Register of advice
This list is a record of general advice provided by the Planning Inspectorate. We publish this to comply with the 2008 Planning Act.
Project specific advice can be viewed on the relevant project page.
Search advice
Search by key words or the name of person the advice was given to.
Showing 601 to 698 of 698 entries, newest first.
Results per page View 25 results per page | View 50 results per page | 100
-
View advice to MMO
Enquirer asked if public inquiries still took place under the new planning regime.
-
View advice to Client Earth
Does the IPC deal with applications for generating stations in Scotland?
-
View advice to David Toke
Can you tell me what the arrangements are for the issue of licenses under the European protected species requirement (do you issue this?) and also the 1991 water act for cabling crossing rivers (the... Read more
-
View advice to Bill Temple-Pediani
Dr Temple-Pediani wrote to us to ask what would happen if one element of an NSIP project were concented whilst the other were not.
-
View advice to David Gavin
My question is "can a Compulsory Purchase Order be applied for at the same time as the application to the IPC and determined in parallel with the application."
-
View advice to British Telecom & UKCPC
Mr Hill represents both British Telecom and the UKCPC; he feels both the organisations he represents should be statutory consultees.
-
View meeting with Various
Stakeholder meeting at Aberystwyth to discuss the IPC process
-
View advice to HPA
Caller wanted some information on the examination process and how to make representations
-
View advice to Marrons
If (i) you obtain a planning permission for a development and there is a condition attached which, say, requires that Area A should only be used for open space purposes, (ii) you then... Read more
-
View advice to Marrons
As a general principle, can you please confirm whether a Requirement imposed on a grant of Development Consent, is superseded by a subsequent grant of planning permission as a planning condition would... Read more
-
View meeting with The Crown Estate
Meeting with The Crown Estate to discuss issues which may arise as offshore wind developers follow the new planning process.
-
View advice to Pegasus PG
Mr Atkin called and requested if Nuclear Power stations were to by-pass planning all togethor in an attempt to speed up the process for Nuclear Power station builds.
-
View advice to Gary Reevell
Could you advise me if you have ever received an application for a 40MW biomass power plant at Scawby Brook, Brigg. North Lincolnshire? The application was refused by the local council earlier this... Read more
-
View advice to EWTEC
Is it possible, once an application has been submitted to the IPC, for the sheme to be altered to fall beneath the threshold of a Nationally Significant Infrastructure Project (NSIP) and still be... Read more
-
View advice to North Lincolnshire Council
My question relates to what happens after the application is granted in relation to minor amendments. I.e. If there was an application for an amendment to part of the original application would this... Read more
-
View advice to Lancashire County Council
Enquirer sought clarification on s22 (2) (b) of the Planning Act 2008 as there is a high level of ambiguity.
-
View advice to Cognisant Research
Developers are required to fund all consultation activities, including any evaluation undertaken by the relevant Local Authority. Is this accurate?
-
View advice to BPE Design & Support Ltd
Dear Sir/Madam I am currently working on the outline design for a 50 MWatt biomass power station in Southern England and would appreciate your advice regarding the Registered Generator Capacity in... Read more
-
View advice to Bill Temple-Pediani
Infimation copied to you was not with the intention of IPC influencing LB of Newham in any way on its LDF. It is the IPC which advised me earlier this year, which you are repeating in today's e-mail,... Read more
-
View advice to Bill Temple-Pediani
Dr Temple-Pediani called to discuss KTI energy's proposals for the Unex site in the Royal Docks, and advice that had been given in the past.
-
View advice to Bill Temple-Pediani
Dr Temple-Pediani of KTI energy copied us into correspondence which, intentionaly or otherwise, suggested that we had an oversight role over the behaviour or performance of local authorities, and that... Read more
-
View advice to Mariana Heimrich
If we submit an application how would you let us know that you have accepted/refused it?
-
View advice to GVA Grimley
What weight is to be given to National Policy Statements (NPSs) in in comparison to Planning Policy Statements (PPSs)/Planning Policy Guidance (PPG) and is a S.36 still applicable?
