Mae'r rhestr isod yn cynnwys cofnod o gyngor a roddwyd gennym ar gyfer y prosiect hwn.
Chwiliwch yn ôl geiriau allweddol neu enw'r unigolyn y rhoddwyd y cyngor iddo.
-
Please see letter dated 17 July 2020 attached.
-
Query from Paul Gripton by email on 24 September 2018:
Please find attached a letter detailing the issues and advice sought, mentioned in our previous phone conversation. It is lengthy but evidence...
Darllen mwy
-
Project update meeting
-
Project update meeting in relation to the proposed material change to the DCO
-
Hi thank you for the response, for clarity:-
The consultees to non material changes do not include interested or registered persons from the full formal process?
Who are the required consultees?
...
Darllen mwy
-
Good afternoon, i note on your website a number of ‘non material changes’ have both been advertised and confirmed, i was part of the original inspection, registering and speaking.
I am interested t...
Darllen mwy
-
Meeting regarding proposed non-material change application
-
Please see attached letter from EDF Energy
-
Meeting to update on project progress and to discuss proposed applications to make changes to the DCO
-
see attached letter
-
Meeting between EDF and the Planning Inspectorate regarding lessons learnt on the administration of the Hinkley Point C application.
-
Assuming EDF is given planning consent for Hinkley PointC, could it delay the start of the project for a period of time, possibly years?
-
The Equality and Human Rights Commission requested if they could be removed from the Hinkley Point C mailing lists as information regarding planning applications does not fit with the type of work car...
Darllen mwy
-
Mr Gripton called to clarify when he could submit comments into the Hinkley examination process on the issues discussed at the Issue Specific Hearing on 26-27 June 2012.
-
Avon & Somerset Police have sought clarification as to the matters to be covered at the Issue Specific Hearing on 26 June 2012 to which they are invited.
-
EDF sought clarification regarding the exact nature of the six sites highlighted in paragraph 1.8 of the Hinkley Panel?s Further Written Questions (extract shown below).
Question for the Applicant
...
Darllen mwy
-
Sedgemoor District Council, Somerset County Council and West Somerset District Council asked for clarification about the Panel?s intentions concerning the invitation to Interested Parties in the Proce...
Darllen mwy
-
Mr Rigby queried the application process for Hinkley Point C and when he had the opportunity to make objections to the scheme.
-
1) At what point would it be sensible for any revised DCO to be submitted to the examination to give parties an opportunity to comment on any revised drafting of requirements or DCO provisions?
2) ...
Darllen mwy
-
It is unfortunate that the IPC did not make it clear to parish or town councils that there was a possibility to meet with them, separate from the public meetings, in order to discuss procedural matter...
Darllen mwy
-
Would it assist the host parish of Stogursey and the hamlets to be similarly recognised as a ?Principle Issue? if we were also permitted to send a delegation to lobby the IPC in person?
-
I?m still rather mystified as to how the Commissioners actually reached the conclusion that Combwich should be treated as a Principle issue. As the district councils have not yet submitted their Local...
Darllen mwy
-
Ms Meskell called on behalf of Royal and Sun Alliance to ask how they could identify an land intrests over which it the applicant was seeking Compulsory Aquisition powers.
-
Query whether their relevant representations would be considered during examination proceedings and whether attendance at the Preliminary Meeting would be required to allow the opportunity to make an ...
Darllen mwy
-
Query regarding status as an interested party and as an affected person for the Hinkley Point C application.
-
Query regarding correspondence received by household in connection with the Hibkley Point C application.
-
The lack of a scheduled site visit to the Stogursey area was queried in relation to the Hinkley Point C application.
-
Dear Sir
I note your intention to have site visits in September.
I would respectfully request that these visits are carried out prior to the preparatory works of which EDF have already secured ...
Darllen mwy
-
Example Query
I think it would be appropriate if a site visit were made prior to commencement of the main preliminary works in order to put the site in perspective with regard to the surrounding ha...
Darllen mwy
-
IPC Ref EN010001
THE IPC's letter regarding the above makes no mention of Shurton, yet this is the community most affected by the development. Actually, replace affected with devasted.
This all...
Darllen mwy
-
Dear Mr Phillipson
Further to your letter of 10.2.12, I can confirm the following:
1) Stogursey Parish Council will be attending the preliminary meeting on 21.3.12
2) Stogursey Parish Council w...
Darllen mwy
-
Lesley Flash called during a West Hinkley Action Group meeting to ask the following questions:
-
Councillor Bannister sent an enquiry whether possible amendments to the Hinkley Point C application would be an infringement of the IPC process and how this could be reconciled with the need for publi...
Darllen mwy
-
Can you please advise me what are the legal obligations imposed upon an applicant, with regard to carrying out public consultations, the action they need to take in response to the consultations and ...
Darllen mwy
-
I note from the IPC web page that the preliminary meeting will be held in public and also that interested parties will receive an invite.
