Register of advice
This list is a record of general advice provided by the Planning Inspectorate. We publish this to comply with the 2008 Planning Act.
Project specific advice can be viewed on the relevant project page.
Search advice
Search by key words or the name of person the advice was given to.
Showing 701 to 727 of 727 entries, newest first.
Results per page View 25 results per page | View 50 results per page | 100
-
View meeting with National Grid
From National Grid (NG) perspective: establishing feedback on NG’s consultation processes; and ongoing engagement between NG and IPC. From IPC’s perspective: setting out the processes and rules associ... Read more
-
View meeting with GE ENERGY
IPC to provide an overview of its strategic approach as well as the operations for dealing with Nationally Significant Infrastructure Projects (NSIPs).
-
View advice to Member of the Public
Caller had been told that some land he was looking to purchase was to be used for housing, the application for which will be made to the IPC. Can we confirm that this is so?
-
View advice to EDF
Please see questions asked in the advice given column.
-
View advice to Brecon Beacons National Park Aut
Please can you clarify, with respect to the six steps, what is the expected involvement in responding to the IPC and promoter for a statutory consultee such as Brecon Beacons National Park?
-
View advice to Mary Halt
Call regarding a proposed project and the communication with the IPC.
-
View advice to Public Health Wales
Mr Brunt had received a consultation request from Covanta and wanted clarification as to where in the process the application is.
-
View advice to Member of the Public
How many turbines does a proposal need to have for the application to be made to the IPC?
-
View advice to Health Protection Agency
As part of Schedule 1 of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 the HPA are a statutory consultee for all proposed applications likely to involve c... Read more
-
View meeting with Environment Agency
To explore the relationship between environmental permitting and development consent orders.
-
View meeting with StopHinkley etc.
Gain a broader understanding of the new planning regime under the Planning Act 2008 and how NGO’s can engage in the process.
-
View advice to Oswald Desybel
What is the future of the IPC?
-
View advice to Henry Le Brecht
I have recently been having conversations with Gary Mohamed of DECC regarding Determination Assessments associated with high pressure gas pipelines. Specifically in this case we are assessing the ... Read more
-
View advice to Did not wish to disclose Did not wish to disclose
Caller requested at what stage Merthyr Tydfil was within the new planning process and how/when to get involved. What are the procedural rules to be upheld during a hearing?
-
View advice to ARUP
Dear Sir/Madam, I have a question regarding at what point the relevant Local Authority recieves a copy of the DCO application material. I presume it is sent at the point of successful registration ... Read more
-
View advice to Eversheds
Sir/Madam Eversheds are advising in relation to a proposed wind farm project in Wales. It is considered that the project is a nationally significant infrastructure project for the purposes of the... Read more
-
View advice to SSE
When publishing the Statement of Community Consultation (SoCC), what should be included? Can a summary be published?
-
View advice to Christopher Tolmie
Caller enquired whether the IPC is involved with the High Speed Railway 2 (HS2) project given the nature of its size?
-
View meeting with JNCC, WAG, CCW
To set out key responsibilities with regards to off shore NSIP developments.
-
View advice to Freshfields
If an application that was previously approved under the old planning regime was amended, would a new application need to be made to the IPC?
-
View advice to David Croft
As the National Policy Statements (NPSs) are currently in draft, what weight do they hold in the decision making process?
-
View advice to Health Protection Agency
Eirain from HPA has received scoping opinion correspondence regarding Nant-y-Moch from two Local Health Boards. HPA would like to comment on the proposal but had missed the deadline. HPA request... Read more
-
View advice to Scottish Rural Property & Busine
The SRPBA represents landowners in Scotland (equivalent to the CLA in England and Wales). I am trying to ascertain the potential impact of the IPC in terms of infrastructure projects (specifically gas... Read more
-
View advice to Chris Whitehead
We have recently been employed by a wind farm developer to write their Statement of Community Consultation for an off-shore wind farm development. Is there any specific guidance for off-shore developm... Read more
-
View meeting with MGT Power North Tyneside Council
A meeting note taken on 11th May 2010 describing discussions with MGT Power and North Tyneside Council regarding the proposed biomass plant in North Tyneside, and the IPC processes.
-
View advice to Stanley Gono
Could you please advise whether or not Sections 36 & 37 of the Electricity Act 1989 has been disapplied by section 33(1) of the Planning Act 2008? Please explain the primary legislation and how planni... Read more
-
View advice to Eversheds LLP
We have the following enquiry and would appreciate your views. Regulation 5(2) of the 2009 Regulations specifies at subparagraphs (i) to (n) individual plans which are required to accompany the ap... Read more