-
View advice to KTI Energy
Dr Temple-Padiani wrote to us to express dissatisfaction with the requirements of the 2008 NSIP regime and to ask for guidence on whether or not a proposed course of action would satisfy those... Read more
-
View advice to SLR Consulting Ltd
We are a consultancy working on a planning application at Hoo Island in the Medway Channel. The Island has a long standing permission for the deposit of dredged material and engineering... Read more
-
View advice to Robert Wynn & Sons
Thank for your email in response to my request for guidance regarding the process for ensuring that the decisions made by the IPC are mindful of Government policy in connection with the movement of... Read more
-
View advice to Mel Roberts
I am Mel Moench from Moench Inc. (www.moenchinc.com) and we are evaluating a scale-up of our technology to the size of a municipal power plant. We feel that our grass combustion technology would... Read more
-
View meeting with Various Stakeholders North East England
Meeting Note from outreach event on 23 September 2010 with various stakeholders.
-
View meeting with Various Various
Minutes of the Offshore Consenting Forum meeting held at the IPC Office, Temple Quay, Bristol on 22nd September 2010. Attendees were the IPC, Natural England, Joint Nature Conservation Committee,... Read more
-
View advice to Neil Miller
With regards to underground gas storage, an amendment to an existing production licence may be required - Would this application be submitted to DECC or to the IPC as part of a DCO?
-
View advice to Bridgend County Council
A call from Jonathan Parsons requesting copies of all the IPC's advice notes and the generic leaflet in English and Welsh in order to enable officers to brief members about the work of the IPC and the... Read more
-
View advice to Nicola Pilkington
Nicola pilkington called and would like to know the casework team for Hinkley point C power station and also if the whole team are going to be available for the proposed submission date of the 01 12... Read more
-
View advice to English Heritage
Your letter refers to the submission of two proposals relating to the north east region. Whilst we have been consulted by the developer on the Port of Blyth Biomass Plant proposal on the basis that... Read more
-
View meeting with Various Stakeholders
Outreach event in connection with various schemes in the Humberside area
-
View advice to Graham Wrigglesworth
I would be grateful if you could advise whether compulsory access to private land in connection with an NSIP would need to be obtained from the IPC pursuant to section 53 of the Planning Act 2008 or,... Read more
-
View advice to Freedom Group
Query from company Freedom Group who are looking at opportunities to provide consents services to utility companies. Worked with National Grid and Transco in the past and wanted to make sure we had a... Read more
-
View advice to Siemens Windpower
Phone call from Theresa Cook, Head of Business Development, and Jasper Miller of Siemens Windpower [SW] about possible investment in UK. Referred to IPC by British Embassy in Copenhagen.
-
View advice to Natural England
Mr Neale called requesting further information on the Hole House Farm Gas Pipeline project, proposed by National Grid. He sought further information and clarity on the project's status and whether the... Read more
-
View advice to Able UK Ltd
What are the logistics for submitting a scoping report to the IPC for an opinion?
-
View advice to Bill Temple-Pediani
Dr Temple-Pediani wrote to clarify whether or not a proposal for a generating scheme forming part of a larger building in the Royal Docks fell to be considered by the London Borough of Newham or by... Read more
-
View advice to Sellafield Ltd
I havent read the detailed guidance as yet but, wondered if you have a process flow chart or timeline thats shows all the process steps with indicative durations and whose involved -step by step ... Read more
-
View advice to Paula Craig
Paula Craig, a researcher at Queens University Belfast, wrote to us to ask for some general information about the role of the IPC and the process by which policy was formed.
-
View advice to Jacobs
Planning permission has already been granted for construction of 9 underground gas storage caverns (approx total capacity 420Mscm) although construction has not commenced yet. The project now needs to... Read more
-
View advice to Linda Rogers
Caller was concerned that she had been given little time to respond to a consultation request and that all four proposed substation locations for the onshore connection are unsuitable.
-
View advice to Robert Wynn & Sons Ltd
Mr West wrote to us to explore how best to engage with the consent process to ensure that energy proposals reflected the “Water Preferred Policy” for the movement of abnormal indivisible loads.
-
View advice to Forestry Commission Wales
I am working developing a framework for assessing the Community Benefit/Trust Fund commitments made by developers regarding wind farm developments on the Assembly Woodland Estate. I am interested in... Read more
-
View advice to M.J.C.A.
