advice in detail

Advice to Anonymous

Back to list

Enquiry

From
Anonymous
Date advice given
22 July 2020
Enquiry type
Email

My wife and I have both received a letter asking for a contact email in relation to the application by North Somerset Council for an order granting development consent for the Portishead Branch Line - MetroWest Phase 1. I'm writing to ask that you remove our details from your records as we are in the process of selling our property so will no longer be directly impacted by the development.

Advice given

The Applicant’s Book of Reference (the document identifying ‘Affected Persons’ whose rights will be affected by Compulsory Acquisition required to construct and operate the scheme) lists both yourself and your wife due to your properties’ proximity to the proposed Portishead Branch Line - MetroWest Phase 1. The Planning Inspectorate is legislatively required to correspond with all Affected Persons for the duration of the application until the Secretary of State’s decision is issued. I will forward your email to the Applicant so it’s aware of the situation. It would be helpful if you could confirm again once you have formally left the property so we can temporarily amend our records to ‘Owner / Occupier’ until those persons have been identified.

Attachments

View advice (PDF)

View advice (PDF)