  • Peridot Solar Ltd (Peridot Solar Ltd)

    Peridot Solar Ltd and its wholly owned Assured Asset Solar 2 Ltd requests that National Highways abide by the Letter of Comfort supplied in the solar farm & BESS planning application ref:... Read more

  • Think Again, Winthorpe Action Group (Think Again, Winthorpe Action Group)

    Submission by Think Again, Winthorpe Action Group 1. Summary Think Again has been liaising with National Highways and their agents since the public consultation on the proposals since 2020. Many of... Read more

  • Aldergate Properties Ltd (Aldergate Properties Ltd)

    1.I am not satisfied that all avenues have been explored such that the effect on our land is avoided. 2. If it is absolutely essential that our land and its rights are affected then we need to know... Read more

  • Wendy Catherine Greenwood

    Concern over the impact dualling of the A46 around Newark will have on future flooding events in Newark and the surrounding areas, despite information received advising that mitigating plans are in... Read more

  • Challenge Ltd (Challenge Ltd)

    As owners of the property (redacted), we feel it is prudent to list some of our concerns both during works and the long-term effects when the works are completed on the new A46 Newark bypass. We were... Read more

  • Ian Thomson

    I am particularly concerned about: 1. Pollution caused by construction works and due to increased traffic flow following completion and the direct affect of this on the the health and wellbeing of the... Read more

  • Simon Tilley

    I want to register my concerned that the bypass will increase particulate pollution including dust in its construction and use. Has this impact been assessed? I would also like you to assess the scope... Read more

  • Extinction Rebellion Newark and Sherwood (Extinction Rebellion Newark and Sherwood)

    I am concerned following the recent Supreme Court ruling that scope 3 emissions do not appear to have been taken into consideration for this infrastructure project. ie the projected increase in CO2... Read more

  • Protect Newark's Green Spaces (Protect Newark's Green Spaces)

    We are concerned about: 1.Increase in pollution (both during construction and on build completion) and health impacts for the Newark population. 2.Loss of natural environment, habitats, trees,... Read more

  • Collingham Parish Council (Collingham Parish Council)

    We're registering because many residents use the road regularly and we want to be able to put forward their views.

  • Andrew Leary

    1)Impact on Pine Cottage, Hargon Lane. Can I see specific landscaping, noise and vibration reduction plans along with light pollution reduction measures to prevent vehicle headlights and street lights... Read more

  • Savills (Savills) on behalf of John James Miller

    Comments submitted by Lucie Muddiman (Savills (UK) Ltd) on behalf of John James Miller ‘ John Miller’ to: “Register to have your say about a national infrastructure project due by 14 July 2024” Land... Read more

  • Robert Palgrave

    The proposed development will increase carbon emissions and will futher degrade air quality. I request that you refuse development consent

  • Climate Emergency Planning and Policy (Climate Emergency Planning and Policy)

    Dr Andrew Boswell, Climate Emergency Planning and Policy Independent environmental consultant specialising in climate science, policy, and law. The environmental statement for the scheme, including... Read more

  • Newark & Notts Agricultural Society (Newark & Notts Agricultural Society)

    The Newark & Nottinghamshire Agricultural Society (“NNAS”) is a Charity whose principal objective is to support and promote Agriculture and related industries. It achieves this through various... Read more

  • Winthorpe Primary School (Winthorpe Primary School)

    1) The underpass - Our children and school community use the underpass to cycle and walk to school. Some of our pupils take this route by themselves. It is imperative for the school that the cycling... Read more

  • RWE Generation UK PLC (RWE Generation UK PLC)

    RWE Generation UK are the owners and operators of the Staythorpe Power Station. RWE have an interest in the possible impacts the proposed development may have on the operation and future development... Read more

  • W A Rainbow & Sons Ltd (W A Rainbow & Sons Ltd)

    Our Company, support the proposed project. The current A46 layout causes significant traffic congestion at peak times (such as Friday afternoons). The traffic congestion is not limited to the A46... Read more

  • GTC Pipelines Ltd (GTC Pipelines Ltd)

    I can confirm there are 2 areas within the entire order limits of the plan that may affect existing GTC infrastructure; the order limits red line boundary, as showing in the attached documents on the... Read more

  • Stewart Codd

    I feel the current options are not fit for purpose. We need a bypass fit for the next 50-100 years. The current by-pass was outdated with a few years of being built and not the option originally... Read more

  • Farndon Parish Council (Farndon Parish Council)

    My Council will be interested in the following issues: Access to Newark and the impact of the work to the A46 roundabout. Noise Flood Compensation Areas and the potential impact on flooding in the... Read more

  • The Charity of Thomas Brewer (The Charity of Thomas Brewer)

    Our charity owns some land that is rented by a tenant farmer for agricultural purposes. The project will, according to the latest plans and our previous discussions with National Highways and their... Read more

  • Newark A46 Active Travel Partnership (Newark A46 Active Travel Partnership)

    That a major scheme to speed up motor vehicles movement on the A46 and A1 neglects to improve Active Travel journeys/options, especially on the eastern side of Newark where the A1, A46 & A17 junction... Read more

  • Newark Branch Line;Aldergate Properties (Newark Branch Line;Aldergate Properties)

    The information is very difficult to get at. We own the old branch line adjacent Kings Mill Marina. There is insufficient detail to comment in a meaning ful way.We want to know what is proposed... Read more

  • Adrian Peter Hatton

    I am the landowner of (redacted), on which it is proposed by National Highways to take land and lower surface to bring it within flooding levels as part of Flood Compensation in relation to the A46... Read more