Advice to Environmental Agency

Back to list

Enquiry

From
Environmental Agency
Date advice given
21 February 2011
Enquiry type
Email

When does the developer have to submit the statement of common ground?

Advice given

For clarification, a Statement of Common Ground is not required to be submitted as part of the initial application submission to the IPC, it will be required (where appropriate) to be submitted during the examination stage. We do however encourage all parties to undertake preparatory work on such statements as early as possible in the process.

Shortly after the preliminary meeting is held, the Examining authority will set a deadline for receipt of the statement of common ground.