Chwiliwch yn ôl yr unigolyn neu'r grŵp sy'n gwneud y cyflwyniad neu gynnwys y cyflwyniad.
-
Anglian Water Services is the statutory water and wastewater services provider for the proposed pipeline route from Immingham to Theddlethorpe in North East Lincolnshire and East Lindsey District...
Darllen mwy
-
ASSOCIATED PETROLEUM TERMINALS (IMMINGHAM) LIMITED AND HUMBER OIL TERMINALS TRUSTEE LIMITED PROPOSED VIKING CCS CARBON DIOXIDE PIPELINE DEVELOPMENT CONSENT ORDER RELEVANT REPRESENTATION 1 Introduction...
Darllen mwy
-
• No attempt to meet to discuss commercial terms whatsoever and a lack of meaningful consultation with the landowners and their agents. • No attempt to discuss a methodology for the pipeline...
Darllen mwy
-
Please see attached
-
Calor Gas Limited are the owners and operators of the Calor Cylinder Distribution site, which is located off Manby Road (A1173) and is used for the storage and distribution of liquefied petroleum gas...
Darllen mwy
-
No attempt to meet to discuss commercial terms whatsoever and a lack of meaningful consultation with the landowners and their agents. No attempt to discuss a methodology for the pipeline construction...
Darllen mwy
-
Historic England Advice - Our ref PL00794831 Viking CSS. The Historic Buildings and Monuments Commission for England (HBMCE) is better known as Historic England, and we are the Government’s adviser on...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
The Marine Management Organisation (MMO) will retain a watching brief on this proposal. A draft deemed marine licence has not been submitted, therefore the MMO have no comments at present. However if...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•No attempt to meet to discuss commercial terms whatsoever and a lack of meaningful consultation with the landowners and their agents. •No attempt to discuss a methodology for the pipeline...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Relevant Representation of National Grid Electricity Transmission Plc in respect of the Viking CCS Pipeline DCO (the “Project”) This relevant representation is submitted on behalf of National Grid...
Darllen mwy
-
Viking CCS Pipeline Project (EN070008) SECTION 56 PLANNING ACT 2008: RELEVANT REPRESENTATION OF NATIONAL HIGHWAYS LIMITED NATIONAL HIGHWAYS LIMITED (“National Highways”) has been appointed by the...
Darllen mwy
-
Please advise if there is an e mail address I can copy document to. Thank you. Date: 15 January 2024 Our ref: 24768 Your ref: EN07 0008 The Planning Inspectorate Major Applications & Plans Temple Quay...
Darllen mwy
-
Thank you for the opportunity to register as an Interested Party. North East Lincolnshire Council is a host authority. We have been liaising directly with the developer for some time now and have...
Darllen mwy
-
North Lincolnshire Council is aware that as the host Authority we will be automatically registered as an Interested Party in the Viking CCs Pipeline examination, under Section 102(1)(c) of the...
Darllen mwy
-
The following representations are submitted on behalf of Northern Powergrid (Yorkshire) Plc (‘Northern Powergrid’) as an electricity undertaker for the area within which the Viking CCS Pipeline DCO...
Darllen mwy
-
Application by Chrysaor Production (U.K.) Limited (“Chrysaor”) for an Order Granting Development Consent for the Viking CCS Pipeline ("the Project") 1. This Relevant Representation is submitted on...
Darllen mwy
-
PHILLIPS 66 LIMITED PROPOSED VIKING CCS CARBON DIOXIDE PIPELINE DEVELOPMENT CONSENT ORDER RELEVANT REPRESENTATION Introduction 1.1 This is a relevant representation (“RR”) for and on behalf of...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
• Failure to agree a method statement for the pipeline construction and failure to provide clarity regarding construction depth of the pipeline and assurances that the land can be farmed going forward...
Darllen mwy
-
Thank you for your consultation regarding the above development. The UK Health Security Agency (UKHSA) welcomes the opportunity to comment on your proposals at this stage of the project. Please note...
Darllen mwy
-
1. Agreement on unfarmable severed areas; 2. Management of severed land; 3. Control of (injurious) weeds on stored soils; 4. Maintaining on-going water supplies to residential premises; 5....
Darllen mwy
-
Representations on behalf of The Haigh Family First Estate Settlement (for themselves, R H C Haigh, the R Haigh 2022 No. 1 Settlement and S A C Haigh):- 1. Agreement on unfarmable severed areas; 2....
Darllen mwy
-
VPI Immingham LLP Representation This representation is made by VPI Immingham LLP in relation to the Viking CCS DCO Application. VPI Immingham LLP owns and operates the existing 1260 megawatt (MW)...
Darllen mwy
-
Our primary concern is in relation to survivability in the event of a pipeline rupture. Unfortunately, throughout the consultation process, the applicant has been unwilling to engage with affected...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Planning & Strategic Infrastructure at East Lindsey District Council, The Hub, Mareham Road, Horncastle, Lincolnshire, LN9 6PH. S56 Notification – Relevant Representation – Summary Viking CCS...
Darllen mwy
-
Construction of pipelines and safety valves? And gas leaks
-
Dear Sir/Madam Planning Act 2008 (as amended) – Section 55 Application by Chrysaor Production (UK) Limited Development Consent Order for Viking CCS Relevant Representations Following the Planning...
Darllen mwy
-
Introduction This is the representation of Statera Energy Limited (“Statera”) and its wholly owned subsidiary, Mablethorpe Flexible Generation Limited (“Mablethorpe”) to the application by Chrysaor...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Relevant Representation of National Gas Transmission Plc in respect of the Viking CCS Pipeline DCO This relevant representation is submitted on behalf of National Gas Transmission Plc (“NGT”) in...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
The application documents have been reviewed. The area of the proposals which run through and are adjacent to the West Lindsey District are in line with our previous consultation responses and...