Mr Mordue telephoned the IPC to enquire whether or not the advice on format and presentation of documents in Advice Note 6 applied to enviromental statements.
-
View advice to AECOM
Further to our conversation I have a client who wished to construct a anaerobic digestion plant for the production of bio-fuels. Therefore I was wondering if you could provide any advice on what... Read more
-
View advice to K Little
Registering an interested for several wind farm projects in Wales, from a letter from a member of public.
-
View advice to Keith Dalton
Is it possible for the IPC to provide a scoping opinion on a project where there are 3 potential sites?
-
View advice to Elizabeth Jones
What is included within a decision notice? More specifically, does the decision notice only provide planning permission for a proposal or does it include consent to other regimes.
-
View advice to Coventry City Council
Coventry City Council explained the background to the Coventry to Nuneaton Rail Improvements Project, with particular reference to the proposed new stations at Coventry Ricoh Arena and Bermuda Park,... Read more
-
View advice to Clive Hughes
Request for details on fees and the pre-application process
-
View advice to Olympics and Thames Gateway UDC
What is the status and role of urban development corporations in the context of s42 of the Planning Act 2008. Urban Development Corporations (and there are 2 in the Thames Gateway) have planning... Read more
-
View advice to Augean
Augean wrote to the IPC to notify us of their intention to submit a development consent order application for development of a hazardous waste magement facilty near Peterborough.
-
View advice to Arup
We are giving some strategic advice to a client regarding a DCO to be submitted to the IPC. We are trying to determine if it is possible to integrate particular ‘non-planning’ consents and permits... Read more
-
View advice to Winford Emanual
Does an application submitted to the IPC which is located in Wales need to be submitted in English?
-
View advice to Cognisant Research
To whom it may concern, I understand that the 2008 Planning Act requires the undertaking of public consultation with people living in the vicinity of proposed works in advance of any Development... Read more
-
View advice to RWE npower
Consent from the LPA is required under these regulations for the removal of hedgerows unless the work falls within an exempt category. Normally, our work falls under the exemption 6(e) 'Permitted... Read more
-
View advice to Carmarthenshire Council
Who enforces requirements? Who discharges requirements? When will the IPC be merged with PINs?
-
View meeting with National Grid
From National Grid (NG) perspective: establishing feedback on NG’s consultation processes; and ongoing engagement between NG and IPC. From IPC’s perspective: setting out the processes and rules... Read more
-
View advice to Chamber of Shipping
It has come to our attention that we have been missed from your Statutory and Non statutory list for projects that have been submitted for Offshore renewable development. We would be grateful if this... Read more
-
View advice to Tim West
I am keen to understand the process that is gone though prior to planning approval being granted for major power generation projects i.e. those over 50MW. I am aware that this was previously... Read more
-
View meeting with EveloGen
Introductory Meeting with Evelogen and URS to discuss the pre-application process
-
View advice to Friston Parish Council
Queries regarding the Scoping Opinion consultation undertaken by the IPC. 1) Does the IPC consult all Parish Councils in the area? 2) Is this the main consultation undertaken for the proposal?
-
View advice to Tim Maddison
Mr Maddison wished to express concern about the consultation exercise undertaken by Covanta in relation to the proposed Energy from Waste plant in Merthyr Tydfil.
-
View advice to Burges Salmon
Requested clarification on the use of S132 of the Planning Act 2008 (Commons, open spaces etc: Compulsory acquisition of rights over land) in relation to development proposals in Wales.
-
View advice to Charles Hawkins
Would a truck stop network be considered a Nationally Significant Infrastructure Project?
-
View advice to SKM Enviros
Section 16 of the Planning Act 2008 states when an electric line should be considered as an NSIP. However, I assume that this refers to permanent lines? There is often the need for ‘temporary’... Read more
-
View advice to Sebastian Head
If an application was made in March 2010 (for a project that would now be an NSIP) for planning permission and the application is refused by the local planning authority, can it still be appealed... Read more
-
View advice to DLA Piper
Query regarding APFP Regulation 5(3) particularly in connection with Reg 5(2)(l) and (m). In certain cases it was felt inappropriate to provide plans of A0 size at 1:2500 scale, where the... Read more
-
View meeting with National Grid
From National Grid (NG) perspective: establishing feedback on NG’s consultation processes; and ongoing engagement between NG and IPC. From IPC’s perspective: setting out the processes and rules... Read more
-
View meeting with GE ENERGY
IPC to provide an overview of its strategic approach as well as the operations for dealing with Nationally Significant Infrastructure Projects (NSIPs).
