Register of advice
This list is a record of general advice provided by the Planning Inspectorate. We publish this to comply with the 2008 Planning Act.
Project specific advice can be viewed on the relevant project page.
Search advice
Search by key words or the name of person the advice was given to.
Showing 526 to 550 of 735 entries, newest first.
Results per page 25 | View 50 results per page | View 100 results per page
-
View advice to Pegasus Planning Group
I understand that legally energy projects of more than 50MW have to go down the IPC route. My query is whether projects of less than 50MW may also be referred to the IPC? The context is, we ha... Read more
-
View advice to Cotswold District Council
I would be grateful for your thoughts as to whether the IPC would be the determining authority for a development 50 - 200 MW gas fired turbine plant, rather than the District Council, due to the scale... Read more
-
View advice to SLR Consulting Ltd
I have submitted a planning application for a Biomass CHP facility. The facility will generate up to 25MWe and up to 35MWth (low grade steam). The planning authority are unsure as to whether the a... Read more
-
View advice to William Runciman
IPC has cropped up in relation to a planning application for a wind farm submitted I believe just prior to your coming into existence. As an individual it sounds to me as if your role is to streamline... Read more
-
View advice to Angela Norris
Caller asked for an overview of the development consent application process and the opportunities for public involvement
-
View advice to South Gloucestershire Council
Can the IPC determine whether or not a proposed electric line is a Nationally Significant Infrastructure Project (NSIP)?
-
View advice to Meridian Power
Mr Troughton of Meridian Power enquired how fees for the examination of a Nationally Significant Infrastructure Project are structured and if an estimate can be provided.
-
View advice to Consense
Ms Topham on behalf of Consense requested a meeting with the IPC regarding pre-application consultation and in specific web based consultation.
-
View meeting with Environment Agency
Liaison meeting with the Environment Agency
-
View advice to Petrochem Carless Ltd
The engineering manager at Petrochem Carless, a small oil refinery in Harwich Essex, wrote to the IPC to investigate the installation of a pipeline. A copy of that email and its attachements is pu... Read more
-
View advice to Michael Troughton
What will happen now the IPC has been abolished? If consent was needed for a generating station above 50MW would the application be considered by DECC under s.36? Why are DECC are still consid... Read more
-
View meeting with Quarry Battery Company
Refer to meeting note, attached
-
View advice to Kelvin Hui
I am writing to enquire as to which guidelines/ policies the IPC are currently using to guide application decisions (especially relating to energy projects) in light of the fact that the NPS' are stil... Read more
-
View advice to Network Rail
Mr Pearson of Network Rail enquired about regulation 5(2)(l) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 Regulations, states that plans and informati... Read more
-
View advice to Jacobs
If a development, that has received development consent through the IPC, starts but never reaches its original planned capacity/electricity generation, e.g. only 1 line is developed and not 3 lines do... Read more
-
View advice to Undine Scientific
Mr Smurthwaite enquired about the definition of extension under the Planning Act 2008 (the Act).
-
View advice to Pinsent Masons
Correspondent queried whether a Development Consent Order (DCO) may make provision for incidental matters dealt with by the Highways Act 1980 such as licencing the planting of trees in a highway (s142... Read more
-
View advice to Sheridan Treger
What is offshore development and where in regards to offshore development would an application have to be publicised under section 48 of the 2008 Planning Act?
-
View advice to Daniel Chapman
Having read the Planning Act 2008 new overhead transmissions lines which are rated at over 132kV require an application to the IPC. Can you tell me whether an IPC application is required if an exist... Read more
-
View advice to Office for Nuclear Development
Mr Petrie enquired how the IPC would consider material changes to a Development Consent Order after an application has been submitted and before consent has been granted in the absence of regulations ... Read more
-
View meeting with EdF Energy Nuclear New Build
The purpose of the meeting was to conclude discussions on an approach to handling applications for development consent for nuclear generating stations which was consistent both with the regulations go... Read more
-
View advice to Andrew Dobson
The enquiry can be viewed here: http://infrastructure.independent.gov.uk/wp-content/uploads/2011/04/MX-5000N_20110413_152745.pdf
-
View advice to Ross Taylor
Confirmation of timeframes for the examination and decision/recommendation stages of the IPC process and whether there might be indication from the Examining Authority if they anticipate the completio... Read more
-
View advice to Chris Eaglen
Dr Chris Eaglen wrote to us with some general queries and observations about Nuclear Generating Stations. A copy of his correspondence can be found here: http://infrastructure.independent.gov.uk/wp... Read more
-
View advice to Mark Pearson
Caller asked whether there was any scope for the IPC to extend an extant planning permission in connection with terrestiral works to a port.