Darllen mwy
-
Fully Withdrawn via REP1-096 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Fully Withdrawn via REP1-104 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Fully Withdrawn via REP1-097 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
To whom it may concern, Viking CCS Pipeline consultation response relating to the Easington-Immingham Condensate Pipeline, prepared by Strutt & Parker on behalf of Centrica. Strutt & Parker acts on...
Darllen mwy
-
Fully Withdrawn via REP1-107 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-108 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-109 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-111 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
The Environment Agency has reviewed the Development Consent Order (DCO) application, the Environmental Statement (ES) chapters and supporting documents relevant to environmental issues within its...
Darllen mwy
-
Fully Withdrawn via REP1-116 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-117 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Fully Withdrawn via REP1-121 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Fully Withdrawn via REP1-099 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-101 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
•Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents •Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Fully Withdrawn via REP1-143 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-145 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
• Failure to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failure to agree a method statement for the pipeline construction and failure to...
Darllen mwy
-
Fully Withdrawn via REP1-102 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-103 My client wishes to raise the following concerns surrounding the project; • Failure to agree commercial terms due to a lack of meaningful consultation with the landowners...
Darllen mwy
-
Fully Withdrawn via REP1-106 The schemes has; • Failed to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failed to agree a method statement for...
Darllen mwy
-
Fully Withdrawn via REP1-098 The schemes has; • Failed to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failed to agree a method statement for...
Darllen mwy
-
We are an energy developer and service provider, deploying several large scale decarbonised energy projects across the UK, including potentially in the area to which the development relates...
Darllen mwy
-
Fully Withdrawn via REP1-120 My clients property is affected by a proposed permanent access route to the above ground infrastructure and there has been little consultation regarding this. Also, the...
Darllen mwy
-
Good afternoon, The following comments were sent direct to Viking CCS's agent (Gately Hamer) on Friday 2nd December 2023 via E Mail, which also included an attached set of shape files identifying the...
Darllen mwy
-
The schemes has; • Failed to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failed to agree a method statement for the pipeline construction and...
Darllen mwy
-
Fully Withdrawn via REP1-141 The schemes has; • Failed to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failed to agree a method statement for...
Darllen mwy
-
Fully Withdrawn via REP1-142 The schemes has; • Failed to agree commercial terms due to a lack of meaningful consultation with the landowners and their agents • Failed to agree a method statement for...
Darllen mwy
-
Planning Inspectorate Temple Quay House 2 The Square Bristol BS1 6PN Tuesday, 09 January 2024 To the Planning Inspectorate Planning Act (2008) as amended Relevant Representation made on behalf of...
Darllen mwy
-
Mablethorpe and Sutton Town Council resolved, at the planning meeting on Monday 8th January, to register as an interested party and be involved in the process with the objective of protecting our...
Darllen mwy
-
The proposed CO2 pipeline route overlaps with Uniper's high pressure natural gas pipeline from Theddlethorpe to Killingholme. There is a HSSE risk and therefore Uniper must be fully engaged at all...
Darllen mwy
-
Relevant Representation: Viking CCS Pipeline 1.1 This representation is submitted by Air Products (BR) Limited (Air Products) in respect of the proposed Viking CCS Pipeline project (Viking). Air...
Darllen mwy
-
We act for DVSA and we have been liaising with solicitors and agents acting for the Promoter. DVSA occupies a site on which Promoter's agent has confirmed the Promoter intends to use, at the very...
Darllen mwy
-
Practical Comments - The works are carried out and completed on the land within a 12-month period ending June, to enable the land to be returned to full agricultural production, timely that autumn AND...
Darllen mwy
-
Application route south-eastern extent of the pipeline is located just to the south of the Donna Nook Air Weapon Range estate, but is within the plan R (Range) statutory consultation zone. The MOD...
Darllen mwy
-
APPLICATION BY CHRYSAOR PRODUCTION (U.K.) FOR AN ORDER GRANTING DEVELOPMENT CONSENT FOR VIKING CCS PIPELINE Planning Inspectorate Reference Number: EN070008 Section 56 Planning Act 2008: Relevant...
Darllen mwy
-
My client has yet to agree terms for the Option Agreement for Lease, we reserve the ability to make personal reps or changes to these document in the future. My client has yet to agree terms for a...
Darllen mwy
-
My client has yet to agree terms for the Option Agreement for Lease, we reserve the ability to make personal reps or changes to these document in the future. My client has yet to agree terms for a...
Darllen mwy
-
My client has yet to agree terms for the Option Agreement for Lease, we reserve the ability to make personal reps or changes to these document in the future. My client has yet to agree terms for a...
Darllen mwy
-
The proposed Viking CCS pipeline and associated heavy construction works will have a direct, and we believe negative, impact on the lives and homes of residents in our village. Many local people have...
Darllen mwy
-
As a community we are very concerned about the potential impact of such a massive project. Information received to date has not filled us with confidence. The construction work will have a detrimental...
Darllen mwy
-
We have just moved here. A long-awaited move to a place where coast and countryside collide. We chose this area because of the beautiful countryside, the close proximity to the sea, the wildlife and...
Darllen mwy
-
BPA maintains the Prax owned high pressure fuel pipeline that is crossed by this project. Consequently, all activities in close proximity to the pipeline must be reviewed and accepted by us to ensure...
Darllen mwy
-
Technical and environmental impacts
-
Impact to residents Depth of pipeline Safety issues if pipe ruptures
-
I am against this project
-
This proposal facilitates the Capture and Storage of Carbon Dioxide, in an attempt to curb rising atmospheric levels of greenhouse gases which are the cause of global heating / anthropogenic climate...
Darllen mwy