Search by the person or group making the submission or the content of the submission.
-
Peridot Solar Ltd and its wholly owned Assured Asset Solar 2 Ltd requests that National Highways abide by the Letter of Comfort supplied in the solar farm & BESS planning application ref:...
Read more
-
Submission by Think Again, Winthorpe Action Group 1. Summary Think Again has been liaising with National Highways and their agents since the public consultation on the proposals since 2020. Many of...
Read more
-
1.I am not satisfied that all avenues have been explored such that the effect on our land is avoided. 2. If it is absolutely essential that our land and its rights are affected then we need to know...
Read more
-
Concern over the impact dualling of the A46 around Newark will have on future flooding events in Newark and the surrounding areas, despite information received advising that mitigating plans are in...
Read more
-
As owners of the property (redacted), we feel it is prudent to list some of our concerns both during works and the long-term effects when the works are completed on the new A46 Newark bypass. We were...
Read more
-
I am particularly concerned about: 1. Pollution caused by construction works and due to increased traffic flow following completion and the direct affect of this on the the health and wellbeing of the...
Read more
-
I want to register my concerned that the bypass will increase particulate pollution including dust in its construction and use. Has this impact been assessed? I would also like you to assess the scope...
Read more
-
I am concerned following the recent Supreme Court ruling that scope 3 emissions do not appear to have been taken into consideration for this infrastructure project. ie the projected increase in CO2...
Read more
-
We are concerned about: 1.Increase in pollution (both during construction and on build completion) and health impacts for the Newark population. 2.Loss of natural environment, habitats, trees,...
Read more
-
We're registering because many residents use the road regularly and we want to be able to put forward their views.
-
1)Impact on Pine Cottage, Hargon Lane. Can I see specific landscaping, noise and vibration reduction plans along with light pollution reduction measures to prevent vehicle headlights and street lights...
Read more
-
Comments submitted by Lucie Muddiman (Savills (UK) Ltd) on behalf of John James Miller ‘ John Miller’ to: “Register to have your say about a national infrastructure project due by 14 July 2024” Land...
Read more
-
The proposed development will increase carbon emissions and will futher degrade air quality. I request that you refuse development consent
-
Dr Andrew Boswell, Climate Emergency Planning and Policy Independent environmental consultant specialising in climate science, policy, and law. The environmental statement for the scheme, including...
Read more
-
The Newark & Nottinghamshire Agricultural Society (“NNAS”) is a Charity whose principal objective is to support and promote Agriculture and related industries. It achieves this through various...
Read more
-
1) The underpass - Our children and school community use the underpass to cycle and walk to school. Some of our pupils take this route by themselves. It is imperative for the school that the cycling...
Read more
-
RWE Generation UK are the owners and operators of the Staythorpe Power Station. RWE have an interest in the possible impacts the proposed development may have on the operation and future development...
Read more
-
Our Company, support the proposed project. The current A46 layout causes significant traffic congestion at peak times (such as Friday afternoons). The traffic congestion is not limited to the A46...
Read more
-
I can confirm there are 2 areas within the entire order limits of the plan that may affect existing GTC infrastructure; the order limits red line boundary, as showing in the attached documents on the...
Read more
-
I feel the current options are not fit for purpose. We need a bypass fit for the next 50-100 years. The current by-pass was outdated with a few years of being built and not the option originally...
Read more
-
My Council will be interested in the following issues: Access to Newark and the impact of the work to the A46 roundabout. Noise Flood Compensation Areas and the potential impact on flooding in the...
Read more
-
Our charity owns some land that is rented by a tenant farmer for agricultural purposes. The project will, according to the latest plans and our previous discussions with National Highways and their...
Read more
-
That a major scheme to speed up motor vehicles movement on the A46 and A1 neglects to improve Active Travel journeys/options, especially on the eastern side of Newark where the A1, A46 & A17 junction...
Read more
-
The information is very difficult to get at. We own the old branch line adjacent Kings Mill Marina. There is insufficient detail to comment in a meaning ful way.We want to know what is proposed...
Read more
-
I am the landowner of (redacted), on which it is proposed by National Highways to take land and lower surface to bring it within flooding levels as part of Flood Compensation in relation to the A46...