The list below includes a record of advice we have provided for this project.
There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.
Search by key words or the name of person the advice was given to.
Showing 1 to 22 of 22 documents, newest first.
Results per page View 25 results per page | 50 | View 100 results per page
Could someone explain why work has started on the construction of the rail compounds, e.g. at Sheepway Farm; has other work started of which I am not aware? Is this DCO application, which is still sub... Read more
My wife and I have both received a letter asking for a contact email in relation to the application by North Somerset Council for an order granting development consent for the Portishead Branch Line -... Read more
Advice following issue of decision to accept the application for Examination
Post Acceptance advice on concerns related to the Flood Risk Assessment (FRA)
Advice to the Applicant following issue of decision to accept the application for Examination
Advice regarding the status of notifications made in accordance with the 2009 EIA Regulations and the applicability with likewise requirements in the 2017 EIA Regulations.
Please see the attachment
At the MetroWest Phase 1 meeting with you on 25th June we asked whether PINS required notification under Regulation 8 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017 ... Read more
The applicant raised the following enquiries pertaining to their proposed DCO application expected for submission in September 2019: a. Could you please confirm you would like to see a revised version... Read more
Project Update Meeting
Project update meeting
Project update meeting 23 February 2018
My query relates to Regulation 11(c)(ii) of the Infrastructure Planning (EIA) Regulations 2017. Regulation 11(c)(ii) requires the Secretary of State or relevant authority to notify the applicant i... Read more
In the MetroWest Scoping Opinion (August 2015), PINS identified LNG at Appendix 1 as a "relevant statutory undertaker" for EIA consultation purposes. In March 2017, LNG was dissolved and struck of... Read more
Portishead Branch Line Site Visit
Portishead Branch Line Project Update Meeting Note
In your correspondence you pose a series of questions in respect of the proposals to reopen the railway line between Bristol and Portishead. More specifically you ask why a Development Consent Order ... Read more
Update on project progress to date
Note of inception meeting. See attached.