Register of advice

This list is a record of general advice provided by the Planning Inspectorate. We publish this to comply with the 2008 Planning Act.

Project specific advice can be viewed on the relevant project page.

View all projects

Search advice

Search by key words or the name of person the advice was given to.

Showing 576 to 600 of 698 entries, newest first.

Results per page 25 | View 50 results per page | View 100 results per page

  • View advice to Network Rail

    Whether works can be included in DCO application which are Permitted development and other associated queries with regard to works necessary to achieve electrification

  • View advice to Ramblers Cymru

    When can we make a representation on a case? Specifically in the case of Nant-y-Moch Wind Farm, Wales

  • View advice to R W Richardson

    Would a scheme to underground part of an existing 132,000 kv overhead line need consent under the Planning Act 2008 (the Act)?

  • View advice to Redcar and Cleveland Council

    A few years ago this Council granted consent for the development of a new container terminal at PD Ports on Teesside. The approval we granted was for the landward works , the seaward works were... Read more

  • View advice to Susan Whitham

    Caller wished to make a representation on the merits of the scheme

  • View advice to Ceredigion County Council

    Do you publish the Local Impact Report documents on your website along with the other Project Documents? I’ve been trying to find an example of an LIR that has been submitted to yourselves.

  • View advice to EDF Energy

    I work for EDF Energy in Asset Development. One of our projects relates to increasing our biomass co-firing capability within an existing coal-fired power station. We have co-milling capability within... Read more

  • View advice to Kings Lynn Council

    Would a generating station be considered a Nationally Significant Infrastructure Project (NSIP) if it does not have the intention to link up to the national grid?

  • View advice to Penspen Ltd

    Query is in relation to whether a proposed application for a DCO (a gas-fired power station/compressor station/wellhead and a cross-country pipeline (more than 10 miles long), is to be classified as... Read more

  • View advice to Ben Porte

    Further to our telephone conversation on 26 November 2010 I thought it prudent to seek clarity on the issues that have since arisen. My client has recently discovered that an existing power line... Read more

  • View advice to Victoria Hamlyn

    I am a PhD student at the University Plymouth researching the legal regimes governing marine renewable energy in England and Wales (with a focus on wave energy). At the moment I am researching the... Read more

  • View meeting with Civil Aviation Authority

    Introductory Meeting for the CAA to learn more about the IPC and the 2008 Planning Act process. Also for the IPc to learn more about the CAA and related issues around aerospace aand NSIPs,... Read more

  • View advice to RSK Environment LTD

    I have now spoken with Tees Refining Limited regarding progression of the project in light of your recent email. Our view is that, given the inherent linkages between the various components of the... Read more

  • View advice to Hannah Sweilam

    Ms Sweiham called the IPC enquires line to ask whether or not, in general terms, conversion of a coal-fired generating station to fire biomass fuel would represent a nationaly significant... Read more

  • View advice to CCW

    Is there any flexibility or chance to extend a 28 day deadline for consultation under section 42 of the Planning Act, which includes preliminary environmental information? Or is the 28 days a... Read more

  • View advice to Charles Rogers

    Are effects on health relevant to an examination?

  • View advice to Bill Douie

    Requesting advice as to whether planning consent is required for the installation of portacabins or other temporary structures for the purpose of training on Railway Land leased from Network Rail in... Read more

  • View advice to John Morgan

    What is the deadline given to Local Authorities for the submission of (a) their adequacy of consultation representation and (b) their Local Impact Reports (LIR)

  • View advice to Karen Howard

    Q1: Can CPO powers necessary for an NSIP be sought in parallel to an application under alternative legislation? (The query related to managing likely CPO powers as part of a project timetable- i.e.... Read more

  • View advice to Nathaniel Lichfield and Partners

    As discussed, our client is developing a proposals for a carbon reclaimation and processing plant for the purpose of generating aviation fuel. The input will be approximately 500,000 tonnes of... Read more

  • View meeting with National Air Traffic Service (NATS)

    Introductory/strategic overview meeting requested by NATS to dicuss and comprehend the IPC's role and processes.

  • View advice to RSK Environment Ltd

    Email regarding a proposed application for an oil processing plant in Teesside. A query was raised as to whether an oil processing plant can lawfully be determined as an NSIP under the current... Read more

  • View advice to NVQ Academy

    Is there an age limit for people who wish to fill in a relevant representation form?

  • View advice to Dover District Council

    I would appreciate your advice in respect of a development proposal that may come forward in the near future, on a site that falls within the Dover and Thanet Council district boundaries. The... Read more

  • View advice to Powys County Council

    1. At which stage in the process does the Local Authority (LA) comment on an applicant's consultation activities? 2. Do LAs have to register as interested parties following the acceptance of an... Read more