Daventry International Rail Freight Terminal Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 8 July 2013

The examination closed on 8 January 2014

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

8 July 2013 - Preliminary Meeting

Closed

Preliminary Meeting for DIRFT 3

15 July 2013 - Deadline 1

Closed

Issue of:

  • Procedural timetable
  • Examining Authority’s (ExA) first written questions

19 July 2013 - Site Visit (Accompanied)

Closed

Accompanied site visit

14 August 2013 - Deadline 2

Closed

Deadline for receipt by the ExA of:

  • Comments on relevant representations (RRs) already received
  • Summaries of all RRs exceeding 1500 words
  • Written representations (WRs) by all interested parties
  • Summaries of all WRs exceeding 1500 words
  • Local Impact Report(s) (LIR) from local authorities
  • Responses to the ExA’s first written questions
  • Statements of Common Ground from the applicant
  • Revised version of the draft Development Consent Order from the applicant

30 August 2013 - Issue Specific Hearing 1

Closed

First hearing on draft development consent order

13 September 2013 - Deadline 3

Closed

Deadline for receipt by the ExA of:

  • Comments on WRs and responses to comments on RRs
  • Comments on LIRs
  • Comments on responses to the ExA's first written questions

20 September 2013 - Deadline 4

Closed

Issue of the ExA’s further written questions

11 October 2013 - Deadline 5

Closed

Deadline for receipt by the ExA of:

  • Requests for any issue specific hearings, compulsory acquisition and open floor hearings
  • Responses to Examining Authority's further written questions

22 October 2013 - Issue Specific Hearing 2

Closed

Second hearing on draft DCO

25 October 2013 - Deadline 6

Closed

Notification by the ExA of date, time and place of:

  • Open floor hearing (if requested)
  • Compulsory acquisition hearing (if requested)
  • Any issue specific hearings (in the event the ExA decides during the progress of the examination that they are needed)

1 November 2013 - Deadline 7

Closed

Deadline for receipt by the ExA of:

  • Comments on responses to ExA's further written questions

18 November 2013 - Deadline 8

Closed

Deadline for submission to the ExA of the final draft DCO and completed s106 undertaking(s) and Period reserved (18 November to 29 November) for final draft DCO hearing, any other issue specific hearings, compulsory acquisition and open floor hearings

27 November 2013 - Issue Specific Hearing 3

Closed

Third hearing on draft DCO

27 November 2013 - Open Floor Hearing

Closed

Open Floor Hearing

20 December 2013 - Deadline 9

Closed

Deadline for receipt by the ExA of:

  • Written comments on the Draft National Policy Statement (NPS) for the National Road and Rail Networks