The list below includes a record of advice we have provided for this project.

There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.

Search advice

Search by key words or the name of person the advice was given to.

Showing 1 to 30 of 30 documents, newest first.

Results per page View 25 results per page | View 50 results per page | 100

  • View meeting with Able Humber Ports Limited

    A meeting took place between Able Humber Ports Limited and the Planning Inspectorate to discuss a potential change to the DCO

  • View advice to Stephen Kirkwood

    I am finding it very difficult to negotiate my way through both the site and the process. The Planning Inspectorate stated a couple of weeks ago that the proposed wetland creation site was not part o... Read more

  • View advice to David Hickling

    Have the new Able UK proposals at Cherry Cobb Sands been screened for EIA purposes? If so, by whom and what was the verdict (bearing in mind the 'part of a bigger scheme' clause in the Regs)?

  • View advice to Care Plus (NHS)

    A letter has arrived at 1 Prince Albert Gardens today and been delivered to me. However, I am not the correct recipient. Would you kindly advise as to whom this letter should go to and I will hand... Read more

  • View advice to Groveport Logistics Ltd

    We write as the directors of Groveport Logistics Limited, the owners and operators of Groveport, being a large port complex on the River Trent. We consider ourselves to be a significant Humber port an... Read more

  • View advice to Natural England

    Further to the Examining Authority?s Rule 8 letter below, and the questions contained within it, my colleagues and I have a couple of queries which I should be grateful if you could assist us with. Th... Read more

  • View advice to Highways Agency

    Thank you for forwarding a copy of the Rule 8 letter to me. I would be grateful if you would clarify/amend question 72 in Appendix D1 as follows: (a) The Rosper Road/Humber Road junction is not pa... Read more

  • View advice to Highways Agency

    Thank you for forwarding a copy of the Rule 8 letter to me. I would be grateful if you would clarify/amend question 72 in Appendix D1 as follows: (a) The Rosper Road/Humber Road junction is not p... Read more

  • View advice to Rod Ambler

    An email was received with comments concerning the Able Marine Energy Park proposal

  • View advice to Simon Taylor

    I have submitted a representation for Able Marine Energy Park and wish to add information to my representation. Could you send me Advice notes concerning making a relevant representation, the Develope... Read more

  • View advice to Ken Jones

    An email was received with comments concerning the Able Marine Energy Park

  • View advice to East Riding of Yorkshire Council

    I have received a letter from ABLE UK advising me that their application is able for the public to view in Hedon Customer Service Centre from 20th February - 2nd April 2012. As I haven't been invo... Read more

  • View advice to Wind Prospect

    What are the timescales following acceptance

  • View advice to Hull City Council

    Mr Codd requested clarification on any deadlines associated with the submission of Hull City Council's Local Impact Report (LIR).

  • View advice to RSPB

    Concerns were raised about pre-application consultation

  • View advice to Winckworth Sherwood

    Winckworth Sherwood wrote to the IPC identifying points of concern relating to the pre-application consultation carried out by Able UK Ltd.

  • View advice to Osborne Clarke

    Osborne Clarke wrote to the IPC identifying points of concern relating to the pre-application consultation carried out by Able UK Ltd.

  • View advice to DLA Piper UK Ltd

    DLA Piper UK Ltd wrote to the IPC identifying points of concern relating to the pre-application consultation carried out by Able UK Ltd.

  • View advice to Hull City Council

    Hull City Council sought to understand the likely timescale for the preparation and submission of a Local Impact Report should an application be accepted.

  • View advice to Bircham Dyson Bell LLP

    The developer provided the IPC with a draft Development Consent Order for comment.

  • View advice to Bircham Dyson Bell LLP

    Mr Walker enquired about the potential for inclusion of requirements within the DCO in relation to agreeing finished ground levels of the compensatory land with the regulator and Local Authority.

  • View advice to Angus Walker

    Mr Walker raised queries about plans in relation to Tree Preservation Orders and amendments to the DCO.

  • View advice to DLA Piper UK

    Representatives of a potential stakeholder raised queries concerning consultation.

  • View advice to John Wang

    Mr Wang requested application documents for the Able Marine Energy Park proposed application.

  • View advice to Able UK

    The IPC provided advice concerning the applicants Draft Habitats Regulations Assessment (HRA) Report.

  • View advice to East Riding of Yorkshire Council

    I am in pre-application consultation with Able regarding the diversion of a Public Footpath. This is my first encounter with a scheme that is to be submitted to the IPC and would like some advice. ... Read more

  • View advice to RSPB

    We understand that the Able UK Ltd is currently undertaking pre-application consultation on the Able Marine Energy Park (AMEP) at North Killingholme. This includes consultation on the preliminary envi... Read more

  • View meeting with Able UK

    Meeting with scheme promoter to provide a project update.

  • View advice to Osborne Clarke

    Please see link for copy of query - http://infrastructure.independent.gov.uk/wp-content/uploads/2011/02/110204_TR030001_OC_letter_re_NSIP_thresholds1.pdf

  • View advice to Able UK

    Mark, We are preparing the Preliminary Environmental Information Report for consultation with the public in respect of the above project. We would not normally publicise information on Badgers sin... Read more