I would like to request that myself and Steve Smith (interi...
Darllen mwy
-
I submitted my representation for HINK-00178 online yesterday. Ref no given to me 10014520. When am I likely to receive an email with a copy of my representation please?
And if I don't, what should ...
Darllen mwy
-
To discuss procedural arrangements for the Preliminary Meeting and the Examination between IPC and EDF.
-
Can I still register as an interested party? I may wish to attend the Preliminary Meeting and would like to keep up-to-date with the Hinkley Point C New Nuclear Power Station project. How can I do thi...
Darllen mwy
-
I have submitted a relevant representation form. I am not an interested party in a legal sense but I am interested in how this application is examined. How can I ensure I am kept up to date with the p...
Darllen mwy
-
Mr Clubb requested that the relevant representation form for the Hinkley Point C project in Somerset was made available in Welsh. He commented that, in his opinion, not to provide it in Welsh would co...
Darllen mwy
-
Can you please send me a registration form as attachment which I can print off for several elderly people in my village who don't have internet access?
-
I have three times tried to register with you, on behalf of the Governor's of Cannington CofE School
and three times your system has rejected the application. What do we have to do to register with y...
Darllen mwy
-
Following an EDF roadshow, Mr Bullen wished to enhance his summary on the community impacts of the project and speak at any open floor hearing. He enquired to the best method for updating the infomati...
Darllen mwy
-
The email author enquired where they could read or see a list of the registrations received to date for Hinkley Point C application?
-
Does the MMO have to use the IPC's online relevant representation form?
-
Does the Environment Agency (EA) have to use the IPC's online relevant representation form? What format can EA use to submit its relevant representation?
-
When should electronic copies of the application be made available to the public?
-
Discussion of outreach and Preliminary Meeting arrangements with local authorities and EDF.
-
Comments were supplied regarding EDF's pre-application consultation and scheme for Hinkley Point C New Nuclear Power Station.
-
Comments were supplied regarding EDF's pre-application consultation and scheme for Hinkley Point C New Nuclear Power Station.
-
Correspondence dated ?November 2011? has been received from ?The Power Trust? without an address for return correspondence. The correspondence is titled ?Advance Briefing for IPC Commissioners and Ass...
Darllen mwy
-
I wish to register my Parish Councils' interest in this project
-
Comments were supplied regarding the scheme and EDF's consultation. It was also queried why the IPC was to consult Exmoor National Park Authority, but not Cannington Parish Council.
-
I must say that I find it entirely unsatisfactory that you are unable to inform individuals when the registration process opens, and that one is required to scan all the national and local papers on a...
Darllen mwy
-
Query regarding the Royal Mail's status as a statutory consultee and the process relating to making an objection to the IPC regarding the Hinkley Point C scheme.
-
Further to your joint letter from SCC, SDC and WSC dated 5th October regarding the above we would like to register our interest and be kept informed of developments. I have tried to register online on...
Darllen mwy
-
I wish to register and make representations in regard to the application for development at Hinkley Point. I appreciate that I cannot do this until the IPC has accepted the application but (assuming t...
Darllen mwy
-
It appears from the webpage below that the Hinkley C application has been accepted by the IPC for consideration. I would like to please be kept informed of the date from which one can register to make...
Darllen mwy
-
The caller queried their inability to submit a relevant representation for the Hinkley Point C application via the IPC website.
-
I have been asked by many residents who are not on line to seek clarification that, now that EDF have submitted their application and, if accepted by the IPC in the 28 day period, is it during this 2...
Darllen mwy
-
Can you provide me with information on how to register Durleigh Parish Council's interest in this project?
-
Ms Valerie Bannister of Cannington Parish Council telephoned; she asked whether the Parish Council and other interested parties could write directly to the IPC with regards to the adequacy of consulta...
Darllen mwy
-
Advice sought regarding EIA regulation 24 Transboundary Impacts
-
The Council would like to have a full copy of the application at the same time as it is submitted to the IPC, to enable it to make an adequacy statement.
What would happen if the Council was not ab...
Darllen mwy
-
I would like to register to be able to put my views when an application for Hinkley Point C is submitted or if it has already been submitted.
-
Mr Silk called to ask which part or parts of the book of reference a party with a very specific intrest in land would best be included in.
-
Are developers required to submit a full copy of the application to a local authority at the same time as it is submitted to the IPC?
Is it appropriate for local authorities to publish the applicat...
Darllen mwy
-
Will the time we can register/write to the IPC regarding Hinkley Point C be published in local newspapers for those without computers?
-
Mr Ensor telephoned the IPC to ask how representatives of Parish Councils can make relevant representations on behalf of their organisations.
Our response was by telephone.
-
Mr Gillam asked to be kept advised of the submission date of the forthcoming application for a generating station at Hinkley Point, and the period for making relevant representations.