-
View advice to Member of the Public
Caller had been told that some land he was looking to purchase was to be used for housing, the application for which will be made to the IPC. Can we confirm that this is so?
-
View advice to EDF
Please see questions asked in the advice given column.
-
View advice to Brecon Beacons National Park Aut
Please can you clarify, with respect to the six steps, what is the expected involvement in responding to the IPC and promoter for a statutory consultee such as Brecon Beacons National Park?
-
View advice to Mary Halt
Call regarding a proposed project and the communication with the IPC.
-
View advice to Public Health Wales
Mr Brunt had received a consultation request from Covanta and wanted clarification as to where in the process the application is.
-
View advice to Member of the Public
How many turbines does a proposal need to have for the application to be made to the IPC?
-
View advice to Health Protection Agency
As part of Schedule 1 of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 the HPA are a statutory consultee for all proposed applications likely to involve... Read more
-
View meeting with Environment Agency
To explore the relationship between environmental permitting and development consent orders.
-
View meeting with StopHinkley etc.
Gain a broader understanding of the new planning regime under the Planning Act 2008 and how NGO’s can engage in the process.
-
View advice to Oswald Desybel
What is the future of the IPC?
-
View advice to Henry Le Brecht
I have recently been having conversations with Gary Mohamed of DECC regarding Determination Assessments associated with high pressure gas pipelines. Specifically in this case we are assessing the... Read more
-
View advice to Did not wish to disclose Did not wish to disclose
Caller requested at what stage Merthyr Tydfil was within the new planning process and how/when to get involved. What are the procedural rules to be upheld during a hearing?
-
View advice to ARUP
Dear Sir/Madam, I have a question regarding at what point the relevant Local Authority recieves a copy of the DCO application material. I presume it is sent at the point of successful registration... Read more
-
View advice to Eversheds
Sir/Madam Eversheds are advising in relation to a proposed wind farm project in Wales. It is considered that the project is a nationally significant infrastructure project for the purposes of the... Read more
-
View advice to SSE
When publishing the Statement of Community Consultation (SoCC), what should be included? Can a summary be published?
-
View advice to Christopher Tolmie
Caller enquired whether the IPC is involved with the High Speed Railway 2 (HS2) project given the nature of its size?
-
View meeting with JNCC, WAG, CCW
To set out key responsibilities with regards to off shore NSIP developments.
-
View advice to Freshfields
If an application that was previously approved under the old planning regime was amended, would a new application need to be made to the IPC?
-
View advice to David Croft
As the National Policy Statements (NPSs) are currently in draft, what weight do they hold in the decision making process?
-
View advice to Health Protection Agency
Eirain from HPA has received scoping opinion correspondence regarding Nant-y-Moch from two Local Health Boards. HPA would like to comment on the proposal but had missed the deadline. HPA... Read more
-
View advice to Scottish Rural Property & Busine
The SRPBA represents landowners in Scotland (equivalent to the CLA in England and Wales). I am trying to ascertain the potential impact of the IPC in terms of infrastructure projects (specifically gas... Read more
-
View advice to Chris Whitehead
We have recently been employed by a wind farm developer to write their Statement of Community Consultation for an off-shore wind farm development. Is there any specific guidance for off-shore... Read more
-
View meeting with MGT Power North Tyneside Council
A meeting note taken on 11th May 2010 describing discussions with MGT Power and North Tyneside Council regarding the proposed biomass plant in North Tyneside, and the IPC processes.
-
View advice to Stanley Gono
Could you please advise whether or not Sections 36 & 37 of the Electricity Act 1989 has been disapplied by section 33(1) of the Planning Act 2008? Please explain the primary legislation and how... Read more
-
View advice to Eversheds LLP
We have the following enquiry and would appreciate your views. Regulation 5(2) of the 2009 Regulations specifies at subparagraphs (i) to (n) individual plans which are required to accompany the... Read more