-
DCW Johnson commented on concerns about the development of Combwich Wharf during the proposed Hinkley Point C project.
-
Meeting held to discuss the proposed Hinkley Point 'C' project
-
meeting to provide advice about the process and making a representation.
-
Mr Adieze, a legal adviser at Avon and Somerset Police,(ASP) called to ask whether any submissions on the detail of planning obligations accompanying any application for a generating station at Hinkle...
Darllen mwy
-
Meeting with Somerset County Council, West Somerset District Council and sedgemoor District Council to disucss the proposed Hinkley Point 'C' project
-
The IPC chaired a tripartate meeting between various stakeholders to discuss the forthcoming appilcation for a generating station at Hinkley Point in Somerset.
-
1. Would the IPC require an application for a direction deeming Hazardous Substances Consent (HSC) to have been granted to be made at the same time as submission of the application for development con...
Darllen mwy
-
The IPC case team met a team from EDF Energy to discuss the forthcoming application at Hinkley Point in Somerset, and particularly the consultation being undertaken regarding the junction 24 site and...
Darllen mwy
-
Mr Steve Crago, of Avon and Somerset Police, made an enquiry by telephone with regard to drafting s106 obligations under the Planning Act 2008 regime; relating to the Hinkley C generating station prop...
Darllen mwy
-
The IPC observed a meeting held by EDF Energy to present a summary of progress with the Habitats Regulations Assessment for the proposed Hinkley C Nuclear Power Station, for discussion with Natural En...
Darllen mwy
-
To discuss the role of the Infrastructure Planning Commission and opportunities for engagement with the application process under the 2008 Act, with particular reference to the forthcoming application...
Darllen mwy
-
Meeting between EDF, IPC, Sedgemoor DC, West Somerset DC, Somerset CC, Environment Agency and Highways Agency to discuss emerging issues arising out of the proposed application for Hinkley C.
-
Meeting with EDF Energy, West Somerset District Council, Sedgemoor District Council, Somerset County Council, Environment Agency and Highways Agency to discuss the proposed Hinkley Point 'C' project.
-
Meeting to discuss the proposed Hinkley Point 'C' scheme
-
Pre-Application meeting between EDF Energy, and their legal advisers, and the IPC case team to discuss progress on the Hinkley C generating station project, preliminary works applications and forthco...
Darllen mwy
-
In relation to http://infrastructure.independent.gov.uk/projects/south-west/hinkley-point-c-new-nuclear-power-station/
I have recently written to the developer questionning the adequacy of its curren...
Darllen mwy
-
Dr Chris Eaglen submitted three representations on the proposed Hinkley C Generating Station in West Somerset.
http://infrastructure.independent.gov.uk/wp-content/uploads/2011/03/110219_EN010001_Ch...
Darllen mwy
-
Re: http://infrastructure.independent.gov.uk/projects/south-west/hinkley-point-c-new-nuclear-power-station/
According to your website:
"The application is expected to be submitted to the IPC Winte...
Darllen mwy
-
Whether the proposed temporary accommodation campuses can lawfully be included within the Hinkley
Point C application as associated development under s115(2) of the Planning Act 2008 (the Act) .
-
Meeting with Pinsent Masons to discuss associated development.
-
The enquirer requested that we inform EDF Energy and central government that a new road is vital (at Dunball), before any permission is granted for the proposed new build at Hinkley Point.
-
The IPC case team met with delegates from Stop Hinkley Group on 1 December 2010 to discuss the IPC application process and how to participate, with referance to the forthcoming application at Hinkley ...
Darllen mwy
-
Crispin Aubery, on behalf of Stop Hinkley Group, wrote to the IPC with questions in relation to the Hinkley Point C proposal.
Firstly, he wanted to know the IPC's relationship to the current appli...
Darllen mwy
-
The IPC case team chaired a tripartate meeting of stakeholders for the proposed Hinkley C power station on 11 November 2010, including the Highways Agency, the Enviroment Agency, West Somerset DC, Sed...
Darllen mwy
-
Following any application for the proposed Hinkley Point C development consent order and following the examination, which minister makes the final decision whether or not the DCO is issued? If not the...
Darllen mwy
-
Dear Sir or Madam
I wish to draw your most urgent attention to the following facts:
The hamlets of Shurton, Burton and Wick are extremely close to the boundary of the proposed development.
Ed...
Darllen mwy
-
As you are probably aware by now, it's not the building of a new power station that the people of Somerset are trying to stop.
EDF are planning to use existing roads for lorries, cars and coaches....
Darllen mwy
-
See Attached letter
-
As requested at a recent meeting with the Stogursey Parish Council I forward to you a copy of my comments to EdF on their Stage 2 Consultation document for your information.
-
Mrs Laird wrote to us regarding the merits of the proposed development, and the impacts she feels it will have upon the village of Combwich.